MoDOT contract 250418-H02 bid tabulation
J9P3835 - ROUTE 60 - CARTER, HOWELL, SHANNON COUNTIES. Let by Missouri DOT on April 18, 2025, Shannon, Southeast. 6 bids received; low bid $745,884 by Widel, Inc..
- Owner
- Missouri DOT
- Letting
- 18 APR 2025
- Pay items
- 20
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Widel, Inc. | $745,884 | Low |
| 2 | H.R. Quadri Contractors, LLC | $844,678 | +13% |
| 3 | West Plains Bridge & Grading, LLC | $1,060,000 | +42% |
| 4 | Mera Excavating, LLC | $1,288,057 | +73% |
| 5 | Courtney Construction, LLC dba Courtney Excavating & Construction | $1,313,425 | +76% |
| 6 | Putz Construction, LLC | $1,459,525 | +96% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Widel, Inc. | 2. H.R. Quadri Contractors, LLC | 3. West Plains Bridge & Grading, LLC | 4. Mera Excavating, LLC | 5. Courtney Construction, LLC dba Courtney Excavating & Construction | 6. Putz Construction, LLC |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Signet dbe reporting (1081000) | LS | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0020 | Linear grading class 1 (2071000) | STA | 42.90 | $425.00 | $500.00 | $515.00 | $489.57 | $524.41 | $1,850.00 |
| 0030 | Misc.modified linear grading, class 2 (2079909) | STA | 36.30 | $650.00 | $700.00 | $2,150.00 | $511.10 | $619.76 | $2,600.00 |
| 0040 | Misc.furnishing and placing rock ditch liner (6119910) | TON | 4,848.80 | $25.50 | $44.00 | $44.25 | $48.38 | $65.25 | $67.50 |
| 0050 | Misc.furnishing and placing type 2 rock blanket (6119910) | TON | 7,722.10 | $37.50 | $44.00 | $55.00 | $64.18 | $67.00 | $69.50 |
| 0060 | Truck mounted attenuator (TMA) (6123001) | LS | 1 | $7,000.00 | $12,000 | $15,000 | $26,408 | $45,236 | $25,000 |
| 0070 | Construction signs (6161005) | SF | 691 | $10.00 | $8.50 | $8.50 | $22.46 | $16.11 | $9.60 |
| 0080 | Channelizer (trim line) (6161025) | EACH | 125 | $22.50 | $20.00 | $20.00 | $114.44 | $62.61 | $28.80 |
| 0090 | Directional indicator barricade (6161033) | EACH | 40 | $107.50 | $95.00 | $95.00 | $365.29 | $203.09 | $102.00 |
| 0100 | Flashing arrow panel (6161040) | EACH | 2 | $1,175.00 | $1,000.00 | $1,000.00 | $4,023.90 | $1,785.00 | $3,360.00 |
| 0110 | Changeable message sign without communication interface, contractor furnished, contractor retained (6161098A) | EACH | 2 | $3,250.00 | $2,800.00 | $2,800.00 | $6,471.90 | $4,165.00 | $7,200.00 |
| 0120 | Mobilization (6181000) | LS | 1 | $35,000 | $82,429 | $84,897 | $187,035 | $132,797 | $130,000 |
| 0130 | Additional mobilization for seeding (6181020) | EACH | 15 | $600.00 | $600.00 | $600.00 | $600.00 | $600.00 | $600.00 |
| 0140 | Permanent erosion control geotextile (6240103A) | SY | 18,424 | $2.40 | $2.00 | $2.75 | $2.18 | $3.48 | $3.00 |
| 0150 | Seeding - cool season grasses (8051000A) | ACRE | 0.70 | $10,688 | $2,000.00 | $9,500.00 | $12,253 | $5,385.40 | $4,850.00 |
| 0160 | Seeding - warm season grasses (8052000A) | ACRE | 6.60 | $4,100.00 | $2,000.00 | $3,650.00 | $4,799.10 | $7,289.44 | $5,200.00 |
| 0170 | Misc.fiber reinforced matrix (8059919) | ACRE | 7.30 | $6,700.00 | $4,000.00 | $5,950.00 | $7,645.45 | $3,733.23 | $6,250.00 |
| 0180 | Misc.soil biostimulant (8059919) | ACRE | 6.60 | $9,700.00 | $4,000.00 | $8,595.00 | $10,852 | $1,835.62 | $6,140.00 |
| 0190 | Rock ditch check (8061005) | LF | 984 | $23.00 | $12.00 | $9.00 | $16.91 | $43.52 | $40.00 |
| 0200 | Sediment removal (8061016) | CY | 82 | $20.00 | $20.00 | $6.00 | $60.40 | $115.42 | $35.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of April 18, 2025. Compiled by Mirage Metrics.