MoDOT contract 260515-A02 bid tabulation

JNW0165-ROUTE 71-NODAWAY COUNTY. Let by Missouri DOT on May 15, 2026, Nodaway, Northwest. 1 bid received; low bid $3,067,646 by Leavenworth Excavating & Equipment Company, Inc..

Owner
Missouri DOT
Letting
15 MAY 2026
Pay items
53
Data through
16 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Leavenworth Excavating & Equipment Company, Inc.$3,067,646Low
MoDOT contract 260515-A02: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Leavenworth Excavating & Equipment Company, Inc.
0010Clearing and grubbing (2013000)ACRE3$4,900.00
0020Removal of improvements (2022010)LS1$37,705
0030Class A excavation (2031000)CY1,969$50.00
0040Unclassified excavation (2035000)CY3,143$39.00
0050Embankment in place (2035500)CY3,636$53.00
0060Compacting embankment (2036000)CY2,200$5.00
0070Class 3 excavation (2063000)CY6$50.00
0080Culvert cleanout (2063500)EACH4$2,200.00
0090Type 5 aggregate for base (6 in. thick) (3040506)SY21,065$24.00
0100Paved approach, 8 in. (6085008)SY811.30$120.00
0110Rock lining (6097000)CY4$295.00
0120Construction signs (6161005)SF499$8.00
0130Channelizer (trim-line) (6161025)EACH147$25.00
0140Type 3 moveable barricade (6161030)EACH4$150.00
0150Direction indicator barricade (6161033)EACH28$50.00
0160Flashing arrow panel (6161040)EACH2$1,000.00
0170Mobilization (6181000)LS1$205,160
0180Additional mobilization for seeding (6181020)EACH2$600.00
0190Preformed thermoplastic pavement marking, left/right arrow (6200021)EACH6$350.00
02006 in. white class 2 pavement marking paint (25-mil, type L beads) (6205902B)LF6,175$0.26
02106 in. yellow class 2 pavement marking paint (25-mil, type L beads) (6205903B)LF7,555$0.26
022012 in. white class 2 pavement marking paint (25-mil, type L beads) (6205906B)LF770$1.00
0230Pavement marking removal (6207001)LF4,117$0.10
0240Contractor furnished surveying and staking (6274000)LS1$14,940
025015 in. pipe group B (7250315A)LF66$120.00
026018 in. pipe group B (7250318A)LF137$125.00
027024 in. pipe group B (7250324A)LF82$155.00
028015 in. or allowed substitute group B flared end section (7320015A)EACH2$690.00
029018 in. or allowed substitute group B flared end section (7320018A)EACH2$740.00
030018 in. or allowed substitute safety slope end section (7321014A)EACH2$1,985.00
031024 in. or allowed substitute safety slope end section (7321016A)EACH2$2,835.00
0320Mulching (8025006)ACRE3.40$1,700.00
0330Seeding - cool season grasses (8051000A)ACRE3.40$2,070.00
0340Alternate ditch check (8061006)LF1,180$10.60
0350Sediment removal (8061016)CY124$20.00
0360Silt fence (8061019)LF530$4.00
03909 inches, asphaltic concrete pavement SP125C (4030402)SY20,253$70.00
0400Bituminous shoulder rumble strip (6261000A)STA100.90$55.00
0410Lighting pole, 45 FT. or 13.5 M, type at design 1 (9011060)EACH2$4,237.00
0420Bracket arm, 15 FT. or 4.6 M (9011115)EACH2$1,138.00
0430Luminaire, LED-B (9011312)EACH2$562.00
0440Base mounted control station 240 volt - 4 circuit (9012230)EACH1$8,500.00
0450Conduit, 2 in. rigid, in trench (9013002)LF25$0.01
0460Conduit, 4 in. rigid, pushed (9014004)LF491$30.00
0470Trenching type I (9015010)LF5,145$9.00
0480Pull box, preformed class 1 (9016110)EACH14$850.00
0490Cable, 10 AWG 1 conductor, pole and bracket (9017110)LF240$1.25
0500Cable-conduit, 1 in., 2 conductors and 1 bare neutral, 4 AWG (9017402)LF5,710$13.14
0510Pole foundation (45 FT. or 13.5 M mounting height) (9018245)EACH2$3,125.00
0520Power supply assembly, type 1, 240/120 volt service, lighting only (9018610)EACH1$7,000.00
0530Concrete footings, embedded (9031010)CY9.40$1,400.00
0540Pipe posts (9031220)LB3,950$7.00
0550SH-flat sheet (9035004A)SF516$22.00
MoDOT contract 260515-A02: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

Every contract let that day: MoDOT letting of May 15, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy