MoDOT contract 261016-A02 bid tabulation

JNWM0144 - ROUTE 29 - ANDREW COUNTY. Let by Missouri DOT on October 16, 2026, Andrew, Northwest. 3 bids received; low bid $197,400 by Tri-Star Hauling LLC.

Owner
Missouri DOT
Letting
16 OCT 2026
Pay items
4
Data through
16 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Tri-Star Hauling LLC$197,400Low
2Gene Haile Excavating, Inc.$364,050+84%
3Louis-Company, LLC$740,853+275%
MoDOT contract 261016-A02: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Tri-Star Hauling LLC2. Gene Haile Excavating, Inc.3. Louis-Company, LLC
0010Misc.misc. {brush cutting and stump painting} (2019901)LS1$56,500$140,000$442,707
0020Misc.stump grinding and tree and brush removal (2019919)ACRE32.90$3,450.00$5,500.00$2,748.44
0030Misc.temporary traffic control (6169901)LS1$20,500$10,000$56,627
0040Mobilization (6181000)LS1$6,895.00$33,100$151,095
MoDOT contract 261016-A02: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.

Every contract let that day: MoDOT letting of October 16, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy