MoDOT contract 261016-D07 bid tabulation
JCD0230, JCD0260-VARIOUS ROUTES-VARIOUS COUNTIES. Let by Missouri DOT on October 16, 2026, Various, Central. 7 bids received; low bid $1,122,268 by Southern Coatings of Tarpon Springs, LLC.
- Owner
- Missouri DOT
- Letting
- 16 OCT 2026
- Pay items
- 36
- Data through
- 16 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Southern Coatings of Tarpon Springs, LLC | $1,122,268 | Low |
| 2 | Omega Coatings & Construction, LLC | $1,295,670 | +15% |
| 3 | Kalymnos Bridge Painting, LLC | $1,841,786 | +64% |
| 4 | Southern Road & Bridge, LLC | $2,083,625 | +86% |
| 5 | Olympus Painting Contractors, Inc. | $2,087,209 | +86% |
| 6 | Thomas Industrial Coatings, Inc. | $2,379,292 | +112% |
| 7 | Steel City Contractors, LLC | $2,413,770 | +115% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Southern Coatings of Tarpon Springs, LLC | 2. Omega Coatings & Construction, LLC | 3. Kalymnos Bridge Painting, LLC | 4. Southern Road & Bridge, LLC | 5. Olympus Painting Contractors, Inc. | 6. Thomas Industrial Coatings, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0010 | Changeable message sign with communication interface, contractor furnished retained (6161099) | EACH | 2 | $2,200.00 | $3,000.00 | $5,220.00 | $2,400.00 | $5,400.00 | $3,200.00 |
| 0020 | Temporary long-term rumble strips (6162002) | EACH | 8 | $1,600.00 | $2,000.00 | $2,320.00 | $1,850.00 | $3,000.00 | $1,200.00 |
| 0030 | Misc.lump sum temporary traffic control (6169901) | LS | 1 | $23,612 | $22,000 | $24,677 | $26,000 | $25,527 | $27,690 |
| 0040 | Misc.work zone intelligent transportation system (6169901) | LS | 1 | $55,000 | $41,000 | $46,980 | $60,000 | $48,600 | $147,000 |
| 0050 | Misc.detectable pedestrian channelizing barricade (6169902) | EACH | 2 | $170.00 | $110.00 | $121.80 | $195.00 | $126.00 | $250.00 |
| 0060 | Mobilization (6181000) | LS | 1 | $37,500 | $50,000 | $110,000 | $44,000 | $114,500 | $170,000 |
| 0070 | 6 in. white class 2 pavement marking paint (25-mil, type L beads) (6205902B) | LF | 1,600 | $1.00 | $1.00 | $0.87 | $1.00 | $0.90 | $7.75 |
| 0080 | Pavement marking removal (6207001) | LF | 14,530 | $0.85 | $3.00 | $3.48 | $1.00 | $3.60 | $1.25 |
| 0090 | 4 in temporary pavement marking paint (6208076) | LF | 12,930 | $0.50 | $3.00 | $3.48 | $0.65 | $3.60 | $1.50 |
| 0100 | Surface preparation for recoating structural steel (7125200) | SF | 19,100 | $5.50 | $12.67 | $10.00 | $10.00 | $12.00 | $33.00 |
| 0110 | Field application of inorganic zinc primer (7125210) | SF | 19,100 | $3.50 | $6.00 | $6.00 | $8.00 | $3.00 | $3.00 |
| 0120 | Finished field coat (system L) (7125397) | SF | 19,100 | $3.50 | $2.10 | $6.00 | $6.00 | $5.00 | $2.00 |
| 0130 | Surface preparation for recoating structural steel (7125200) | SF | 5,800 | $8.00 | $12.94 | $10.00 | $15.00 | $17.00 | $33.00 |
| 0140 | Field application of inorganic zinc primer (7125210) | SF | 5,800 | $6.00 | $6.45 | $6.00 | $5.00 | $3.00 | $3.00 |
| 0150 | Finished field coat (system L) (7125397) | SF | 5,800 | $6.00 | $2.10 | $6.00 | $7.00 | $6.00 | $2.00 |
| 0160 | Surface preparation for recoating structural steel (7125200) | SF | 2,700 | $10.00 | $12.65 | $15.00 | $25.00 | $40.00 | $33.00 |
| 0170 | Field application of inorganic zinc primer (7125210) | SF | 2,700 | $8.00 | $6.30 | $10.00 | $5.00 | $7.00 | $3.00 |
| 0180 | Finished field coat (system L) (7125397) | SF | 2,700 | $8.00 | $2.10 | $10.00 | $7.00 | $12.00 | $2.00 |
| 0190 | Surface preparation for recoating structural steel (7125200) | SF | 8,200 | $8.00 | $12.68 | $15.00 | $25.00 | $15.00 | $33.00 |
| 0200 | Field application of inorganic zinc primer (7125210) | SF | 8,200 | $6.00 | $6.30 | $10.00 | $9.00 | $3.00 | $3.00 |
| 0210 | Finished field coat (system L) (7125397) | SF | 8,200 | $6.00 | $2.10 | $10.00 | $9.00 | $6.00 | $2.00 |
| 0220 | Surface preparation for recoating structural steel (7125200) | SF | 2,900 | $10.00 | $12.62 | $15.00 | $25.00 | $40.00 | $33.00 |
| 0230 | Field application of inorganic zinc primer (7125210) | SF | 2,900 | $8.00 | $6.30 | $10.00 | $10.00 | $7.00 | $3.00 |
| 0240 | Finished field coat (system L) (7125397) | SF | 2,900 | $8.00 | $2.10 | $10.00 | $10.00 | $12.00 | $2.00 |
| 0250 | Changeable message sign without communication interface, contractor furnished retained (6161098A) | EACH | 2 | $2,200.00 | $3,000.00 | $3,480.00 | $2,500.00 | $3,600.00 | $3,200.00 |
| 0260 | Misc.temporary traffic control (6169901) | LS | 1 | $2,500.00 | $1,500.00 | $1,672.72 | $3,000.00 | $1,734.00 | $1,444.00 |
| 0270 | Mobilization (6181000) | LS | 1 | $50,000 | $10,000 | $85,000 | $200,000 | $57,500 | $45,100 |
| 0280 | Surface preparation for recoating structural steel (7125200) | SF | 3,700 | $10.00 | $12.68 | $15.00 | $25.00 | $38.00 | $33.00 |
| 0290 | Field application of inorganic zinc primer (7125210) | SF | 3,700 | $8.00 | $6.45 | $10.00 | $9.00 | $7.00 | $3.00 |
| 0300 | Finished field coat (system L) (7125397) | SF | 3,700 | $8.00 | $2.10 | $10.00 | $9.00 | $12.00 | $2.00 |
| 0310 | Surface preparation for recoating structural steel (7125200) | SF | 3,700 | $7.50 | $12.68 | $15.00 | $25.00 | $38.00 | $33.00 |
| 0320 | Field application of inorganic zinc primer (7125210) | SF | 3,700 | $5.00 | $6.45 | $10.00 | $9.00 | $7.00 | $3.00 |
| 0330 | Finished field coat (system L) (7125397) | SF | 3,700 | $5.00 | $2.10 | $10.00 | $9.00 | $12.00 | $2.00 |
| 0340 | Surface preparation for recoating structural steel (7125200) | SF | 4,300 | $8.00 | $12.55 | $15.00 | $25.00 | $35.00 | $33.00 |
| 0350 | Field application of inorganic zinc primer (7125210) | SF | 4,300 | $6.00 | $6.25 | $10.00 | $9.00 | $5.00 | $3.00 |
| 0360 | Finished field coat (system L) (7125397) | SF | 4,300 | $6.00 | $2.10 | $10.00 | $9.00 | $10.00 | $2.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from MoDOT's tabulation for this contract. MoDOT letting tabulation PDFs (vendor ranking and bid tabulation), January 2020 to October 2026. About one bid in eight did not match its published total and is left out. Item codes from before mid 2021 are written in the current MoDOT format so one item groups across years.
Every contract let that day: MoDOT letting of October 16, 2026. Compiled by Mirage Metrics.