NJDOT contract 25449 bid tabulation
MTN Pavement Markings Contract, Central - 2025. Let by New Jersey DOT on February 4, 2025, Hunterdon, Mercer, Middlesex, Monmouth, Ocean,, C4. 4 bids received; low bid $811,840 by Dan Swayze & Son, Inc..
- Owner
- New Jersey DOT
- Letting
- 04 FEB 2025
- Pay items
- 28
- Data through
- 16 APR 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Dan Swayze & Son, Inc. | $811,840 | Low |
| 2 | Zone Striping, Inc. | $972,150 | +20% |
| 3 | Traffic Lines, Inc. | $1,087,250 | +34% |
| 4 | Denville Line Painting, Inc. | $1,345,125 | +66% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Dan Swayze & Son, Inc. | 2. Zone Striping, Inc. | 3. Traffic Lines, Inc. | 4. Denville Line Painting, Inc. |
|---|---|---|---|---|---|---|---|
| 0001 | Performance bond and payment bond (151006M) | DOL | 1 | $2,820.00 | $7,000.00 | $4,000.00 | $16,000 |
| 0002 | Pollution liability insurance (152015P) | DOL | 1 | $15,510 | $8,000.00 | $20,000 | $16,500 |
| 0003 | Mobilization (MMR004M) | U | 18 | $3,000.00 | $3,000.00 | $3,000.00 | $3,000.00 |
| 0004 | Special mobilization (MMR005M) | U | 5 | $1,500.00 | $1,500.00 | $1,500.00 | $1,500.00 |
| 0005 | Emergency mobilization (MMR006M) | U | 1 | $2,500.00 | $2,500.00 | $2,500.00 | $2,500.00 |
| 0006 | Field office equipment (MMG018M) | DOL | 2,500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0007 | Oil only emergency spill kit, type 1 (158072M) | U | 1 | $940.00 | $1,000.00 | $2,000.00 | $3,000.00 |
| 0008 | Force account (109006M) | DOL | 30,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 0009 | Clearing site (MMR080M) | LF | 30,000 | $0.24 | $0.50 | $0.15 | $0.95 |
| 0010 | Traffic stripes, 4" (callouts less than 50,000 L.F.) (610003M) | LF | 50,000 | $1.18 | $1.50 | $2.00 | $2.95 |
| 0011 | Traffic stripes, 6" (callouts less than 50,000 L.F.) (610006M) | LF | 15,000 | $1.88 | $2.25 | $3.00 | $3.95 |
| 0012 | Traffic stripes, 8" (callouts less than 50,000 L.F.) (610007M) | LF | 9,500 | $2.82 | $4.00 | $4.00 | $4.95 |
| 0013 | Traffic stripes, 4" (callouts of 50,000 L.F. and greater) (610003M) | LF | 40,000 | $0.94 | $1.00 | $0.80 | $2.50 |
| 0014 | Traffic stripes, 6" (callouts of 50,000 L.F. and greater) (610006M) | LF | 20,000 | $1.88 | $2.00 | $1.20 | $3.50 |
| 0015 | Traffic stripes, 8" (callouts of 50,000 L.F. and greater) (610007M) | LF | 20,000 | $2.82 | $3.00 | $1.60 | $4.50 |
| 0016 | Traffic markings symbols (610060M) | SF | 9,000 | $18.80 | $20.00 | $30.00 | $21.00 |
| 0017 | Traffic marking lines, 4" (610013M) | LF | 10,000 | $1.88 | $2.00 | $3.00 | $4.00 |
| 0018 | Traffic marking lines, 8" (610014M) | LF | 15,000 | $3.76 | $7.50 | $6.00 | $7.50 |
| 0019 | Traffic marking lines, 12" (610016M) | LF | 2,000 | $5.64 | $10.00 | $9.00 | $15.00 |
| 0020 | Traffic marking lines, 24" (610017M) | LF | 10,000 | $14.57 | $18.00 | $22.00 | $20.00 |
| 0021 | RPM, mono-directional, white lens (610012M) | U | 25 | $36.00 | $100.00 | $40.00 | $100.00 |
| 0022 | RPM, mono-directional, amber lens (610018M) | U | 25 | $36.00 | $100.00 | $40.00 | $100.00 |
| 0023 | RPM, BI-directional, amber lens (610021M) | U | 25 | $36.00 | $100.00 | $40.00 | $100.00 |
| 0024 | Removal of RPM (610024M) | U | 150 | $20.00 | $1.00 | $20.00 | $50.00 |
| 0025 | Removal and replacement of RPM lens (610027M) | U | 250 | $15.00 | $25.00 | $20.00 | $45.00 |
| 0026 | Flexible delineator, ground mounted (610030M) | U | 50 | $100.00 | $90.00 | $150.00 | $400.00 |
| 0027 | Removal of traffic stripes (610036M) | LF | 4,500 | $1.41 | $1.00 | $2.00 | $3.85 |
| 0028 | Removal of traffic markings (610039M) | SF | 4,500 | $4.69 | $5.00 | $7.50 | $7.95 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NJDOT's tabulation for this contract. NJDOT bid tabulation PDFs linked from its 2018 to 2026 award pages (lettings from June 2017 to April 2026). Bids on redacted tabulations with scanned pages could not be read and are left out, as are bids that did not match their published total. Some maintenance contracts price an adjustment factor (unit PCT): published as is, not a unit price.
Every contract let that day: NJDOT letting of February 4, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way