NYSDOT contract D265352 bid tabulation
ADA Requirements Contract New York City. Let by New York State DOT on January 9, 2025, Bronx, Queens, Region 11. 4 bids received; low bid $1,216,073 by Roadwork Ahead Inc.
- Owner
- New York State DOT
- Letting
- 09 JAN 2025
- Pay items
- 60
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Roadwork Ahead Inc | $1,216,073 | Low |
| 2 | A-Tech Concrete Company Inc | $1,592,382 | +31% |
| 3 | Oliveira Contracting Inc | $1,998,446 | +64% |
| 4 | J Anthony Enterprises Inc | $2,344,801 | +93% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Roadwork Ahead Inc | 2. A-Tech Concrete Company Inc | 3. Oliveira Contracting Inc | 4. J Anthony Enterprises Inc |
|---|---|---|---|---|---|---|---|
| 1 | Unclassified Excavation and Disposal (203.02) | CY | 512 | $125.00 | $400.00 | $168.00 | $430.00 |
| 2 | Embankment In Place (203.03) | CY | 10 | $50.00 | $400.00 | $200.00 | $15.00 |
| 3 | (209.11010024) | 20 | $500.00 | $300.00 | $125.00 | $350.00 | |
| 4 | Subbase Course, Type 2 (304.12) | CY | 277 | $92.00 | $445.00 | $100.00 | $45.00 |
| 5 | (404.0001) | TON | 2 | $140.00 | $140.00 | $140.00 | $140.00 |
| 6 | (404.1281) | TON | 28 | $1,000.00 | $1,000.00 | $500.00 | $500.00 |
| 7 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 2,096 | $7.00 | $10.00 | $4.00 | $1.00 |
| 8 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 10 | $37.00 | $100.00 | $405.00 | $300.00 |
| 9 | PCC Foundation for Pavement, PEM Concrete (503.1013) | CY | 82 | $1,380.00 | $750.00 | $2,200.00 | $500.00 |
| 10 | (520.09000010) | 2,096 | $8.00 | $4.00 | $3.00 | $21.00 | |
| 11 | (520.51000006) | 51 | $8.00 | $7.00 | $10.00 | $10.00 | |
| 12 | (520.55000015) | 1,105 | $8.00 | $6.00 | $8.00 | $5.00 | |
| 13 | Box Beam Guide Railing (606.10) | LF | 35 | $380.00 | $80.00 | $85.00 | $150.00 |
| 14 | Box Beam End Piece (606.120101) | EACH | 1 | $10,000 | $1,400.00 | $1,400.00 | $1,500.00 |
| 15 | HPBO (Mod.) Corrugated Beam Guide Railing End Terminal (Energy-Absorbing) (606.27) | EACH | 1 | $15,000 | $7,000.00 | $5,000.00 | $10,000 |
| 16 | HPBO (Mod.) Corrugated Beam Guide Railing (606.2701) | LF | 34 | $200.00 | $70.00 | $75.00 | $150.00 |
| 17 | HPBO (Mod.) Corrugated Beam Guide Railing (Shop Curved) (606.270101) | LF | 7 | $200.00 | $200.00 | $160.00 | $180.00 |
| 18 | Resetting Precast Concrete Barrier (606.57) | LF | 20 | $100.00 | $200.00 | $100.00 | $250.00 |
| 19 | Removing and Storing Precast Concrete Barrier (606.65) | LF | 40 | $100.00 | $100.00 | $100.00 | $250.00 |
| 20 | (606.73000015) | 20 | $50.00 | $150.00 | $300.00 | $100.00 | |
| 21 | Removing and Disposing Weak- and Heavy-Post Corrugated Beam Energy-Absorbing Terminals (606.7911) | EACH | 1 | $250.00 | $200.00 | $300.00 | $100.00 |
| 22 | (607.3103) | LF | 6 | $225.00 | $300.00 | $500.00 | $500.00 |
| 23 | (607.41010010) | 55 | $12.00 | $10.00 | $125.00 | $25.00 | |
| 24 | (607.62000010) | 6 | $30.00 | $30.00 | $250.00 | $50.00 | |
| 25 | (607.98870001) | 19 | $150.00 | $80.00 | $500.00 | $250.00 | |
| 26 | Concrete Sidewalks and Driveways (608.0101) | CY | 90 | $1,500.00 | $2,325.00 | $2,920.00 | $8,000.00 |
| 27 | Embedded Detectable Warning Units (608.21) | SY | 33 | $400.00 | $1,200.00 | $316.00 | $100.00 |
| 28 | (609.0401) | LF | 18 | $55.00 | $100.00 | $250.00 | $55.00 |
| 29 | (609.26020111) | 841 | $185.00 | $290.00 | $400.00 | $520.00 | |
| 30 | Topsoil - Lawns (610.1403) | CY | 18 | $200.00 | $200.00 | $150.00 | $125.00 |
| 31 | Turf Establishment -Lawns (610.1602) | SY | 36 | $20.00 | $40.00 | $180.00 | $25.00 |
| 32 | Watering Vegetation (610.19) | 1,000 GALLONS | 5 | $20.00 | $1,000.00 | $900.00 | $500.00 |
| 33 | (614.08110009) | 15 | $200.00 | $445.00 | $200.00 | $250.00 | |
| 34 | (614.08210009) | 15 | $200.00 | $475.00 | $200.00 | $250.00 | |
| 35 | Tree Root Pruning (614.09) | LF | 30 | $50.00 | $10.00 | $100.00 | $150.00 |
| 36 | (615.33010011) | 2 | $500.00 | $1,000.00 | $1,250.00 | $750.00 | |
| 37 | (615.43000011) | 300 | $100.00 | $5.00 | $45.00 | $10.00 | |
| 38 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $125,000 | $125,000 | $310,000 | $250,000 |
| 39 | (619.080102) | LF | 4,557 | $7.00 | $2.00 | $2.00 | $1.00 |
| 40 | (619.10050020) | 500 | $38.00 | $30.00 | $50.00 | $75.00 | |
| 41 | Survey Operations (625.01) | LS | 1 | $20,000 | $45,000 | $30,000 | $35,000 |
| 42 | Cleaning and Preparation of Pavement Surfaces-Lines (635.0103) | LF | 2,500 | $3.00 | $1.00 | $4.00 | $1.00 |
| 43 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $500.00 | $2,000.00 | $5,000.00 | $2,500.00 |
| 44 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 18 | $3,500.00 | $7,500.00 | $15,000 | $9,000.00 |
| 45 | (637.31020020) | 18 | $950.00 | $750.00 | $950.00 | $950.00 | |
| 46 | Office Technology and Supplies (637.34) | DOL | 2,500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 47 | (639.10210011) | LS | 1 | $50,000 | $50,000 | $50,000 | $50,000 |
| 48 | (642.31100024) | 21 | $6.00 | $35.00 | $25.00 | $50.00 | |
| 49 | Type A Sign Posts (645.81) | EACH | 6 | $1,500.00 | $750.00 | $1,250.00 | $350.00 |
| 50 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 6 | $600.00 | $400.00 | $1,500.00 | $350.00 |
| 51 | (655.17000011) | 19 | $380.00 | $400.00 | $1,250.00 | $150.00 | |
| 52 | Adjust Existing Valve Box Elevation (663.33) | EACH | 10 | $200.00 | $200.00 | $850.00 | $150.00 |
| 53 | Remove and Dispose of Existing Hydrant (663.43) | EACH | 1 | $1,000.00 | $5,000.00 | $3,000.00 | $5,000.00 |
| 54 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 4,557 | $10.00 | $4.00 | $6.00 | $4.00 |
| 55 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 100 | $10.00 | $4.00 | $8.00 | $4.00 |
| 56 | Field Change Payment (FCP) (697.03) | DOL | 74,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 57 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 58 | Fuel Price Adjustment (698.05) | DOL | 119 | $1.00 | $1.00 | $1.00 | $1.00 |
| 59 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 60 | Mobilization (699.040001) | LS | 1 | $46,772 | $60,000 | $75,000 | $90,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of January 9, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way