RankBidderTotal bidAgainst the low bid
1Elderlee Inc$744,541Low
2Pavilion Drainage Supply Co Inc$749,542+1.0%
NYSDOT contract D265430: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Elderlee Inc2. Pavilion Drainage Supply Co Inc
1Clearing and Grubbing (201.06)LS1$2,000.00$5,600.00
2 (203.24010017)348$110.00$103.50
3Box Beam Guide Railing (606.10)LF10,188$42.00$43.50
4Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002)LF234$62.00$50.50
5Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH23$2,200.00$1,840.00
6Box Beam End Assembly Type III (606.1203)EACH1$5,600.00$6,410.00
7Removing and Storing Corrugated Beam Guide Railing (606.61)LF1,936$2.00$3.50
8Removing and Storing Box Beam Guide Railing (606.63)LF7,258$3.00$5.00
9Removing and Storing Anchorage Units for Corrugated Beam Guide Railing and Median Barriers (606.6910)EACH6$300.00$150.00
10Removing and Storing Box Beam Guide Railing End Assembly (606.6920)EACH13$35.00$75.00
11Removing and Disposing Cable Guide Railing (606.70)LF1,565$2.00$1.60
12Removing and Disposing Anchorage Units for Cable Guide railing or Median Barrier (606.79)EACH6$300.00$150.00
13Basic Work Zone Traffic Control (619.01)LS1$74,126$55,000
14Mailboxes (619.27)EACH5$300.00$285.00
15 (625.09010015)LS1$1,000.00$3,070.00
16Engineer’s Field Office – Type 1 (637.11)MONTH8$3,000.00$2,800.00
17Office Technology and Supplies (637.34)DOL200$1.00$1.00
18Construction Testing supplies – Consumables (637.36)DOL200$1.00$1.00
19Reference Marker Panel (646.21)EACH8$30.00$36.00
20Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23)EACH95$20.00$19.50
21Steel Post, 2.0 lb/ft (646.32)EACH81$60.00$78.00
22Field Change Payment (FCP) (697.03)DOL36,000$1.00$1.00
23Asphalt Price Adjustment (698.04)DOL100$1.00$1.00
24Fuel Price Adjustment (698.05)DOL100$1.00$1.00
25Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00
26Mobilization (699.040001)LS1$28,500$28,800
NYSDOT contract D265430: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of February 20, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy