NYSDOT contract D265448 bid tabulation
Regional Graffiti Removal Contract. Let by New York State DOT on February 27, 2025, Columbia, Dutchess, Orange, Putnam,, Region 08. 4 bids received; low bid $420,119 by Metroexpress Services Inc.
- Owner
- New York State DOT
- Letting
- 27 FEB 2025
- Pay items
- 19
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Metroexpress Services Inc | $420,119 | Low |
| 2 | Coyle Industries Inc. | $662,825 | +58% |
| 3 | Morano Brothers Corp | $771,700 | +84% |
| 4 | Rover Contracting Inc | $1,214,600 | +189% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Metroexpress Services Inc | 2. Coyle Industries Inc. | 3. Morano Brothers Corp | 4. Rover Contracting Inc |
|---|---|---|---|---|---|---|---|
| 1 | (559.22010008) | 48 | $400.00 | $400.00 | $400.00 | $400.00 | |
| 2 | (559.22020008) | 2 | $1,200.00 | $1,200.00 | $1,200.00 | $1,200.00 | |
| 3 | (559.23010008) | 11,025 | $5.00 | $25.00 | $20.00 | $50.00 | |
| 4 | (559.23020008) | 225 | $30.00 | $40.00 | $20.00 | $150.00 | |
| 5 | (559.23030008) | 3 | $6,800.00 | $10,000 | $7,500.00 | $3,000.00 | |
| 6 | (619.01931110) | 35 | $3,200.00 | $2,000.00 | $5,600.00 | $8,000.00 | |
| 7 | (619.01931210) | 12 | $3,200.00 | $2,500.00 | $4,500.00 | $8,000.00 | |
| 8 | (619.01931310) | 1 | $4,200.00 | $2,500.00 | $8,400.00 | $7,500.00 | |
| 9 | (619.01931410) | 1 | $3,200.00 | $2,500.00 | $5,700.00 | $7,500.00 | |
| 10 | (619.01931510) | 1 | $3,200.00 | $2,500.00 | $7,500.00 | $7,500.00 | |
| 11 | (619.01991108) | 2 | $5,600.00 | $3,500.00 | $6,500.00 | $8,000.00 | |
| 12 | (619.01991208) | 8 | $6,200.00 | $4,000.00 | $6,800.00 | $9,000.00 | |
| 13 | Type III Construction Barricades (619.04) | EACH | 10 | $525.00 | $100.00 | $110.00 | $200.00 |
| 14 | (619.24010011) | 2 | $1,100.00 | $2,000.00 | $3,000.00 | $10,000 | |
| 15 | Engineer’s Field Office – Type 1 (637.11) | MONTH | 22 | $2,400.00 | $6,000.00 | $5,200.00 | $1,200.00 |
| 16 | Office Technology and Supplies (637.34) | DOL | 2,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 17 | Field Change Payment (FCP) (697.03) | DOL | 16,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 18 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 19 | Mobilization (699.040001) | LS | 1 | $16,094 | $25,000 | $24,000 | $46,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of February 27, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.