NYSDOT contract D265496 bid tabulation

ADA SIDEWALKS AND RAMPS. Let by New York State DOT on May 22, 2025, Dutchess, Putnam, Region 08. 4 bids received; low bid $3,808,579 by Paleen Construction Corp.

Owner
New York State DOT
Letting
22 MAY 2025
Pay items
34
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Paleen Construction Corp$3,808,579Low
2Scape-Tech Landscape Technology Inc.$3,981,409+5.0%
3Sun Up Construction Corp$4,367,103+15%
4Morano Brothers Corp$4,394,988+15%
NYSDOT contract D265496: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Paleen Construction Corp2. Scape-Tech Landscape Technology Inc.3. Sun Up Construction Corp4. Morano Brothers Corp
1Clearing and Grubbing (201.07)ACRE1$10,000$30,000$5,750.00$9,500.00
2Mulch – Temporary (209.100101)SY3,200$4.50$5.00$2.30$1.00
3 (404.0001)TON6$120.00$120.00$120.00$120.00
4 (404.1281)TON120$575.00$440.00$575.00$380.00
5Straight Tack Coat (407.0103)GAL32$25.00$15.00$5.75$50.00
6Asphalt Pavement Joint Adhesive (418.7603)LF9,510$5.00$4.00$8.63$4.00
7PCC Foundation for Pavement, PEM Concrete (503.1013)CY294$700.00$425.00$805.00$560.00
8 (604.070801)EACH42$1,700.00$1,400.00$1,265.00$940.00
9Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013)QUALITY UNIT1$120.00$120.00$120.00$120.00
10Concrete Sidewalks and Driveways (608.0101)CY1,265$1,350.00$1,300.00$1,500.00$1,100.00
11 (608.02010015)2,455$149.00$200.00$172.50$210.00
12Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON51$600.00$505.00$690.00$440.00
13 (608.02020015)1,295$150.00$195.00$287.50$220.00
14 (608.21000003)200$500.00$320.00$465.00$410.00
15 (609.0405)LF165$100.00$68.00$230.00$110.00
16Turf Establishment – Performance (610.1605)SY3,200$35.00$38.00$3.45$6.00
17Basic Work Zone Traffic Control (619.01)LS1$400,000$400,000$500,000$1,056,000
18 (619.080102)LF448$3.00$3.00$2.88$6.00
19Mailboxes (619.27)EACH12$400.00$1,100.00$890.00$440.00
20 (619.27000007)1$2,500.00$400.00$890.00$700.00
21Survey Operations (625.01)LS1$25,000$152,000$72,000$113,800
22 (625.09010015)LS1$2,500.00$15,000$15,000$2,000.00
23Engineer’s Field Office – Type 3 (637.13)MONTH24$4,000.00$4,500.00$4,025.00$8,000.00
24Office Technology and Supplies (637.34)DOL2,000$1.00$1.00$1.00$1.00
25Type A Sign Posts (645.81)EACH30$200.00$310.00$289.00$500.00
26Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31)EACH40$200.00$480.00$275.00$690.00
27Adjust Existing Valve Box Elevation (663.33)EACH31$200.00$220.00$138.00$70.00
28 (670.14480010)10$600.00$1,250.00$575.00$900.00
29White Epoxy Reflectorized Pavement Stripes - 15 mil (685.0101)LF9,958$5.04$5.40$4.83$6.00
30Field Change Payment (FCP) (697.03)DOL105,000$1.00$1.00$1.00$1.00
31Asphalt Price Adjustment (698.04)DOL160$1.00$1.00$1.00$1.00
32Fuel Price Adjustment (698.05)DOL102$1.00$1.00$1.00$1.00
33Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00
34Mobilization (699.040001)LS1$146,000$150,000$160,000$165,000
NYSDOT contract D265496: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of May 22, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy