NYSDOT contract D265496 bid tabulation
ADA SIDEWALKS AND RAMPS. Let by New York State DOT on May 22, 2025, Dutchess, Putnam, Region 08. 4 bids received; low bid $3,808,579 by Paleen Construction Corp.
- Owner
- New York State DOT
- Letting
- 22 MAY 2025
- Pay items
- 34
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Paleen Construction Corp | $3,808,579 | Low |
| 2 | Scape-Tech Landscape Technology Inc. | $3,981,409 | +5.0% |
| 3 | Sun Up Construction Corp | $4,367,103 | +15% |
| 4 | Morano Brothers Corp | $4,394,988 | +15% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Paleen Construction Corp | 2. Scape-Tech Landscape Technology Inc. | 3. Sun Up Construction Corp | 4. Morano Brothers Corp |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.07) | ACRE | 1 | $10,000 | $30,000 | $5,750.00 | $9,500.00 |
| 2 | Mulch – Temporary (209.100101) | SY | 3,200 | $4.50 | $5.00 | $2.30 | $1.00 |
| 3 | (404.0001) | TON | 6 | $120.00 | $120.00 | $120.00 | $120.00 |
| 4 | (404.1281) | TON | 120 | $575.00 | $440.00 | $575.00 | $380.00 |
| 5 | Straight Tack Coat (407.0103) | GAL | 32 | $25.00 | $15.00 | $5.75 | $50.00 |
| 6 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 9,510 | $5.00 | $4.00 | $8.63 | $4.00 |
| 7 | PCC Foundation for Pavement, PEM Concrete (503.1013) | CY | 294 | $700.00 | $425.00 | $805.00 | $560.00 |
| 8 | (604.070801) | EACH | 42 | $1,700.00 | $1,400.00 | $1,265.00 | $940.00 |
| 9 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 1 | $120.00 | $120.00 | $120.00 | $120.00 |
| 10 | Concrete Sidewalks and Driveways (608.0101) | CY | 1,265 | $1,350.00 | $1,300.00 | $1,500.00 | $1,100.00 |
| 11 | (608.02010015) | 2,455 | $149.00 | $200.00 | $172.50 | $210.00 | |
| 12 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 51 | $600.00 | $505.00 | $690.00 | $440.00 |
| 13 | (608.02020015) | 1,295 | $150.00 | $195.00 | $287.50 | $220.00 | |
| 14 | (608.21000003) | 200 | $500.00 | $320.00 | $465.00 | $410.00 | |
| 15 | (609.0405) | LF | 165 | $100.00 | $68.00 | $230.00 | $110.00 |
| 16 | Turf Establishment – Performance (610.1605) | SY | 3,200 | $35.00 | $38.00 | $3.45 | $6.00 |
| 17 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $400,000 | $400,000 | $500,000 | $1,056,000 |
| 18 | (619.080102) | LF | 448 | $3.00 | $3.00 | $2.88 | $6.00 |
| 19 | Mailboxes (619.27) | EACH | 12 | $400.00 | $1,100.00 | $890.00 | $440.00 |
| 20 | (619.27000007) | 1 | $2,500.00 | $400.00 | $890.00 | $700.00 | |
| 21 | Survey Operations (625.01) | LS | 1 | $25,000 | $152,000 | $72,000 | $113,800 |
| 22 | (625.09010015) | LS | 1 | $2,500.00 | $15,000 | $15,000 | $2,000.00 |
| 23 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 24 | $4,000.00 | $4,500.00 | $4,025.00 | $8,000.00 |
| 24 | Office Technology and Supplies (637.34) | DOL | 2,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 25 | Type A Sign Posts (645.81) | EACH | 30 | $200.00 | $310.00 | $289.00 | $500.00 |
| 26 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 40 | $200.00 | $480.00 | $275.00 | $690.00 |
| 27 | Adjust Existing Valve Box Elevation (663.33) | EACH | 31 | $200.00 | $220.00 | $138.00 | $70.00 |
| 28 | (670.14480010) | 10 | $600.00 | $1,250.00 | $575.00 | $900.00 | |
| 29 | White Epoxy Reflectorized Pavement Stripes - 15 mil (685.0101) | LF | 9,958 | $5.04 | $5.40 | $4.83 | $6.00 |
| 30 | Field Change Payment (FCP) (697.03) | DOL | 105,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 31 | Asphalt Price Adjustment (698.04) | DOL | 160 | $1.00 | $1.00 | $1.00 | $1.00 |
| 32 | Fuel Price Adjustment (698.05) | DOL | 102 | $1.00 | $1.00 | $1.00 | $1.00 |
| 33 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 34 | Mobilization (699.040001) | LS | 1 | $146,000 | $150,000 | $160,000 | $165,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of May 22, 2025. Compiled by Mirage Metrics.