NYSDOT contract D265497 bid tabulation
SAFETY ENHANCEMENTS PROJECT - NY Route 101. Let by New York State DOT on June 26, 2025, Nassau, Region 10. 6 bids received; low bid $3,544,811 by Posillico Civil Inc.
- Owner
- New York State DOT
- Letting
- 26 JUN 2025
- Pay items
- 138
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Posillico Civil Inc | $3,544,811 | Low |
| 2 | Pratt Brothers Inc | $3,625,000 | +2.0% |
| 3 | H & L Contracting LLC | $3,972,000 | +12% |
| 4 | Stasi General Contracting LLC | $5,669,950 | +60% |
| 5 | Triumph Construction Corp | $6,254,850 | +76% |
| 6 | Fos Development Corp | $6,500,383 | +83% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Posillico Civil Inc | 2. Pratt Brothers Inc | 3. H & L Contracting LLC | 4. Stasi General Contracting LLC | 5. Triumph Construction Corp | 6. Fos Development Corp |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $10,000 | $25,000 | $29,344 | $150,000 | $7,270.00 | $19,872 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 900 | $50.00 | $100.00 | $170.00 | $120.00 | $262.00 | $212.87 |
| 3 | Embankment In Place (203.03) | CY | 5 | $205.00 | $30.00 | $1.44 | $1,000.00 | $447.00 | $99.42 |
| 4 | Select Granular Fill (203.07) | CY | 120 | $50.00 | $40.00 | $50.00 | $100.00 | $147.00 | $80.70 |
| 5 | Trench and Culvert Excavation (206.0201) | CY | 150 | $1.00 | $10.00 | $30.00 | $100.00 | $716.00 | $76.03 |
| 6 | (206.03100010) | 130 | $135.00 | $100.00 | $145.62 | $125.00 | $73.00 | $511.23 | |
| 7 | (209.11010024) | 22 | $455.00 | $125.00 | $690.00 | $250.00 | $359.00 | $2,229.51 | |
| 8 | Silt Fence - Temporary (209.13) | LF | 870 | $25.00 | $12.00 | $25.87 | $14.00 | $14.00 | $10.48 |
| 9 | Removal and Disposal of Underground Pipe ACM (BV14) (210.3111) | LF | 200 | $245.00 | $185.00 | $250.00 | $300.00 | $182.00 | $435.80 |
| 10 | (304.10119917) | 330 | $215.00 | $145.00 | $155.00 | $185.00 | $199.00 | $304.10 | |
| 11 | (404.0001) | TON | 167 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 |
| 12 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 1 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 |
| 13 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 9 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 |
| 14 | (404.0189) | TON | 860 | $170.00 | $175.00 | $120.00 | $150.00 | $298.00 | $274.86 |
| 15 | (404.0961) | TON | 1,704 | $170.00 | $151.00 | $140.00 | $180.00 | $300.00 | $204.68 |
| 16 | (404.1989) | TON | 254 | $170.00 | $345.00 | $450.00 | $200.00 | $237.00 | $672.53 |
| 17 | (404.2589) | TON | 508 | $170.00 | $345.00 | $380.00 | $200.00 | $238.00 | $409.36 |
| 18 | (404.4289) | TON | 63 | $170.00 | $400.00 | $460.00 | $200.00 | $371.00 | $385.97 |
| 19 | Diluted Tack Coat (407.0102) | GAL | 846 | $50.00 | $9.00 | $3.95 | $5.00 | $44.00 | $23.39 |
| 20 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 4,542 | $5.00 | $2.00 | $1.28 | $8.00 | $2.00 | $9.36 |
| 21 | Production Cold Milling of Bituminous Concrete (490.10) | SY | 14,080 | $3.00 | $10.00 | $9.35 | $9.00 | $13.00 | $12.28 |
| 22 | (502.10010018) | LS | 1 | $2,000.00 | $1,500.00 | $5,500.00 | $20,000 | $11,189 | $12,076 |
| 23 | (510.02210018) | 3 | $1,775.00 | $4,000.00 | $6,000.00 | $4,000.00 | $10,368 | $5,178.38 | |
| 24 | (510.20000018) | 11 | $450.00 | $25.00 | $1,140.00 | $1,000.00 | $1,645.00 | $1,205.90 | |
| 25 | (520.05000010) | 4,172 | $4.95 | $5.50 | $4.95 | $6.00 | $7.00 | $9.81 | |
| 26 | (520.09000010) | 615 | $3.00 | $5.00 | $3.00 | $6.00 | $4.00 | $10.33 | |
| 27 | Temporary Timber Sheeting (552.12) | SF | 2,000 | $1.00 | $4.00 | $0.16 | $65.00 | $21.00 | $1.17 |
| 28 | (603.6002) | LF | 42 | $130.00 | $195.00 | $165.00 | $700.00 | $33.00 | $198.83 |
| 29 | (603.6003) | LF | 61 | $165.00 | $200.00 | $169.00 | $800.00 | $38.00 | $224.57 |
| 30 | (603.6005) | LF | 62 | $185.00 | $215.00 | $180.00 | $425.00 | $60.00 | $274.86 |
| 31 | (604.07200110) | 3 | $2,500.00 | $1,500.00 | $3,300.00 | $6,000.00 | $2,325.00 | $1,502.95 | |
| 32 | (604.07210110) | 15 | $2,550.00 | $1,500.00 | $3,300.00 | $500.00 | $230.00 | $1,502.95 | |
| 33 | (604.07240110) | 3 | $4,500.00 | $4,000.00 | $5,200.00 | $5,000.00 | $5,791.00 | $5,848.06 | |
| 34 | (604.501012) | LF | 22 | $100.00 | $2,400.00 | $1,850.00 | $3,000.00 | $1,879.00 | $3,216.43 |
| 35 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 7 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 | $125.00 |
| 36 | Concrete Sidewalks and Driveways (608.0101) | CY | 60 | $785.00 | $1,200.00 | $785.00 | $1,800.00 | $560.00 | $1,257.34 |
| 37 | (608.01020005) | 9 | $2,850.00 | $4,000.00 | $2,850.00 | $2,000.00 | $2,096.00 | $3,536.97 | |
| 38 | (608.01050010) | 54 | $1,375.00 | $1,100.00 | $1,300.00 | $1,800.00 | $900.00 | $1,227.83 | |
| 39 | (608.01050109) | 1 | $4,850.00 | $8,000.00 | $6,500.00 | $17,000 | $3,833.00 | $1,391.85 | |
| 40 | (608.01050209) | 3 | $5,750.00 | $12,000 | $7,500.00 | $18,000 | $957.00 | $1,391.85 | |
| 41 | (608.01051209) | 2 | $22,000 | $20,000 | $16,000 | $18,500 | $1,704.00 | $1,391.85 | |
| 42 | (608.01051409) | 1 | $4,350.00 | $7,500.00 | $6,500.00 | $12,000 | $3,043.00 | $1,391.85 | |
| 43 | (608.02010015) | 7 | $1,500.00 | $765.00 | $100.00 | $125.00 | $496.00 | $309.95 | |
| 44 | (609.04010510) | 1,844 | $80.00 | $65.00 | $60.00 | $55.00 | $62.00 | $28.02 | |
| 45 | (609.04050510) | 243 | $90.00 | $85.00 | $65.00 | $60.00 | $54.00 | $89.80 | |
| 46 | (609.06000008) | 1,152 | $18.00 | $9.00 | $25.00 | $10.00 | $20.00 | $11.70 | |
| 47 | Fertilizer (610.0501) | LB | 50 | $4.00 | $4.00 | $4.00 | $100.00 | $6.00 | $4.68 |
| 48 | Limestone (610.06) | LB | 40 | $4.00 | $4.00 | $4.00 | $100.00 | $6.00 | $4.68 |
| 49 | Mycorrhizal Fungi (610.0701) | LB | 2 | $25.00 | $25.00 | $25.00 | $100.00 | $36.00 | $29.24 |
| 50 | Moisture Retention Additive (610.08) | LB | 6 | $20.00 | $20.00 | $20.00 | $100.00 | $29.00 | $23.39 |
| 51 | Mulch for Planting Type A, B & D Wood Chips and Shredded Bark (610.1101) | CY | 5 | $100.00 | $120.00 | $100.00 | $125.00 | $145.00 | $116.96 |
| 52 | Topsoil - Roadside (610.1402) | CY | 56 | $98.00 | $125.00 | $98.00 | $125.00 | $142.00 | $114.62 |
| 53 | Topsoil - Lawns (610.1403) | CY | 20 | $98.00 | $125.00 | $98.00 | $140.00 | $142.00 | $114.62 |
| 54 | Turf Establishment - Roadside (610.1601) | SY | 481 | $5.00 | $7.00 | $5.00 | $30.00 | $7.00 | $5.85 |
| 55 | Turf Establishment -Lawns (610.1602) | SY | 111 | $10.00 | $13.00 | $10.00 | $30.00 | $15.00 | $11.70 |
| 56 | Watering Vegetation (610.19) | 1,000 GALLONS | 10 | $100.00 | $100.00 | $100.00 | $400.00 | $145.00 | $116.96 |
| 57 | (611.0421) | EACH | 60 | $110.00 | $110.00 | $110.00 | $2,500.00 | $160.00 | $128.66 |
| 58 | (611.0522) | EACH | 20 | $110.00 | $110.00 | $110.00 | $2,000.00 | $160.00 | $128.66 |
| 59 | Post-Planting Care (611.19) | EACH | 30 | $20.00 | $20.00 | $20.00 | $500.00 | $29.00 | $23.39 |
| 60 | (615.02050124) | 3 | $1,000.00 | $1,000.00 | $296.75 | $1,000.00 | $727.00 | $2,159.66 | |
| 61 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $400,000 | $295,000 | $524,022 | $150,000 | $793,125 | $1,742,722 |
| 62 | Type III Construction Barricades (619.04) | EACH | 12 | $235.00 | $125.00 | $55.00 | $7,000.00 | $362.00 | $365.50 |
| 63 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 5,700 | $3.62 | $3.50 | $3.62 | $4.00 | $4.00 | $3.33 |
| 64 | (619.0904) | LF | 19,579 | $2.94 | $2.85 | $2.94 | $4.00 | $4.00 | $2.92 |
| 65 | (619.10050020) | 720 | $40.00 | $75.00 | $5.00 | $500.00 | $36.00 | $61.53 | |
| 66 | (619.111133) | EACH | 3 | $8,300.00 | $25,000 | $12,000 | $25,000 | $43,046 | $39,733 |
| 67 | Maintain Traffic Signal Equipment (Requirement A) Intersection (619.1611) | MONTH | 3 | $3,000.00 | $1,600.00 | $3,000.00 | $6,500.00 | $1,749.00 | $1,407.04 |
| 68 | Temporary Positive Barrier – Category 5 (Pinning Prohibited) (619.1715) | LF | 4,140 | $75.00 | $50.00 | $85.00 | $45.00 | $173.00 | $114.88 |
| 69 | Warning Lights on Temporary Positive Barriers (619.1719) | EACH | 414 | $30.00 | $150.00 | $135.00 | $100.00 | $73.00 | $48.86 |
| 70 | Temporary Impact Attenuator - Redirective (Test Level 3) (619.1803) | EACH | 8 | $13,225 | $9,000.00 | $12,500 | $10,000 | $13,271 | $10,667 |
| 71 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $150,000 | $135,611 | $75,000 | $150,000 | $155,432 | $261,586 |
| 72 | Traffic Control Supervisor (619.25) | MONTH | 12 | $100.00 | $1,000.00 | $150.00 | $15,000 | $31,638 | $22,162 |
| 73 | Cleaning Closed Drainage Systems (621.03) | LF | 1,885 | $6.00 | $5.00 | $9.05 | $7.00 | $28.00 | $28.07 |
| 74 | Cleaning Drainage Structures (621.04) | EACH | 18 | $1,150.00 | $1,200.00 | $1,300.00 | $1,000.00 | $1,288.00 | $584.81 |
| 75 | Survey Operations (625.01) | LS | 1 | $70,000 | $55,000 | $115,000 | $50,000 | $171,562 | $70,177 |
| 76 | (625.09010015) | LS | 1 | $7,000.00 | $21,000 | $2,500.00 | $50,000 | $175,924 | $35,088 |
| 77 | Cleaning Existing Pavement and/or Shoulder (633.11) | SY | 14,080 | $0.30 | $0.20 | $0.15 | $30.00 | $2.00 | $1.17 |
| 78 | Cleaning, Sealing and/or Filling Cracks (633.12) | LS | 1 | $18,000 | $25,000 | $13,036 | $95,000 | $24,717 | $17,544 |
| 79 | (634.10010015) | LS | 1 | $10,000 | $16,000 | $10,000 | $50,000 | $10,000 | $11,696 |
| 80 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $5,000.00 | $2,000.00 | $3,500.00 | $5,000.00 | $4,892.00 | $2,924.03 |
| 81 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 14 | $10,000 | $7,000.00 | $8,000.00 | $4,000.00 | $15,759 | $10,937 |
| 82 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 83 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 84 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 85 | (637.41000115) | 14 | $112.00 | $250.00 | $227.51 | $5,000.00 | $815.00 | $258.99 | |
| 86 | (637.41000215) | 14 | $112.00 | $250.00 | $227.51 | $5,000.00 | $815.00 | $258.99 | |
| 87 | (637.41000315) | 14 | $112.00 | $250.00 | $227.51 | $5,000.00 | $815.00 | $258.99 | |
| 88 | (637.41000415) | 14 | $112.00 | $250.00 | $227.51 | $5,000.00 | $815.00 | $258.99 | |
| 89 | (637.41000515) | 14 | $112.00 | $250.00 | $227.51 | $5,000.00 | $815.00 | $258.99 | |
| 90 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 58 | $103.50 | $104.00 | $103.50 | $500.00 | $150.00 | $71.55 |
| 91 | Type A Sign Posts (645.81) | EACH | 21 | $305.00 | $305.00 | $305.00 | $500.00 | $443.00 | $665.12 |
| 92 | Reference Marker, Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels Relocation (646.24) | EACH | 1 | $95.00 | $95.00 | $95.00 | $1,500.00 | $138.00 | $254.90 |
| 93 | Steel Post, 1.1 lb/ft (646.31) | EACH | 1 | $150.00 | $150.00 | $150.00 | $1,800.00 | $218.00 | $254.90 |
| 94 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 15 | $554.00 | $555.00 | $554.00 | $2,500.00 | $805.00 | $664.34 |
| 95 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 1 | $75.00 | $75.00 | $75.00 | $3,000.00 | $109.00 | $1,180.66 |
| 96 | Remove and Dispose High Capacity Type A Ground Mounted Sign Support and Foundation (647.64) | EACH | 14 | $800.00 | $800.00 | $800.00 | $3,000.00 | $1,163.00 | $337.34 |
| 97 | (655.05010010) | 9 | $3,400.00 | $2,300.00 | $3,400.00 | $1,000.00 | $1,680.00 | $1,228.09 | |
| 98 | (655.07030010) | 3 | $2,840.00 | $2,300.00 | $2,472.72 | $5,000.00 | $3,801.00 | $2,561.45 | |
| 99 | Manhole Frame & Cover (655.1202) | EACH | 3 | $2,840.00 | $1,200.00 | $1,400.00 | $3,000.00 | $833.00 | $935.69 |
| 100 | (655.16000011) | 3 | $700.00 | $2,000.00 | $800.00 | $1,000.00 | $853.00 | $247.96 | |
| 101 | (662.62000010) | 1 | $755.00 | $7,500.00 | $3,300.00 | $1,000.00 | $1,680.00 | $1,518.16 | |
| 102 | Adjust Existing Valve Box Elevation (663.33) | EACH | 12 | $135.00 | $100.00 | $175.00 | $500.00 | $215.00 | $415.21 |
| 103 | (670.14480010) | 4 | $955.00 | $900.00 | $900.00 | $800.00 | $727.00 | $1,035.11 | |
| 104 | (680.05010007) | 1 | $25,000 | $26,000 | $27,000 | $50,000 | $36,758 | $29,570 | |
| 105 | Pole Excavation and Concrete Foundation (680.5001) | CY | 4 | $4,500.00 | $2,200.00 | $5,500.00 | $2,000.00 | $5,386.00 | $844.46 |
| 106 | (680.51050010) | 2 | $3,500.00 | $4,600.00 | $1,900.00 | $2,800.00 | $4,607.00 | $3,706.50 | |
| 107 | (680.520106) | LF | 60 | $26.00 | $112.00 | $26.00 | $35.00 | $162.00 | $130.30 |
| 108 | (680.520108) | LF | 75 | $62.00 | $122.00 | $62.00 | $80.00 | $177.00 | $142.34 |
| 109 | (680.6708) | EACH | 3 | $2,500.00 | $2,800.00 | $2,500.00 | $3,500.00 | $3,312.00 | $2,664.38 |
| 110 | (680.730214) | LF | 185 | $3.00 | $5.90 | $3.00 | $6.00 | $9.00 | $6.90 |
| 111 | (680.730514) | LF | 1,265 | $4.00 | $6.40 | $4.00 | $10.00 | $9.00 | $7.49 |
| 112 | (680.79400010) | 1 | $7,500.00 | $740.00 | $1,200.00 | $1,500.00 | $1,076.00 | $865.51 | |
| 113 | (680.80324515) | 1 | $2,500.00 | $5,225.00 | $2,500.00 | $2,500.00 | $7,569.00 | $6,088.99 | |
| 114 | Traffic Signal Module - 12-inch, Red Ball, LED (680.810101) | EACH | 1 | $180.00 | $340.00 | $180.00 | $2,500.00 | $491.00 | $395.33 |
| 115 | Traffic Signal Module - 12-inch, Yellow Ball, LED (680.810103) | EACH | 1 | $180.00 | $345.00 | $180.00 | $2,000.00 | $500.00 | $402.34 |
| 116 | Traffic Signal Module - 12-inch, Green Ball, LED (680.810105) | EACH | 1 | $180.00 | $345.00 | $180.00 | $2,000.00 | $500.00 | $402.34 |
| 117 | Traffic Signal Section - Polycarbonate, Type I, 12-inch (680.810601) | EACH | 3 | $500.00 | $525.00 | $500.00 | $1,000.00 | $762.00 | $612.88 |
| 118 | Traffic Signal Bracket Assembly - 1 Way (680.8111) | EACH | 1 | $300.00 | $725.00 | $300.00 | $800.00 | $1,053.00 | $846.80 |
| 119 | Pedestrian Signal Section, Aluminum, Type I, for 16 inches by 18 inches LED module (680.813108) | EACH | 7 | $550.00 | $775.00 | $550.00 | $800.00 | $1,124.00 | $904.11 |
| 120 | Pedestrian Signal Bracket Mount Assembly (680.8141) | EACH | 2 | $400.00 | $485.00 | $400.00 | $800.00 | $701.00 | $563.76 |
| 121 | Pedestrian Signal Post Top Mount Assembly (680.8142) | EACH | 5 | $550.00 | $685.00 | $550.00 | $800.00 | $994.00 | $800.01 |
| 122 | Pedestrian Signal Module - 16-inch x 18-inch, Bi-Modal Hand/Man Symbols with Countdown Timer, LED (680.815002) | EACH | 7 | $900.00 | $660.00 | $900.00 | $1,200.00 | $955.00 | $768.43 |
| 123 | (680.8151) | EACH | 3 | $1,200.00 | $1,550.00 | $1,200.00 | $1,800.00 | $2,242.00 | $1,803.54 |
| 124 | (680.8152) | EACH | 4 | $2,200.00 | $3,100.00 | $2,200.00 | $3,000.00 | $4,448.00 | $3,577.84 |
| 125 | (680.83200010) | LS | 1 | $5,000.00 | $10,000 | $5,000.00 | $10,000 | $4,197.00 | $5,614.13 |
| 126 | Performance Concrete Quality Adjustment (680.99) | QUALITY UNIT | 1 | $11.00 | $11.00 | $11.00 | $11.00 | $11.00 | $11.00 |
| 127 | (680.99050010) | 1 | $3,000.00 | $2,890.00 | $2,887.00 | $5,000.00 | $6,979.00 | $3,376.67 | |
| 128 | (685.07200110) | 3,092 | $0.60 | $0.80 | $0.81 | $4.00 | $2.00 | $1.93 | |
| 129 | (685.07200310) | 20 | $159.58 | $155.00 | $159.58 | $800.00 | $138.00 | $111.11 | |
| 130 | (685.07200410) | 4,121 | $0.60 | $2.20 | $2.24 | $4.00 | $2.00 | $1.93 | |
| 131 | (685.07200510) | 1,985 | $2.77 | $2.70 | $2.77 | $4.00 | $2.00 | $1.93 | |
| 132 | (685.07200610) | 2,539 | $0.60 | $0.80 | $0.81 | $4.00 | $2.00 | $1.93 | |
| 133 | (685.07200710) | 120 | $2.24 | $2.20 | $2.24 | $4.00 | $2.00 | $1.93 | |
| 134 | Field Change Payment (FCP) (697.03) | DOL | 250,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 135 | Asphalt Price Adjustment (698.04) | DOL | 4,236 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 136 | Fuel Price Adjustment (698.05) | DOL | 1,066 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 137 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 138 | Mobilization (699.040001) | LS | 1 | $136,339 | $135,000 | $150,000 | $100,000 | $238,500 | $178,290 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of June 26, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.