Traffic Signal Module - 12-inch, Red Ball, LED, NYSDOT 680.810101
Low bidders on NYSDOT contracts carried a median of $140.00 per EACH for this item, over the 24 months to 15 OCT 2026, across 50 low bids. Half of all 169 bids fell between $107.50 and $195.00.
- Owner
- New York State DOT
- Item
- 680.810101
- Unit
- EACH
- Data through
- 15 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 19 | 19 | $116.00 | 95 | $116.00 |
| 2023 | 20 | 20 | $105.50 | 80 | $121.00 |
| 2024 | 24 | 24 | $120.00 | 88 | $120.00 |
| 2025 | 23 | 23 | $140.00 | 80 | $150.00 |
| 2026 | 22 | 22 | $152.50 | 65 | $150.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Region 05 | 19 | $140.00 | 66 | $150.00 |
| Region 04 | 10 | $104.28 | 30 | $108.50 |
| Region 08 | 8 | $157.50 | 27 | $155.00 |
| Region 10 | 6 | $180.00 | 27 | $180.00 |
| Region 03 | 6 | $112.97 | 17 | $107.50 |
Regions with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 8 | 12 | $180.00 |
| 9 to 18 | 13 | $125.00 |
| 20 to 36 | 12 | $100.00 |
| 49 to 100 | 13 | $150.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Sealand Contractors Corp. | 25 | 16 (64%) |
| McLaughlin Construction Corp/DBA Edbauer Construction | 26 | 14 (54%) |
| Power Line Constructors Inc | 10 | 9 (90%) |
| Oakgrove Construction Inc | 14 | 7 (50%) |
| Concrete Applied Technologies Corp/DBA:Catco | 33 | 5 (15%) |
| Occhino Corp | 7 | 5 (71%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 15 OCT 2026 | D265848 | Region 08 | 27 | $90.02 | $131.00 | 3 | Power Line Constructors Inc | NYSDOT |
| 01 OCT 2026 | D265850 | Region 05 | 8 | $138.62 | $200.00 | 3 | Lake Shore Paving Inc | NYSDOT |
| 17 SEP 2026 | D265830 | Region 04 | 4 | $750.00 | $750.00 | 1 | Cold Spring Construction Company | NYSDOT |
| 17 SEP 2026 | D265847 | Region 05 | 34 | $125.00 | $128.00 | 5 | Concrete Applied Technologies Corp/DBA:Catco | NYSDOT |
| 30 JUL 2026 | D265702 | Region 03 | 60 | $107.50 | $108.00 | 3 | Lancaster Development and Tully Construction Co LLC | NYSDOT |
| 30 JUL 2026 | D265812 | Region 10 | 100 | $175.00 | $224.00 | 2 | Commander Electric Inc | NYSDOT |
| 21 MAY 2026 | D265772 | Region 05 | 6 | $200.00 | $175.00 | 4 | Oakgrove Construction Inc | NYSDOT |
| 21 MAY 2026 | D265798 | Region 05 | 16 | $150.00 | $189.81 | 2 | Concrete Applied Technologies Corp/DBA:Catco | NYSDOT |
| 07 MAY 2026 | D265764 | Region 08 | 12 | $165.00 | $124.85 | 2 | Stilsing Electric Inc | NYSDOT |
| 07 MAY 2026 | D265787 | Region 05 | 33 | $90.00 | $120.00 | 2 | McLaughlin Construction Corp/DBA Edbauer Construction | NYSDOT |
| 07 MAY 2026 | D265789 | Region 05 | 49 | $150.00 | $157.50 | 2 | Concrete Applied Technologies Corp/DBA:Catco | NYSDOT |
| 16 APR 2026 | D265773 | Region 05 | 8 | $450.00 | $325.00 | 2 | Cold Spring Construction Company | NYSDOT |
| 09 APR 2026 | D265755 | Region 04 | 12 | $120.00 | $120.00 | 3 | Seneca Stone Corp | NYSDOT |
| 26 FEB 2026 | D265652 | Region 10 | 10 | $183.00 | $199.00 | 2 | GGG Construction Corp | NYSDOT |
| 05 FEB 2026 | D265609 | Region 05 | 6 | $120.00 | $142.50 | 4 | D&H Paving LLC | NYSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the NYSDOT explorer.
How these prices were read
NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NYSDOT's own: this item is compared with NYSDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the NYSDOT letting of 15 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way