NYSDOT contract D265850 bid tabulation

NY Route 474 ADA & Pedestrian Improvements; Town of Clymer. Let by New York State DOT on October 1, 2026, Chautauqua, Region 05. 3 bids received; low bid $2,245,147 by Lake Shore Paving Inc.

Owner
New York State DOT
Letting
01 OCT 2026
Pay items
140
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Lake Shore Paving Inc$2,245,147Low
2Concrete Applied Technologies Corp/DBA:Catco$2,323,115+3.0%
3McLaughlin Construction Corp/DBA Edbauer Construction$2,755,075+23%
NYSDOT contract D265850: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Lake Shore Paving Inc2. Concrete Applied Technologies Corp/DBA:Catco3. McLaughlin Construction Corp/DBA Edbauer Construction
1Clearing and Grubbing (201.06)LS1$5,100.00$1,000.00$10,000
2Unclassified Excavation and Disposal (203.02)CY1,310$60.00$75.00$150.00
3Embankment In Place (203.03)CY215$29.20$35.00$45.00
4Select Granular Fill (203.07)CY420$122.30$84.00$84.00
5 (203.24010017)165$55.00$150.00$25.00
6Structure Excavation (206.01)CY450$31.90$41.00$24.00
7Trench and Culvert Excavation (206.0201)CY1,310$110.00$31.00$38.00
8 (206.03060005)13$116.50$200.00$175.00
9Test Pit Excavation (206.05)EACH2$1,070.00$2,500.00$3,500.00
10Geotextile Bedding (207.20)SY55$25.55$30.00$15.00
11Geotextile Separation (207.21)SY170$5.00$4.00$4.00
12Seed and Mulch – Temporary (209.1003)SY1,750$5.55$1.00$0.10
13Drainage Structure Inlet Protection, Gravel Bag – Temporary (209.1702)CY16$266.15$320.00$1.00
14 (209.23010009)200$19.65$11.00$1.00
15 (304.15200005)860$190.90$95.00$175.00
16 (404.0982)TON85$291.00$275.00$475.00
17 (404.1989)TON45$265.30$180.00$425.00
18 (404.3789)TON65$277.55$160.00$325.00
19Diluted Tack Coat (407.0102)GAL160$19.00$13.00$15.00
20Asphalt Pavement Joint Adhesive (418.7603)LF2,560$1.22$0.90$1.00
21Miscellaneous Cold Milling of Bituminous Concrete (490.30)SY200$33.60$13.00$20.00
22PCC Foundation for Pavement, PEM Concrete (503.1013)CY57$472.25$665.00$550.00
23Shields and Shoring (552.17)SF8,000$0.60$0.30$0.50
24 (553.030001)EACH1$1.00$1.00$100.00
25 (553.030002)EACH1$1.00$1.00$100.00
26Steel Bridge Railing (Four-Rail) (568.51)LF8$1,036.80$1,040.00$1,055.00
27Transition Bridge Railing (568.70)LF64$299.40$300.00$310.00
28 (595.50000018)1,140$2.32$6.00$7.00
29Culvert-End Safety Grate (603.0101)SF100$52.57$45.00$30.00
30 (603.051014)LF24$69.86$159.00$400.00
31 (603.051416)LF16$102.89$297.00$253.00
32 (603.171416)EACH2$1,192.30$1,200.00$750.00
33 (603.171614)EACH1$1,412.00$1,500.00$1,320.00
34 (603.63060415)57$1,820.00$1,650.00$1,800.00
35 (603.6606)LF164$321.50$242.00$420.00
36Concrete Collars (603.77)EACH18$1,205.00$2,400.00$1,700.00
37 (603.9812)LF142$16.75$30.00$140.00
38 (603.9815)LF85$21.38$35.00$145.00
39 (603.9824)LF13$98.50$82.00$320.00
40 (603.99450005)15$253.00$97.00$155.00
41 (604.070501)EACH10$1,034.70$3,350.00$4,000.00
42 (604.070502)EACH3$3,925.63$4,450.00$5,900.00
43 (604.070503)EACH2$5,284.00$5,250.00$8,000.00
44 (604.07260011)4$1,625.40$1,050.00$1,687.00
45 (604.300103)LF6$680.75$596.00$1,045.00
46 (604.300711)LF35$1,187.25$866.00$1,323.00
47 (604.301911)LF18$548.30$522.00$1,117.00
48 (604.500501)LF21$576.27$848.00$1,207.00
49Underdrain Filter, Type II (605.1001)CY450$104.74$75.00$75.00
50 (605.1701)LF130$4.50$15.00$28.00
51 (605.98101218)456$24.80$22.00$74.00
52 (605.98103618)464$91.20$74.00$130.00
53Box Beam Guide Railing (606.10)LF6$85.95$87.00$92.00
54Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH2$3,182.70$3,200.00$3,400.00
55 (607.41010010)35$18.00$10.00$1.00
56 (607.95000008)110$15.65$8.00$7.00
57Concrete Sidewalks and Driveways (608.0101)CY298$688.78$840.00$1,246.00
58Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON30$314.24$250.00$550.00
59 (608.21000003)24$595.50$495.00$510.00
60 (609.0401)LF1,240$43.30$72.00$46.00
61 (609.0403)LF80$109.05$118.00$110.00
62Compost (610.10)CY23$235.83$145.00$50.00
63Topsoil - Roadside (610.1402)CY265$155.86$115.00$35.00
64Turf Establishment -Lawns (610.1602)SY2,360$4.50$3.15$1.00
65Watering Vegetation (610.19)1,000 GALLONS26$277.24$350.00$25.00
66 (611.0151)EACH12$998.00$1,005.00$1,012.00
67 (611.0291)EACH33$610.00$965.00$1,075.00
68Portable Drip Irrigation System (611.17)EACH45$83.17$70.00$87.00
69 (611.19010024)12$138.62$490.00$110.00
70 (611.19020024)33$138.62$490.00$100.00
71 (613.04000001)33$98.35$130.00$45.00
72Care of Trees up to 12” Diam. at Breast Height – Pruning (614.0411)EACH1$1,940.68$1,100.00$2,300.00
73Care of Trees Over 12” to 24” Diam. at Breast Height - Pruning (614.0421)EACH1$1,940.68$1,500.00$2,300.00
74Care of Trees Over 36” to 48” Diam. at Breast Height – Pruning (614.0441)EACH1$3,000.00$2,200.00$100.00
75 (615.99000110)12$1,693.54$1,420.00$1,700.00
76 (618.73115124)20$2,193.35$1,075.00$1,000.00
77Basic Work Zone Traffic Control (619.01)LS1$90,314$243,700$220,520
78Type III Construction Barricades (619.04)EACH12$227.88$80.00$120.00
79 (619.110513)EACH4$8,755.85$1,800.00$4,400.00
80Maintain Traffic Signal Equipment (Requirement A) Intersection (619.1611)MONTH8$166.34$500.00$1,200.00
81Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711)LF80$71.56$30.00$45.00
82Mailboxes (619.27)EACH5$350.00$625.00$250.00
83Stone Filling (Medium) (620.04)CY65$264.50$205.00$140.00
84Bedding Material, Type 1 (620.0801)CY70$146.70$155.00$110.00
85Cleaning Closed Drainage Systems (621.03)LF2,100$4.20$4.50$5.00
86Cleaning Drainage Structures (621.04)EACH17$315.17$305.00$404.00
87 (621.51000015)100$25.00$11.00$18.00
88Crushed Gravel (By Weight) (623.02)TON65$89.10$75.00$110.00
89Crushed Gravel (In-Place Measure) (623.11)CY40$186.96$105.00$110.00
90Survey Operations (625.01)LS1$45,350$36,000$75,000
91Steel Pin and Cap Right of Way Markers (625.05)EACH58$332.00$590.00$325.00
92Permanent Survey Markers (625.06)EACH8$1,996.00$2,000.00$2,500.00
93 (627.50140008)2,700$6.12$7.50$12.00
94 (635.01030011)11,600$1.05$1.00$1.10
95Concrete Cylinder Curing Equipment (637.04)EACH1$2,200.00$3,700.00$100.00
96Engineer’s Field Office – Type 2 (637.12)MONTH14$3,265.00$2,400.00$1,100.00
97Office Technology and Supplies (637.34)DOL500$1.00$1.00$1.00
98White Paint Reflectorized Pavement Stripes – 20 mils (640.20)LF8,550$0.86$0.90$1.00
99Yellow Paint Reflectorized Pavement Stripes - 20 mils (640.21)LF3,850$0.86$0.90$1.00
100Ground-Mounted Sign Panels without Z-bars (645.5101)SF8$37.70$39.00$40.00
101Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF581$39.92$40.00$41.00
102Type A Sign Posts (645.81)EACH95$208.50$209.00$213.00
103 (645.81090003)56$73.19$74.00$75.00
104Reference Marker Panel (646.21)EACH11$44.36$45.00$50.00
105Steel Post, 2.0 lb/ft (646.32)EACH11$72.08$73.00$80.00
106Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61)EACH49$37.70$38.00$38.00
107 (647.83001002)11$13.31$14.00$25.00
108Welded Frame & Reticuline Grate 3 (655.1103)EACH1$1,250.88$1,650.00$2,450.00
109Welded Frame & Reticuline Grate 11 (655.1111)EACH16$1,538.54$1,730.00$2,500.00
110Manhole Frame & Cover (655.1202)EACH6$1,210.74$1,040.00$1,900.00
111 (662.60000108)2,500$1.00$1.00$1.00
112Adjust Existing Valve Box Elevation (663.33)EACH10$353.82$570.00$450.00
113Adjust Existing Curb Box Elevation (663.35)EACH5$353.82$570.00$350.00
114Pole Excavation and Concrete Foundation (680.5001)CY5$3,653.08$3,600.00$3,550.00
115 (680.50500005)2$443.59$1,000.00$720.00
116 (680.510201)EACH2$2,273.36$2,600.00$3,500.00
117 (680.510301)EACH2$2,716.95$2,800.00$3,600.00
118 (680.520508)LF26$27.72$50.00$40.00
119 (680.600534)EACH2$16,246$26,225$16,000
120Dual Span Wire Assembly with Upper Tether Wire (680.7002)EACH1$4,380.40$5,200.00$5,878.00
121Riser Assembly, 1-inch Diameter (680.700603)EACH1$1,608.00$1,000.00$1,700.00
122 (680.730514)LF932$6.65$5.50$8.00
123 (680.79000105)1$3,881.36$4,000.00$5,420.00
124 (680.80620215)1$2,217.92$4,000.00$3,600.00
125Traffic Signal Module - 12-inch, Red Ball, LED (680.810101)EACH8$138.62$200.00$200.00
126Traffic Signal Section - Aluminum Type I, 12-inch (680.810107)EACH8$243.97$260.00$162.00
127Traffic Signal Bracket Assembly - 1 Way (680.8111)EACH8$526.76$350.00$439.00
128Traffic Signal Disconnect Hanger (680.8120)EACH8$582.21$750.00$839.00
129Backplates for Traffic Signal Heads (680.8199)EACH8$227.34$200.00$130.00
130Meter Pan (680.9402)EACH1$1,996.12$1,000.00$1,320.00
131Install Electrical Disconnect/Generator Transfer Switch (680.9499)EACH1$1,552.55$1,200.00$789.00
132 (680.950106)LF102$6.65$27.00$13.00
133Performance Concrete Quality Adjustment (680.99)QUALITY UNIT1$10.00$10.00$10.00
134White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104)LF3,320$4.38$4.30$4.75
135Field Change Payment (FCP) (697.03)DOL91,000$1.00$1.00$1.00
136Asphalt Price Adjustment (698.04)DOL100$1.00$1.00$1.00
137Fuel Price Adjustment (698.05)DOL1,722$1.00$1.00$1.00
138Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00
139 (698.93940015)LS1$30,000$30,000$30,000
140Mobilization (699.040001)LS1$39,000$88,000$105,000
NYSDOT contract D265850: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of October 1, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way