Compost, NYSDOT 610.10
Low bidders on NYSDOT contracts carried a median of $99.00 per CY for this item, over the 24 months to 15 OCT 2026, across 49 low bids. Half of all 208 bids fell between $75.00 and $150.00.
- Owner
- New York State DOT
- Item
- 610.10
- Unit
- CY
- Data through
- 15 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 17 | 17 | $95.00 | 72 | $95.00 |
| 2023 | 9 | 9 | $93.50 | 41 | $110.00 |
| 2024 | 29 | 28 | $91.00 | 112 | $108.12 |
| 2025 | 26 | 25 | $117.00 | 116 | $110.00 |
| 2026 | 15 | 14 | $87.50 | 51 | $100.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Region 05 | 16 | $135.00 | 58 | $140.00 |
| Region 03 | 8 | $159.50 | 32 | $144.50 |
| Region 10 | 5 | $75.00 | 31 | $75.00 |
| Region 09 | 5 | $78.70 | 21 | $90.00 |
| Region 08 | 3 | $100.00 | 16 | $115.00 |
| Region 01 | 4 | $94.00 | 13 | $96.00 |
| Region 02 | 3 | $175.00 | 9 | $144.00 |
Regions with at least three low bids, over the last 24 months.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 0.30 to 15 | 12 | $144.50 |
| 17 to 62.50 | 12 | $145.00 |
| 76 to 200 | 12 | $89.50 |
| 200 to 5,128 | 13 | $77.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| McLaughlin Construction Corp/DBA Edbauer Construction | 19 | 11 (58%) |
| Cold Spring Construction Company | 19 | 6 (32%) |
| Concrete Applied Technologies Corp/DBA:Catco | 23 | 5 (22%) |
| Oakgrove Construction Inc | 13 | 5 (38%) |
| Economy Paving Co Inc | 10 | 5 (50%) |
| Vector Construction Corp | 12 | 4 (33%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 01 OCT 2026 | D265800 | Region 11 | 1,145 | $90.00 | $100.00 | 5 | Westmoreland Construction Inc | NYSDOT |
| 01 OCT 2026 | D265850 | Region 05 | 23 | $235.83 | $145.00 | 3 | Lake Shore Paving Inc | NYSDOT |
| 17 SEP 2026 | D265809 | Region 10 | 109 | $85.00 | $85.00 | 8 | H & L Contracting LLC | NYSDOT |
| 27 AUG 2026 | D265803 | Region 10 | 200 | $45.00 | $80.00 | 5 | Westmoreland Construction Inc | NYSDOT |
| 16 JUL 2026 | D265796 | Region 03 | 51 | $44.00 | $106.50 | 6 | Winn Construction Services Inc | NYSDOT |
| 25 JUN 2026 | D265768 | Region 02 | 145 | $175.00 | $159.50 | 4 | Cci Companies Inc | NYSDOT |
| 21 MAY 2026 | D265781 | Region 08 | 35 | $264.00 | $150.00 | 5 | Hylan Datacom & Electrical LLC | NYSDOT |
| 07 MAY 2026 | D265753 | Region 09 | 1,255 | $78.70 | $105.80 | 2 | Lancaster Development and Tully Construction Co LLC | NYSDOT |
| 07 MAY 2026 | D265787 | Region 05 | 32 | $83.00 | $116.50 | 2 | McLaughlin Construction Corp/DBA Edbauer Construction | NYSDOT |
| 07 MAY 2026 | D265789 | Region 05 | 4 | $165.00 | $703.97 | 2 | Concrete Applied Technologies Corp/DBA:Catco | NYSDOT |
| 12 MAR 2026 | D265664 | Region 11 | 50 | n/a | $210.00 | 1 | Constar Inc | NYSDOT |
| 12 MAR 2026 | D265736 | Region 09 | 1,558 | $50.00 | $61.60 | 2 | Dalrymple Gravel & Contracting Co Inc | NYSDOT |
| 05 FEB 2026 | D265609 | Region 05 | 7 | $76.00 | $113.00 | 4 | D&H Paving LLC | NYSDOT |
| 22 JAN 2026 | D265631 | Region 11 | 50 | $120.00 | $120.00 | 1 | Ahern Painting Contractors Inc | NYSDOT |
| 08 JAN 2026 | D265673 | Region 05 | 22 | $184.00 | $184.00 | 1 | Concrete Applied Technologies Corp/DBA:Catco | NYSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the NYSDOT explorer.
How these prices were read
NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NYSDOT's own: this item is compared with NYSDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the NYSDOT letting of 15 OCT 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.