NYSDOT contract D265631 bid tabulation
BRIDGE PAINTING - VARIOUS LOCATIONS. Let by New York State DOT on January 22, 2026, Bronx, Queens, Richmond, Region 11. 2 bids received; low bid $20,893,024 by Ahern Painting Contractors Inc.
- Owner
- New York State DOT
- Letting
- 22 JAN 2026
- Pay items
- 130
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Ahern Painting Contractors Inc | $20,893,024 | Low |
| 2 | FCS Group LLC | $24,954,747 | +19% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Ahern Painting Contractors Inc | 2. FCS Group LLC |
|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $20,000 | $30,000 |
| 2 | Clearing and Grubbing (201.07) | ACRE | 1 | $7,500.00 | $35,000 |
| 3 | Unclassified Excavation and Disposal (203.02) | CY | 50 | $200.00 | $150.00 |
| 4 | Embankment In Place (203.03) | CY | 100 | $100.00 | $80.00 |
| 5 | (206.04010011) | 100 | $150.00 | $600.00 | |
| 6 | (564.10010011) | 1,400 | $10.00 | $12.75 | |
| 7 | (564.10020011) | 1,400 | $100.00 | $71.50 | |
| 8 | (564.510001) | LB | 13,585 | $88.00 | $71.00 |
| 9 | Lead-Exposure Control Plan (570.01) | LS | 1 | $7,500.00 | $1,000.00 |
| 10 | Medical Testing (570.02) | DOL | 100,000 | $1.00 | $1.00 |
| 11 | Personal-Exposure-Monitoring Sample Analysis (570.03) | DOL | 79,000 | $1.00 | $1.00 |
| 12 | Decontamination Facilities (570.04) | CALENDAR WEEK | 72 | $150.00 | $100.00 |
| 13 | (570.090001) | LS | 1 | $2,000.00 | $7,000.00 |
| 14 | (570.090002) | LS | 1 | $2,000.00 | $3,000.00 |
| 15 | (570.090003) | LS | 1 | $2,000.00 | $3,000.00 |
| 16 | (570.090004) | LS | 1 | $2,000.00 | $5,000.00 |
| 17 | (570.090005) | LS | 1 | $2,000.00 | $5,000.00 |
| 18 | (570.090006) | LS | 1 | $2,000.00 | $5,000.00 |
| 19 | (570.090007) | LS | 1 | $2,000.00 | $7,000.00 |
| 20 | (570.090008) | LS | 1 | $2,000.00 | $3,000.00 |
| 21 | (570.090009) | LS | 1 | $2,000.00 | $3,000.00 |
| 22 | (570.090010) | LS | 1 | $2,000.00 | $3,000.00 |
| 23 | (570.090011) | LS | 1 | $2,000.00 | $3,000.00 |
| 24 | (570.090012) | LS | 1 | $2,000.00 | $7,000.00 |
| 25 | (570.090013) | LS | 1 | $2,000.00 | $7,000.00 |
| 26 | (570.090014) | LS | 1 | $2,000.00 | $7,000.00 |
| 27 | (570.090015) | LS | 1 | $2,000.00 | $7,000.00 |
| 28 | (570.150001) | LS | 1 | $448,250 | $495,000 |
| 29 | (570.150002) | LS | 1 | $359,580 | $250,000 |
| 30 | (570.150003) | LS | 1 | $227,692 | $250,000 |
| 31 | (570.150004) | LS | 1 | $263,356 | $245,000 |
| 32 | (570.150005) | LS | 1 | $571,817 | $480,000 |
| 33 | (570.150006) | LS | 1 | $646,852 | $540,000 |
| 34 | (570.150007) | LS | 1 | $732,865 | $750,000 |
| 35 | (570.150008) | LS | 1 | $249,398 | $200,000 |
| 36 | (570.150009) | LS | 1 | $228,426 | $150,000 |
| 37 | (570.150010) | LS | 1 | $778,809 | $600,000 |
| 38 | (570.150011) | LS | 1 | $949,578 | $600,000 |
| 39 | (570.150012) | LS | 1 | $767,411 | $450,000 |
| 40 | (570.150013) | LS | 1 | $807,760 | $450,000 |
| 41 | (570.150014) | LS | 1 | $543,355 | $355,000 |
| 42 | (570.150015) | LS | 1 | $649,439 | $401,500 |
| 43 | Disposal of Hazardous Paint Removal Waste Containing Lead (571.03) | LB | 170,000 | $0.30 | $0.16 |
| 44 | Disposal of Non-Hazardous Industrial Solid Paint Removal Waste (571.04) | LB | 170,000 | $0.30 | $0.16 |
| 45 | (573.010001) | LS | 1 | $298,833 | $1,080,000 |
| 46 | (573.010002) | LS | 1 | $239,720 | $450,000 |
| 47 | (573.010003) | LS | 1 | $151,794 | $450,000 |
| 48 | (573.010004) | LS | 1 | $175,571 | $430,000 |
| 49 | (573.010005) | LS | 1 | $381,211 | $1,040,000 |
| 50 | (573.010006) | LS | 1 | $431,234 | $1,170,000 |
| 51 | (573.010007) | LS | 1 | $488,576 | $1,300,000 |
| 52 | (573.010008) | LS | 1 | $166,265 | $430,000 |
| 53 | (573.010009) | LS | 1 | $152,284 | $395,000 |
| 54 | (573.010010) | LS | 1 | $519,206 | $1,350,000 |
| 55 | (573.010011) | LS | 1 | $633,052 | $1,350,000 |
| 56 | (573.010012) | LS | 1 | $511,607 | $975,000 |
| 57 | (573.010013) | LS | 1 | $538,507 | $975,000 |
| 58 | (573.010014) | LS | 1 | $362,237 | $600,000 |
| 59 | (573.010015) | LS | 1 | $432,959 | $700,000 |
| 60 | (585.01) | EACH | 25 | $39,000 | $25,100 |
| 61 | Removal of Rivets-Replacement with High Strength Bolts (586.05) | EACH | 610 | $90.00 | $148.00 |
| 62 | Field Drill Holes in Existing Structural Steel (586.10) | EACH | 720 | $90.00 | $148.00 |
| 63 | (589.010001) | LB | 12,350 | $37.00 | $17.00 |
| 64 | (607.41010010) | 3,200 | $10.00 | $12.00 | |
| 65 | Limestone (610.06) | LB | 50 | $2.00 | $2.50 |
| 66 | Mycorrhizal Fungi (610.0701) | LB | 50 | $10.00 | $20.00 |
| 67 | Compost (610.10) | CY | 50 | $120.00 | $1.50 |
| 68 | Mulch for Planting Type C – USDA-APHIS Protocol Wood Chips (610.1102) | CY | 200 | $80.00 | $25.00 |
| 69 | Weed Removal (610.13) | SY | 1,000 | $4.00 | $10.00 |
| 70 | Topsoil - Roadside (610.1402) | CY | 200 | $110.00 | $85.00 |
| 71 | Topsoil - Lawns (610.1403) | CY | 25 | $125.00 | $220.00 |
| 72 | Turf Establishment - Roadside (610.1601) | SY | 1,000 | $9.00 | $7.00 |
| 73 | Turf Establishment -Lawns (610.1602) | SY | 500 | $13.00 | $7.00 |
| 74 | Watering Vegetation (610.19) | 1,000 GALLONS | 200 | $160.00 | $60.00 |
| 75 | Mowing (610.21) | SY | 1,000 | $3.00 | $4.00 |
| 76 | Care of Trees Over 24” to 36” Diam. at Breast Height - Pruning (614.0431) | EACH | 25 | $950.00 | $250.00 |
| 77 | Improvement of Vegetated Areas (614.05) | SY | 200 | $20.00 | $30.00 |
| 78 | (614.060503) | EACH | 20 | $1,500.00 | $750.00 |
| 79 | Tree Root Zone Treatment (Vertical Mulching/Aeration) (614.08) | SY | 200 | $32.00 | $40.00 |
| 80 | (614.08110009) | 50 | $450.00 | $350.00 | |
| 81 | (614.08120009) | 50 | $65.00 | $200.00 | |
| 82 | (614.08210009) | 50 | $275.00 | $700.00 | |
| 83 | (614.08220009) | 50 | $30.00 | $500.00 | |
| 84 | Tree Root Pruning (614.09) | LF | 50 | $30.00 | $200.00 |
| 85 | (615.33010011) | 15 | $625.00 | $500.00 | |
| 86 | (615.33020011) | 30 | $650.00 | $1,500.00 | |
| 87 | (615.33030011) | 315 | $20.00 | $100.00 | |
| 88 | (615.43000011) | 4,400 | $12.50 | $40.00 | |
| 89 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $1,150,000 | $584,000 |
| 90 | Type III Construction Barricades (619.04) | EACH | 1,320 | $20.00 | $75.00 |
| 91 | (619.080102) | LF | 1,200 | $3.00 | $6.00 |
| 92 | (619.100101) | LF | 1,200 | $3.00 | $5.00 |
| 93 | (619.10050020) | 2,010 | $20.00 | $40.00 | |
| 94 | (619.110512) | EACH | 4 | $7,500.00 | $1,500.00 |
| 95 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 2,700 | $50.00 | $100.00 |
| 96 | Warning Lights on Temporary Positive Barriers (619.1719) | EACH | 180 | $50.00 | $40.00 |
| 97 | Temporary Impact Attenuator - Redirective (Test Level 3) (619.1803) | EACH | 2 | $25,000 | $5,000.00 |
| 98 | Temporary Sand Barrel Module (619.21) | EACH | 4 | $1,000.00 | $2,500.00 |
| 99 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $270,000 | $20,000 |
| 100 | (619.67020010) | LS | 1 | $25,000 | $7,000.00 |
| 101 | (619.70040011) | 2,400 | $25.00 | $35.00 | |
| 102 | (634.97100011) | 3,000 | $40.00 | $25.00 | |
| 103 | (634.98010011) | 200 | $10.00 | $30.00 | |
| 104 | Engineer’s Field Office – Type 5 (637.15) | MONTH | 27 | $8,000.00 | $5,280.00 |
| 105 | (637.31020020) | 27 | $1,000.00 | $1,250.00 | |
| 106 | Office Technology and Supplies (637.34) | DOL | 8,500 | $1.00 | $1.00 |
| 107 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 |
| 108 | (639.10210011) | LS | 1 | $78,000 | $80,000 |
| 109 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 1,200 | $3.00 | $6.00 |
| 110 | (691.04000020) | 109,200 | $1.00 | $1.00 | |
| 111 | (695.33110105) | LS | 1 | $5,000.00 | $5,000.00 |
| 112 | (695.33110205) | LS | 1 | $5,000.00 | $2,500.00 |
| 113 | (695.33110305) | LS | 1 | $5,000.00 | $2,500.00 |
| 114 | (695.33110405) | LS | 1 | $5,000.00 | $2,500.00 |
| 115 | (695.33110505) | LS | 1 | $5,000.00 | $2,500.00 |
| 116 | (695.33110605) | LS | 1 | $5,000.00 | $2,500.00 |
| 117 | (695.33110705) | LS | 1 | $5,000.00 | $2,500.00 |
| 118 | (695.33110805) | LS | 1 | $5,000.00 | $2,500.00 |
| 119 | (695.33110905) | LS | 1 | $5,000.00 | $2,500.00 |
| 120 | (695.33111005) | LS | 1 | $5,000.00 | $2,500.00 |
| 121 | (695.33111105) | LS | 1 | $5,000.00 | $2,500.00 |
| 122 | (695.33111205) | LS | 1 | $5,000.00 | $2,500.00 |
| 123 | (695.33111305) | LS | 1 | $5,000.00 | $2,414.00 |
| 124 | (695.33111405) | LS | 1 | $5,000.00 | $5,000.00 |
| 125 | (695.33111505) | LS | 1 | $5,000.00 | $5,000.00 |
| 126 | Field Change Payment (FCP) (697.03) | DOL | 310,000 | $1.00 | $1.00 |
| 127 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 |
| 128 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 |
| 129 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 |
| 130 | Mobilization (699.040001) | LS | 1 | $800,000 | $959,798 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of January 22, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.