Field Drill Holes in Existing Structural Steel, NYSDOT 586.10
Low bidders on NYSDOT contracts carried a median of $62.50 per EACH for this item, over the 24 months to 15 OCT 2026, across 22 low bids. Half of all 84 bids fell between $48.25 and $110.00.
- Owner
- New York State DOT
- Item
- 586.10
- Unit
- EACH
- Data through
- 15 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 13 | 13 | $50.00 | 65 | $60.00 |
| 2023 | 11 | 11 | $72.00 | 47 | $70.00 |
| 2024 | 15 | 15 | $35.00 | 54 | $60.00 |
| 2025 | 10 | 10 | $34.00 | 34 | $74.50 |
| 2026 | 9 | 9 | $75.00 | 35 | $80.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Region 08 | 5 | $65.00 | 26 | $100.00 |
| Region 11 | 4 | $70.00 | 19 | $90.00 |
| Region 05 | 5 | $30.00 | 12 | $32.50 |
Regions with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 18 to 76 | 5 | $35.00 |
| 132 to 320 | 6 | $62.50 |
| 322 to 896 | 5 | $90.00 |
| 1,190 to 56,380 | 6 | $65.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Oakgrove Construction Inc | 9 | 5 (56%) |
| Cold Spring Construction Company | 10 | 3 (30%) |
| Vector Construction Corp | 8 | 2 (25%) |
| Amstar of Western New York Inc | 7 | 2 (29%) |
| Harrison & Burrowes Bridge Constructors Inc | 6 | 2 (33%) |
| Atlas Painting & Sheeting Corporation | 8 | 1 (13%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 01 OCT 2026 | D265800 | Region 11 | 76 | $70.00 | $120.00 | 5 | Westmoreland Construction Inc | NYSDOT |
| 17 SEP 2026 | D265811 | Region 10 | 2,790 | $80.00 | $76.00 | 5 | Ahern Painting Contractors Inc | NYSDOT |
| 30 JUL 2026 | D265799 | Region 10 | 1,190 | $75.00 | $75.00 | 7 | Peter Scalamandre & Sons Inc | NYSDOT |
| 26 MAR 2026 | D265624 | Region 08 | 896 | $350.00 | $207.50 | 2 | Tully Construction Company Inc | NYSDOT |
| 12 MAR 2026 | D265700 | Region 09 | 160 | $60.00 | $78.65 | 4 | R De Vincentis Construction Inc | NYSDOT |
| 05 MAR 2026 | D265756 | Region 11 | 56,380 | $60.00 | $56.50 | 4 | FCS Group LLC | NYSDOT |
| 26 FEB 2026 | D265662 | Region 01 | 731 | $65.00 | $65.00 | 1 | D A Collins Construction Co Inc | NYSDOT |
| 26 FEB 2026 | D265729 | Region 08 | 322 | $200.00 | $85.00 | 5 | FCS Group LLC | NYSDOT |
| 22 JAN 2026 | D265631 | Region 11 | 720 | $90.00 | $119.00 | 2 | Ahern Painting Contractors Inc | NYSDOT |
| 18 DEC 2025 | D265610 | Region 05 | 640 | $25.00 | $25.00 | 2 | Oakgrove Construction Inc | NYSDOT |
| 06 NOV 2025 | D265581 | Region 05 | 50 | $33.00 | $35.00 | 3 | Amstar of Western New York Inc | NYSDOT |
| 23 OCT 2025 | D265495 | Region 11 | 3,727 | $70.00 | $93.00 | 8 | El Sol Contracting / Es II Enterprises JV | NYSDOT |
| 11 SEP 2025 | D265507 | Region 05 | 50 | $35.00 | $35.00 | 3 | Erie Painting & Maintenance Inc | NYSDOT |
| 27 MAR 2025 | D265426 | Region 05 | 10,456 | $30.00 | $30.00 | 2 | Cold Spring Construction Company | NYSDOT |
| 27 MAR 2025 | D265479 | Region 01 | 144 | $100.00 | $100.00 | 1 | Bette & Cring LLC | NYSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the NYSDOT explorer.
How these prices were read
NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NYSDOT's own: this item is compared with NYSDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the NYSDOT letting of 15 OCT 2026 and was rebuilt on 26 NOV 2026.