Westmoreland Construction Inc: NYSDOT bid record
Westmoreland Construction Inc submitted 37 bids on New York State DOT contracts in the data, from 06 JAN 2022 to 01 OCT 2026, and was the low bidder on 10 of them (27%). When it was not low, its total sat a median +21% above the low bid.
- Owner
- New York State DOT
- Low bid volume
- $110,257,883
- Latest bid
- 01 OCT 2026
- Data through
- 15 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 5 | 1 | 20% |
| 2023 | 4 | 2 | 50% |
| 2024 | 5 | 1 | 20% |
| 2025 | 9 | 3 | 33% |
| 2026 | 14 | 3 | 21% |
By region
| Region | Bids | Low bids | Win rate |
|---|---|---|---|
| Region 11 | 17 | 6 | 35% |
| Region 08 | 13 | 2 | 15% |
| Region 10 | 6 | 2 | 33% |
| Region 08, 10, 11 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Office Technology and Supplies | 637.34 | DOL | 34 | 34 (100%) | $1.00 | $1.00 |
| Field Change Payment (FCP) | 697.03 | DOL | 28 | 28 (100%) | $1.00 | $1.00 |
| Fuel Price Adjustment | 698.05 | DOL | 27 | 27 (100%) | $1.00 | $1.00 |
| Steel/Iron Price Adjustment | 698.06 | DOL | 23 | 23 (100%) | $1.00 | $1.00 |
| Asphalt Price Adjustment | 698.04 | DOL | 20 | 20 (100%) | $1.00 | $1.00 |
| Partnering Workshop | 637.35 | DOL | 12 | 12 (100%) | $1.00 | $1.00 |
| Construction Testing supplies – Consumables | 637.36 | DOL | 10 | 10 (100%) | $1.00 | $1.00 |
| 691.04000020 | 10 | 10 (100%) | $1.00 | $1.00 | ||
| 637.31020020 | 17 | 7 (41%) | $1,000.00 | $985.00 | ||
| Engineer’s Field Office – Type 3 | 637.13 | MONTH | 23 | 6 (26%) | $6,000.00 | $6,000.00 |
| Unclassified Excavation and Disposal | 203.02 | CY | 17 | 6 (35%) | $200.00 | $71.00 |
| Concrete Cylinder Curing Equipment | 637.04 | EACH | 12 | 6 (50%) | $1,975.00 | $2,800.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Constar Inc | 13 | 6 of 13 |
| Jrcruz Corp | 10 | 3 of 10 |
| H & L Contracting LLC | 5 | 4 of 5 |
| Paul J Scariano Inc | 5 | 0 of 5 |
| Bove Industries Inc | 5 | 4 of 5 |
| Tully Construction Company Inc | 5 | 2 of 5 |
| Road Safety Systems LLC | 5 | 4 of 5 |
| Es II Enterprises LLC /DBA El Sol Enterprises | 4 | 0 of 4 |
| Quintal Contracting Corp | 4 | 1 of 4 |
| Defoe Corporation | 4 | 2 of 4 |
Latest bids
| Let | Contract | Region | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 01 OCT 2026 | D265800 | Region 11 | Sign Structures Replacement | 1 of 5 | $21,414,264 | Low, 7.0% under the second |
| 17 SEP 2026 | D265820 | Region 08 | BIENNIAL GRAFFITI REMOVAL | 2 of 4 | $395,800 | +4.0% |
| 27 AUG 2026 | D265803 | Region 10 | PARK/RIDE & BIKEWAY MAINTENANCE, GRAFFITI, TREE TRIMMING. | 1 of 5 | $4,694,047 | Low, 13% under the second |
| 27 AUG 2026 | D265828 | Region 08 | Standby Where & When Highway | 4 of 6 | $6,320,996 | +10% |
| 27 AUG 2026 | D265833 | Region 10 | Curve Warning Sign Upgrades Various Highways and Roadways | 2 of 4 | $4,404,203 | +23% |
| 13 AUG 2026 | D265826 | Region 08 | CURVE WARNNG SIGN UPGRADES WESTCHESTER COUNTY | 4 of 5 | $2,844,285 | +39% |
| 13 AUG 2026 | D265827 | Region 08 | CURVE WARNING SIGN UPGRADES ROCKLAND AND ORANGE COUNTIES | 6 of 7 | $1,063,834 | +95% |
| 30 JUL 2026 | D265821 | Region 08 | 2027-2028 Structures Where & When | 6 of 6 | $3,443,008 | +10% |
| 16 JUL 2026 | D265804 | Region 10 | Overhead Sign Structure Replace Nassau & Suffolk | 4 of 5 | $7,676,768 | +33% |
| 21 MAY 2026 | D265781 | Region 08 | INTERCHANGE IMPROVEMENTS - CROSS COUNTY PARKWAY EXIT 3 | 2 of 5 | $3,366,235 | +11% |
| 26 MAR 2026 | D265624 | Region 08 | Parkway Guide Sign and Sign Structure Replacement | 2 of 2 | $20,222,222 | +24% |
| 26 MAR 2026 | D265681 | Region 11 | CONCRETE PAVEMENT PRESERVATION NASSAU CLEARVIEW & BELT PKWY | 5 of 13 | $18,695,309 | +31% |
| 12 MAR 2026 | D265665 | Region 11 | Standby Where and When Non Structural Corrective Maintenance | 4 of 5 | $21,218,004 | +11% |
| 26 FEB 2026 | D265647 | Region 08 | Wall Repair, Drainage and Pavement Improvements. | 1 of 3 | $4,241,979 | Low, 15% under the second |
| 20 NOV 2025 | D265585 | Region 10 | Bridge Cleaning and Sealing Contract Various Locations. | 5 of 5 | $6,217,718 | +54% |
| 06 NOV 2025 | D265616 | Region 08 | Job Order Contract Highway Maintenance, Various Locations | 2 of 4 | $2,378,000 | +2.0% |
| 23 OCT 2025 | D265569 | Region 08 | WORK ZONE TRAFFIC CONTROL FOR PROJECT DEVELOPMENT. | 2 of 2 | $270,800 | +32% |
| 11 SEP 2025 | D265557 | Region 08 | Standby Where & When Highway, Region-Wide | 6 of 6 | $6,634,317 | +12% |
| 24 JUL 2025 | D265488 | Region 11 | Standby Where & When General Repairs on Highways and Bridges | 1 of 7 | $18,510,478 | Low, 13% under the second |
| 24 JUL 2025 | D265502 | Region 10 | TREE TRIMMING / TREE REMOVAL | 1 of 5 | $7,143,235 | Low, 12% under the second |
| 05 JUN 2025 | D265509 | Region 08, 10, 11 | Sign Requirements Contract, Downstate, Regions 8, 10 and 11 | 2 of 2 | $4,141,650 | +25% |
| 23 JAN 2025 | D265357 | Region 11 | RETAINING WALLS REHAB & CORRECTIVE MAINTENANCE IN NYC | 2 of 3 | $37,692,666 | +3.0% |
| 23 JAN 2025 | D265364 | Region 11 | BRIDGE/HIGHWAY - DRAINAGE CLEANING - Various Locations | 1 of 3 | $5,363,333 | Low, 8.0% under the second |
| 21 NOV 2024 | D265342 | Region 08 | REPAIR OVERHEAD SIGN STRUCTURES | 2 of 3 | $3,143,233 | +18% |
| 26 SEP 2024 | D265292 | Region 11 | STANDBY WHERE & WHEN RETAINING WALLS PRESERVATION | 3 of 6 | $4,704,579 | +7.0% |
How this record was read
NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
- Every bid counted here matched its published total to within one dollar; NYSDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.