NYSDOT contract D265804 bid tabulation
Overhead Sign Structure Replace Nassau & Suffolk. Let by New York State DOT on July 16, 2026, Nassau, Suffolk, Region 10. 5 bids received; low bid $5,756,313 by United Fence and Guard Rail Corp.
- Owner
- New York State DOT
- Letting
- 16 JUL 2026
- Pay items
- 106
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | United Fence and Guard Rail Corp | $5,756,313 | Low |
| 2 | H & L Contracting LLC | $7,574,812 | +32% |
| 3 | Constar Inc | $7,597,840 | +32% |
| 4 | Westmoreland Construction Inc | $7,676,768 | +33% |
| 5 | Es II Enterprises LLC /DBA El Sol Enterprises | $12,327,000 | +114% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. United Fence and Guard Rail Corp | 2. H & L Contracting LLC | 3. Constar Inc | 4. Westmoreland Construction Inc | 5. Es II Enterprises LLC /DBA El Sol Enterprises |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $20,000 | $25,000 | $10,000 | $15,000 | $106,939 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 75 | $250.00 | $500.00 | $200.00 | $325.00 | $850.00 |
| 3 | Conduit Excavation and Backfill including Surface Restoration (206.03) | LF | 190 | $75.00 | $220.00 | $80.00 | $400.00 | $130.00 |
| 4 | (206.03120010) | 270 | $90.00 | $88.00 | $200.00 | $70.00 | $88.00 | |
| 5 | Test Pit Excavation (206.05) | EACH | 18 | $1,000.00 | $1,600.00 | $1,500.00 | $3,000.00 | $4,000.00 |
| 6 | (304.10119917) | 4 | $500.00 | $60.00 | $100.00 | $400.00 | $300.00 | |
| 7 | (404.0981) | TON | 9 | $300.00 | $800.00 | $400.00 | $1,000.00 | $510.00 |
| 8 | (404.1989) | TON | 2 | $300.00 | $1,500.00 | $400.00 | $800.00 | $665.00 |
| 9 | (404.2589) | TON | 5 | $300.00 | $1,500.00 | $400.00 | $800.00 | $555.00 |
| 10 | Diluted Tack Coat (407.0102) | GAL | 9 | $50.00 | $10.00 | $10.00 | $25.00 | $30.00 |
| 11 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 208 | $5.00 | $25.00 | $6.00 | $20.00 | $45.00 |
| 12 | (520.09000010) | 208 | $10.00 | $5.00 | $5.00 | $30.00 | $20.00 | |
| 13 | Temporary Timber Sheeting (552.12) | SF | 500 | $1.00 | $11.74 | $10.00 | $10.00 | $22.00 |
| 14 | Concrete for Structures, Performance (555.0021) | CY | 20 | $1,700.00 | $2,280.00 | $6,500.00 | $6,000.00 | $4,000.00 |
| 15 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $15.00 | $15.00 | $15.00 | $15.00 | $15.00 |
| 16 | Epoxy-Coated Steel Fabric Reinforcement (556.0102) | SY | 13 | $60.00 | $100.00 | $35.00 | $50.00 | $52.00 |
| 17 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 209 | $8.00 | $10.00 | $5.00 | $20.00 | $15.00 |
| 18 | Box Beam Median Barrier (606.11) | LF | 60 | $125.00 | $133.00 | $110.00 | $100.00 | $166.00 |
| 19 | HPBO (Mod.) Corrugated Beam Guide Railing (606.2701) | LF | 735 | $55.00 | $42.00 | $75.00 | $100.00 | $53.00 |
| 20 | Anchorage Units for HPBO (Mod.) Corrugated Beam Guide Railing (606.2703) | EACH | 3 | $4,000.00 | $4,200.00 | $6,000.00 | $5,000.00 | $5,200.00 |
| 21 | HPBO (Mod.) Corrugated Beam Median Barrier End Terminal (Energy-Absorbing) (606.28) | EACH | 1 | $18,000 | $10,200 | $14,500 | $7,500.00 | $12,750 |
| 22 | (606.30330008) | 86 | $900.00 | $1,265.00 | $1,000.00 | $1,700.00 | $4,000.00 | |
| 23 | Removing and Disposing HPBO (Mod.) Corrugated Beam Guide Railing (606.7101) | LF | 403 | $15.00 | $12.00 | $25.00 | $20.00 | $15.00 |
| 24 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 156 | $15.00 | $17.00 | $15.00 | $20.00 | $22.00 |
| 25 | Removing and Disposing Box Beam Median Barrier (606.74) | LF | 250 | $15.00 | $22.00 | $12.00 | $20.00 | $29.00 |
| 26 | Removing and Disposing Concrete Barrier (606.75) | LF | 78 | $50.00 | $115.00 | $100.00 | $600.00 | $236.00 |
| 27 | Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920) | EACH | 4 | $300.00 | $56.00 | $500.00 | $1,500.00 | $71.00 |
| 28 | Removing and Disposing Anchorage Units for HPBO(Mod) Corrugated Beam Guide Railing (606.7941) | EACH | 2 | $300.00 | $340.00 | $500.00 | $1,500.00 | $422.00 |
| 29 | Transition Between Box Beam Median Barrier and Single Slope Concrete Median Barrier (606.8805) | EACH | 1 | $75,000 | $12,000 | $30,000 | $20,000 | $80,000 |
| 30 | Transition: HPBO (Mod.) Corrugated Beam Median Barrier to Single Slope Concrete Median Barrier (606.8906) | EACH | 1 | $25,000 | $7,800.00 | $30,000 | $20,000 | $80,000 |
| 31 | (607.30010010) | 20 | $100.00 | $99.00 | $125.00 | $50.00 | $120.00 | |
| 32 | (607.31020010) | 80 | $100.00 | $99.00 | $100.00 | $75.00 | $123.00 | |
| 33 | (607.62000010) | 100 | $20.00 | $12.00 | $18.00 | $25.00 | $15.00 | |
| 34 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 85 | $450.00 | $650.00 | $550.00 | $600.00 | $500.00 |
| 35 | (609.04010510) | 40 | $250.00 | $105.00 | $70.00 | $250.00 | $120.00 | |
| 36 | Topsoil - Roadside (610.1402) | CY | 13 | $200.00 | $375.00 | $150.00 | $125.00 | $200.00 |
| 37 | Turf Establishment - Roadside (610.1601) | SY | 115 | $25.00 | $3.00 | $12.00 | $25.00 | $18.00 |
| 38 | (614.060402) | EACH | 2 | $4,000.00 | $3,300.00 | $2,500.00 | $2,500.00 | $4,000.00 |
| 39 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $325,000 | $675,000 | $1,000,000 | $350,000 | $2,700,000 |
| 40 | Type III Construction Barricades (619.04) | EACH | 75 | $25.00 | $160.00 | $105.00 | $200.00 | $165.00 |
| 41 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 42,110 | $3.75 | $3.50 | $3.75 | $3.00 | $4.00 |
| 42 | (619.100102) | LF | 74,560 | $0.90 | $0.85 | $1.00 | $2.00 | $1.00 |
| 43 | (619.10050020) | 550 | $1.00 | $5.00 | $35.00 | $25.00 | $40.00 | |
| 44 | (619.110943) | EACH | 2 | $10,000 | $55,000 | $15,000 | $7,500.00 | $4,800.00 |
| 45 | (619.111133) | EACH | 6 | $3,000.00 | $60,000 | $15,000 | $7,500.00 | $12,500 |
| 46 | Temporary Positive Barrier – Category 4 (Pinning Permitted) (619.1714) | LF | 3,540 | $60.00 | $32.00 | $100.00 | $80.00 | $80.00 |
| 47 | Warning Lights on Temporary Positive Barriers (619.1719) | EACH | 116 | $50.00 | $225.00 | $75.00 | $25.00 | $30.00 |
| 48 | Temporary Impact Attenuator - Redirective (Test Level 3) (619.1803) | EACH | 8 | $5,000.00 | $15,000 | $9,000.00 | $18,000 | $10,000 |
| 49 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $25,000 | $100,000 | $250,000 | $175,000 | $500,000 |
| 50 | Survey Operations (625.01) | LS | 1 | $45,000 | $5,000.00 | $100,000 | $100,000 | $400,000 |
| 51 | (634.10010015) | LS | 1 | $12,000 | $10,500 | $12,000 | $50,000 | $30,000 |
| 52 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $500.00 | $3,000.00 | $2,500.00 | $1,000.00 | $3,000.00 |
| 53 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 18 | $5,300.00 | $6,500.00 | $5,000.00 | $6,000.00 | $7,000.00 |
| 54 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 55 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 56 | Anchor Bolts (644.11) | LB | 5,400 | $13.00 | $10.56 | $15.00 | $20.00 | $25.00 |
| 57 | Drilled Shaft for Overhead Sign Structures (644.20) | CY | 226 | $3,000.00 | $4,200.00 | $4,000.00 | $5,400.00 | $10,000 |
| 58 | (644.421025) | EACH | 1 | $92,500 | $125,000 | $105,000 | $120,000 | $110,000 |
| 59 | (644.432030) | EACH | 1 | $104,000 | $165,000 | $125,000 | $150,000 | $140,000 |
| 60 | (644.432060) | EACH | 1 | $112,000 | $165,000 | $140,000 | $150,000 | $160,000 |
| 61 | (644.432560) | EACH | 1 | $125,000 | $185,000 | $140,000 | $200,000 | $170,000 |
| 62 | (644.433030) | EACH | 1 | $152,000 | $195,000 | $155,000 | $215,000 | $195,000 |
| 63 | (644.433060) | EACH | 1 | $155,000 | $200,000 | $135,000 | $215,000 | $205,000 |
| 64 | (644.434560) | EACH | 1 | $255,000 | $350,000 | $265,000 | $275,000 | $330,000 |
| 65 | (644.435060) | EACH | 1 | $290,000 | $390,000 | $295,000 | $330,000 | $385,000 |
| 66 | (644.435590) | EACH | 1 | $325,000 | $405,000 | $350,000 | $390,000 | $410,000 |
| 67 | Performance Concrete Quality Adjustment (644.99) | QUALITY UNIT | 1 | $12.50 | $12.50 | $12.50 | $12.50 | $12.50 |
| 68 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 31 | $65.00 | $31.00 | $65.00 | $90.00 | $38.00 |
| 69 | Ground-Mounted Sign Panels greater than 32 SF with Z-bars (645.5103) | SF | 56 | $65.00 | $32.00 | $75.00 | $90.00 | $40.00 |
| 70 | (645.52020110) | 170 | $75.00 | $38.00 | $75.00 | $100.00 | $47.00 | |
| 71 | (645.52030110) | 974 | $85.00 | $39.00 | $100.00 | $100.00 | $48.00 | |
| 72 | Overhead Sign Panels (645.61) | SF | 914 | $45.00 | $40.00 | $95.00 | $60.00 | $50.00 |
| 73 | (645.62000110) | 1,675 | $55.00 | $50.00 | $105.00 | $65.00 | $58.00 | |
| 74 | Type A Sign Posts (645.81) | EACH | 9 | $300.00 | $300.00 | $275.00 | $750.00 | $375.00 |
| 75 | High-Capacity Type A Sign Posts with Soil Plates Only (645.8106) | EACH | 2 | $2,000.00 | $1,300.00 | $2,000.00 | $2,000.00 | $1,581.00 |
| 76 | (645.830202) | EACH | 2 | $2,500.00 | $2,400.00 | $2,200.00 | $2,500.00 | $2,762.00 |
| 77 | (645.85030210) | 2 | $2,600.00 | $3,600.00 | $4,000.00 | $3,500.00 | $4,361.00 | |
| 78 | (645.85040210) | 10 | $3,200.00 | $4,200.00 | $4,200.00 | $4,200.00 | $4,888.00 | |
| 79 | (645.85050210) | 2 | $4,500.00 | $6,500.00 | $6,200.00 | $5,000.00 | $6,820.00 | |
| 80 | Removal of Cantilever Overhead Sign Panel(s), Structure, and Foundations (647.20) | EACH | 8 | $18,000 | $14,000 | $10,000 | $10,000 | $20,000 |
| 81 | Removal of Single Span Overhead Sign Panel(s), Structure, and Foundations (647.21) | EACH | 9 | $22,500 | $25,000 | $12,000 | $7,500.00 | $30,000 |
| 82 | Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51) | EACH | 3 | $400.00 | $29.00 | $200.00 | $500.00 | $36.00 |
| 83 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 1 | $400.00 | $29.00 | $400.00 | $500.00 | $36.00 |
| 84 | (657.12020010) | 5 | $50,000 | $55,000 | $60,000 | $70,000 | $65,000 | |
| 85 | (662.99030010) | LS | 1 | $9,300.00 | $9,300.00 | $9,300.00 | $9,300.00 | $9,300.00 |
| 86 | Ground Wire No. 6 AWG. (670.7501) | LF | 270 | $5.00 | $4.00 | $15.00 | $6.00 | $4.00 |
| 87 | (680.51050010) | 1 | $5,000.00 | $2,700.00 | $3,000.00 | $8,000.00 | $2,700.00 | |
| 88 | (680.520103) | LF | 110 | $43.00 | $41.00 | $50.00 | $115.00 | $42.00 |
| 89 | (680.520106) | LF | 110 | $48.00 | $46.00 | $60.00 | $115.00 | $47.00 |
| 90 | (680.520110) | LF | 160 | $80.00 | $77.00 | $100.00 | $225.00 | $77.00 |
| 91 | (680.520205) | LF | 60 | $40.00 | $38.00 | $50.00 | $120.00 | $38.00 |
| 92 | (680.520405) | LF | 60 | $80.00 | $75.00 | $100.00 | $120.00 | $75.00 |
| 93 | (680.77000105) | 1 | $7,000.00 | $6,400.00 | $8,000.00 | $17,500 | $6,400.00 | |
| 94 | (680.83200010) | LS | 1 | $20,000 | $145,000 | $15,000 | $25,000 | $14,500 |
| 95 | (680.99910011) | LS | 1 | $3,500.00 | $3,194.00 | $15,000 | $25,000 | $3,200.00 |
| 96 | (683.07100010) | 135 | $8.00 | $6.60 | $15.00 | $45.00 | $7.00 | |
| 97 | (683.30110010) | 6 | $15,000 | $13,298 | $15,000 | $15,000 | $14,000 | |
| 98 | (683.84029310) | 1 | $125,000 | $98,772 | $135,000 | $30,000 | $100,000 | |
| 99 | (685.07200110) | 1,500 | $1.00 | $1.75 | $1.50 | $15.00 | $1.25 | |
| 100 | (685.07200610) | 550 | $1.00 | $1.75 | $1.50 | $15.00 | $1.25 | |
| 101 | (691.04000020) | 28,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 102 | Field Change Payment (FCP) (697.03) | DOL | 442,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 103 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 104 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 105 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 106 | Mobilization (699.040001) | LS | 1 | $221,397 | $285,000 | $292,222 | $285,390 | $470,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of July 16, 2026. Compiled by Mirage Metrics.