Constar Inc: NYSDOT bid record
Constar Inc submitted 44 bids on New York State DOT contracts in the data, from 20 JAN 2022 to 01 OCT 2026, and was the low bidder on 13 of them (30%). When it was not low, its total sat a median +10% above the low bid.
- Owner
- New York State DOT
- Low bid volume
- $99,456,144
- Latest bid
- 01 OCT 2026
- Data through
- 15 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 8 | 2 | 25% |
| 2023 | 12 | 5 | 42% |
| 2024 | 8 | 2 | 25% |
| 2025 | 8 | 2 | 25% |
| 2026 | 8 | 2 | 25% |
By region
| Region | Bids | Low bids | Win rate |
|---|---|---|---|
| Region 10 | 29 | 4 | 14% |
| Region 11 | 15 | 9 | 60% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Office Technology and Supplies | 637.34 | DOL | 43 | 43 (100%) | $1.00 | $1.00 |
| Field Change Payment (FCP) | 697.03 | DOL | 37 | 37 (100%) | $1.00 | $1.00 |
| Fuel Price Adjustment | 698.05 | DOL | 37 | 37 (100%) | $1.00 | $1.00 |
| Steel/Iron Price Adjustment | 698.06 | DOL | 35 | 35 (100%) | $1.00 | $1.00 |
| Construction Testing supplies – Consumables | 637.36 | DOL | 35 | 35 (100%) | $1.00 | $1.00 |
| Asphalt Price Adjustment | 698.04 | DOL | 31 | 31 (100%) | $1.00 | $1.00 |
| Engineer’s Field Office – Type 3 | 637.13 | MONTH | 37 | 28 (76%) | $4,000.00 | $6,000.00 |
| 691.04000020 | 19 | 19 (100%) | $1.00 | $1.00 | ||
| Pavement Patching (Force Acount) | 619.2601 | DOL | 13 | 13 (100%) | $1.00 | $1.00 |
| Unclassified Excavation and Disposal | 203.02 | CY | 29 | 12 (41%) | $100.00 | $71.00 |
| Type III Construction Barricades | 619.04 | EACH | 28 | 11 (39%) | $90.00 | $115.00 |
| Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips | 608.000013 | QUALITY UNIT | 11 | 11 (100%) | $125.00 | $90.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Quintal Contracting Corp | 18 | 4 of 18 |
| H & L Contracting LLC | 15 | 11 of 15 |
| Westmoreland Construction Inc | 13 | 7 of 13 |
| GGG Construction Corp | 12 | 2 of 12 |
| Jrcruz Corp | 11 | 1 of 11 |
| United Fence and Guard Rail Corp | 11 | 9 of 11 |
| Bove Industries Inc | 10 | 5 of 10 |
| Liberty II Sweeping and Maintenance Inc | 7 | 5 of 7 |
| Defoe Corporation | 7 | 2 of 7 |
| Triumph Construction Corp | 7 | 3 of 7 |
Latest bids
| Let | Contract | Region | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 01 OCT 2026 | D265840 | Region 10 | Crack Sealing and Joint Overlay Repairs Various Locations. | 2 of 4 | $1,499,725 | +12% |
| 27 AUG 2026 | D265803 | Region 10 | PARK/RIDE & BIKEWAY MAINTENANCE, GRAFFITI, TREE TRIMMING. | 4 of 5 | $5,722,217 | +22% |
| 27 AUG 2026 | D265833 | Region 10 | Curve Warning Sign Upgrades Various Highways and Roadways | 3 of 4 | $4,881,080 | +36% |
| 16 JUL 2026 | D265804 | Region 10 | Overhead Sign Structure Replace Nassau & Suffolk | 3 of 5 | $7,597,840 | +32% |
| 26 MAR 2026 | D265681 | Region 11 | CONCRETE PAVEMENT PRESERVATION NASSAU CLEARVIEW & BELT PKWY | 8 of 13 | $22,029,685 | +55% |
| 12 MAR 2026 | D265664 | Region 11 | Bridge Expansion Joint Repairs and Replacements in NYC | 1 of 2 | $11,348,710 | Low, 121% under the second |
| 26 FEB 2026 | D265699 | Region 10 | CONCRETE PAVEMENT RESTORATION SOUTHERN STATE PKWY (908M). | 3 of 7 | $15,858,412 | +6.0% |
| 05 FEB 2026 | D265685 | Region 10 | Crack Sealing & Joint Overlay Repairs- I-495 Exit 48 to 64 | 1 of 4 | $3,644,572 | Low, 13% under the second |
| 18 DEC 2025 | D265605 | Region 11 | BRIDGE MAINTENANCE - Expansion Joint Repairs and Replacement | 1 of 6 | $9,248,088 | Low, 4.0% under the second |
| 20 NOV 2025 | D265585 | Region 10 | Bridge Cleaning and Sealing Contract Various Locations. | 2 of 5 | $4,377,548 | +8.0% |
| 21 AUG 2025 | D265548 | Region 10 | CRACK SEALING & JOINT OVERLAY REPAIR - VARIOUS LOCATIONS. | 1 of 3 | $2,129,521 | Low, 8.0% under the second |
| 07 AUG 2025 | D265528 | Region 10 | Sign Requirements Contract - Various Locations | 2 of 2 | $3,856,239 | +9.0% |
| 24 JUL 2025 | D265488 | Region 11 | Standby Where & When General Repairs on Highways and Bridges | 5 of 7 | $24,183,558 | +31% |
| 24 JUL 2025 | D265502 | Region 10 | TREE TRIMMING / TREE REMOVAL | 4 of 5 | $8,739,710 | +22% |
| 10 JUL 2025 | D265527 | Region 10 | GUIDERAIL REHABILITATION VARIOUS LOCATIONS | 3 of 3 | $3,342,018 | +29% |
| 20 FEB 2025 | D265382 | Region 10 | I-495 Sound Barrier Requirements, Exits 49-57, | 8 of 11 | $13,364,839 | +50% |
| 12 SEP 2024 | D265270 | Region 10 | GUIDE RAIL - RUSTIC RAIL REPLACEMENT - Various Locations | 2 of 3 | $13,620,566 | +8.0% |
| 11 JUL 2024 | D265269 | Region 10 | GUIDE RAIL REPLACEMENT - Various Locations. | 3 of 4 | $3,390,705 | +6.0% |
| 11 JUL 2024 | D265275 | Region 11 | LANDSCAPE REQUIREMENTS CONTRACT AT VARIOUS LOCATIONS | 1 of 3 | $4,437,760 | Low, 3.0% under the second |
| 28 MAR 2024 | D265215 | Region 10 | Crack Sealing & Joint Overlay Repair Contract Various Towns | 3 of 4 | $6,930,024 | +4.0% |
| 14 MAR 2024 | D265040 | Region 10 | Rustic Rail Replacement Various Locations Nassau Suffolk | 2 of 3 | $7,153,313 | +3.0% |
| 08 FEB 2024 | D265150 | Region 11 | Crack and Joint Sealing at Bronx, Kings, New York & Queens | 1 of 4 | $1,460,575 | Low, 6.0% under the second |
| 25 JAN 2024 | D265047 | Region 10 | Guide Rail Rehabilitation - Nassau & Suffolk Counties | 2 of 3 | $4,166,525 | +12% |
| 11 JAN 2024 | D265174 | Region 11 | HIGHWAY - NON-STRUCTURE MAINTENANCE - Where & When | 3 of 6 | $26,830,564 | +6.0% |
| 14 DEC 2023 | D265090 | Region 11 | Sign Panel Replacements at Rte-9A, BQE, LIE and GCP | 1 of 6 | $3,443,410 | Low, 10% under the second |
How this record was read
NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
- Every bid counted here matched its published total to within one dollar; NYSDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.