NYSDOT contract D265605 bid tabulation
BRIDGE MAINTENANCE - Expansion Joint Repairs and Replacement. Let by New York State DOT on December 18, 2025, Bronx, Kings, New York, Queens,, Region 11. 6 bids received; low bid $9,248,088 by Constar Inc.
- Owner
- New York State DOT
- Letting
- 18 DEC 2025
- Pay items
- 56
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Constar Inc | $9,248,088 | Low |
| 2 | Es II Enterprises LLC /DBA El Sol Enterprises | $9,617,941 | +4.0% |
| 3 | Quintal Contracting Corp | $12,887,401 | +39% |
| 4 | Triumph Construction Corp | $16,380,414 | +77% |
| 5 | Jrcruz Corp | $19,367,976 | +109% |
| 6 | Paul J Scariano Inc | $21,327,000 | +131% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Constar Inc | 2. Es II Enterprises LLC /DBA El Sol Enterprises | 3. Quintal Contracting Corp | 4. Triumph Construction Corp | 5. Jrcruz Corp | 6. Paul J Scariano Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.07) | ACRE | 1 | $5,000.00 | $2,000.00 | $38,000 | $9,000.00 | $10,000 | $10,000 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 50 | $40.00 | $50.00 | $200.00 | $380.00 | $125.00 | $500.00 |
| 3 | Embankment In Place (203.03) | CY | 100 | $30.00 | $50.00 | $95.00 | $160.00 | $75.00 | $250.00 |
| 4 | (206.04010011) | 100 | $30.00 | $50.00 | $85.00 | $106.00 | $200.00 | $150.00 | |
| 5 | (404.0001) | TON | 7 | $213.00 | $213.00 | $213.00 | $213.00 | $213.00 | $213.00 |
| 6 | (404.0981) | TON | 126 | $100.00 | $200.00 | $375.00 | $515.00 | $500.00 | $500.00 |
| 7 | Diluted Tack Coat (407.0102) | GAL | 120 | $5.00 | $5.00 | $30.00 | $32.00 | $50.00 | $75.00 |
| 8 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 1,205 | $10.00 | $10.00 | $45.00 | $27.00 | $50.00 | $100.00 |
| 9 | Epoxy-Coated Steel Fabric Reinforcement (556.0102) | SY | 17 | $100.00 | $20.00 | $100.00 | $11.00 | $500.00 | $250.00 |
| 10 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 11,308 | $2.00 | $5.00 | $2.50 | $5.00 | $5.00 | $10.00 |
| 11 | Bridge Joint Header (567.62) | CF | 11,317 | $115.00 | $100.00 | $350.00 | $345.00 | $425.00 | $200.00 |
| 12 | Bridge Joint Seal (567.63) | LF | 21,670 | $90.00 | $130.00 | $95.00 | $240.00 | $300.00 | $100.00 |
| 13 | Performance Concrete Quality Adjustment (567.99) | QUALITY UNIT | 1 | $39.86 | $39.86 | $39.86 | $39.86 | $39.86 | $39.86 |
| 14 | Removal of Structural Concrete (580.01) | CY | 419 | $800.00 | $1,000.00 | $3,200.00 | $5,588.00 | $2,325.00 | $1,500.00 |
| 15 | Drilling and Grouting Bolts or Reinforcing Bars (with Non-Destructive Investigation) (586.0202) | EACH | 3,298 | $30.00 | $35.00 | $82.00 | $46.00 | $150.00 | $200.00 |
| 16 | (607.41010010) | 200 | $8.00 | $20.00 | $50.00 | $24.00 | $50.00 | $50.00 | |
| 17 | Limestone (610.06) | LB | 50 | $1.00 | $2.00 | $15.00 | $8.00 | $6.50 | $150.00 |
| 18 | Mycorrhizal Fungi (610.0701) | LB | 50 | $5.00 | $25.00 | $50.00 | $57.00 | $46.00 | $150.00 |
| 19 | Compost (610.10) | CY | 50 | $5.00 | $20.00 | $75.00 | $88.00 | $70.00 | $150.00 |
| 20 | Mulch for Planting Type C – USDA-APHIS Protocol Wood Chips (610.1102) | CY | 200 | $20.00 | $70.00 | $68.00 | $74.00 | $59.00 | $150.00 |
| 21 | Weed Removal (610.13) | SY | 1,000 | $1.00 | $20.00 | $15.00 | $3.00 | $2.50 | $25.00 |
| 22 | Topsoil - Roadside (610.1402) | CY | 200 | $40.00 | $80.00 | $68.00 | $147.00 | $110.00 | $150.00 |
| 23 | Turf Establishment - Roadside (610.1601) | SY | 500 | $1.00 | $4.00 | $8.00 | $8.00 | $6.00 | $35.00 |
| 24 | Watering Vegetation (610.19) | 1,000 GALLONS | 200 | $1.00 | $1.00 | $500.00 | $245.00 | $200.00 | $150.00 |
| 25 | Mowing (610.21) | SY | 500 | $1.00 | $10.00 | $2.00 | $4.00 | $3.00 | $30.00 |
| 26 | Care of Trees Over 24” to 36” Diam. at Breast Height - Pruning (614.0431) | EACH | 25 | $200.00 | $500.00 | $1,000.00 | $982.00 | $750.00 | $750.00 |
| 27 | Improvement of Vegetated Areas (614.05) | SY | 200 | $2.00 | $5.00 | $30.00 | $16.00 | $13.00 | $75.00 |
| 28 | (614.060503) | EACH | 20 | $250.00 | $1,000.00 | $1,800.00 | $2,781.00 | $3,800.00 | $1,500.00 |
| 29 | Tree Root Zone Treatment (Vertical Mulching/Aeration) (614.08) | SY | 200 | $5.00 | $15.00 | $50.00 | $82.00 | $13.00 | $50.00 |
| 30 | (614.08110009) | 50 | $20.00 | $100.00 | $150.00 | $491.00 | $500.00 | $400.00 | |
| 31 | (614.08210009) | 50 | $20.00 | $100.00 | $250.00 | $245.00 | $500.25 | $1,500.00 | |
| 32 | Tree Root Pruning (614.09) | LF | 50 | $5.00 | $150.00 | $200.00 | $982.00 | $65.00 | $100.00 |
| 33 | (615.33010011) | 20 | $50.00 | $200.00 | $550.00 | $746.00 | $300.00 | $500.00 | |
| 34 | (615.33020011) | 100 | $50.00 | $200.00 | $600.00 | $746.00 | $400.00 | $750.00 | |
| 35 | (615.43000011) | 200 | $5.00 | $20.00 | $20.00 | $75.00 | $10.00 | $250.00 | |
| 36 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $3,000,000 | $2,500,000 | $2,200,000 | $1,257,000 | $3,000,000 | $10,000,000 |
| 37 | Type III Construction Barricades (619.04) | EACH | 200 | $80.00 | $30.00 | $100.00 | $199.00 | $900.00 | $250.00 |
| 38 | (619.10050020) | 589 | $10.00 | $30.00 | $10.00 | $48.00 | $210.00 | $100.00 | |
| 39 | (619.110511) | EACH | 4 | $15,000 | $5,000.00 | $5,000.00 | $37,398 | $10,000 | $40,000 |
| 40 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $700,000 | $600,000 | $625,000 | $375,000 | $500,000 | $1,761,539 |
| 41 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $2,500.00 | $500.00 | $3,000.00 | $10,482 | $5,000.00 | $7,500.00 |
| 42 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 36 | $5,000.00 | $6,000.00 | $5,000.00 | $14,000 | $8,250.00 | $20,000 |
| 43 | (637.31020020) | 36 | $950.00 | $950.00 | $950.00 | $950.00 | $950.00 | $950.00 | |
| 44 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 45 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 46 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 47 | (639.10210011) | LS | 1 | $75,000 | $75,000 | $75,000 | $75,000 | $75,000 | $75,000 |
| 48 | (675.99000023) | 41,800 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 49 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 1,400 | $2.00 | $6.00 | $6.00 | $12.00 | $6.50 | $10.00 |
| 50 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 2,905 | $2.00 | $6.00 | $6.00 | $12.00 | $6.50 | $10.00 |
| 51 | (691.04000020) | 151,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 52 | Field Change Payment (FCP) (697.03) | DOL | 820,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 53 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 54 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 55 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 56 | Mobilization (699.040001) | LS | 1 | $355,696 | $360,000 | $495,669 | $615,000 | $744,595 | $800,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of December 18, 2025. Compiled by Mirage Metrics.