NYSDOT contract D265699 bid tabulation
CONCRETE PAVEMENT RESTORATION SOUTHERN STATE PKWY (908M). Let by New York State DOT on February 26, 2026, Suffolk, Region 10. 7 bids received; low bid $14,971,643 by H & L Contracting LLC.
- Owner
- New York State DOT
- Letting
- 26 FEB 2026
- Pay items
- 67
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | H & L Contracting LLC | $14,971,643 | Low |
| 2 | Bove Industries Inc | $15,392,862 | +3.0% |
| 3 | Constar Inc | $15,858,412 | +6.0% |
| 4 | GGG Construction Corp | $16,907,910 | +13% |
| 5 | Peter Scalamandre & Sons Inc | $17,636,713 | +18% |
| 6 | Tully Construction Company Inc | $17,968,899 | +20% |
| 7 | Grace Industries LLC | $19,596,089 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. H & L Contracting LLC | 2. Bove Industries Inc | 3. Constar Inc | 4. GGG Construction Corp | 5. Peter Scalamandre & Sons Inc | 6. Tully Construction Company Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Unclassified Excavation and Disposal (203.02) | CY | 218 | $35.00 | $175.00 | $336.00 | $50.00 | $265.00 | $780.00 |
| 2 | (209.11010024) | 20 | $240.00 | $1,000.00 | $500.00 | $50.00 | $300.00 | $100.00 | |
| 3 | (304.00010018) | 154,110 | $1.00 | $2.00 | $0.80 | $1.00 | $1.00 | $1.00 | |
| 4 | (304.10119917) | 176 | $80.00 | $30.00 | $77.00 | $125.00 | $50.00 | $45.00 | |
| 5 | (404.0189) | TON | 74 | $275.00 | $200.00 | $250.00 | $300.00 | $275.00 | $545.00 |
| 6 | (404.0981) | TON | 21 | $1,500.00 | $300.00 | $250.00 | $300.00 | $714.00 | $340.00 |
| 7 | (404.1989) | TON | 74 | $160.00 | $300.00 | $250.00 | $300.00 | $400.00 | $340.00 |
| 8 | (404.90710218) | 111 | $750.00 | $800.00 | $600.00 | $500.00 | $680.00 | $800.00 | |
| 9 | Diluted Tack Coat (407.0102) | GAL | 21 | $3.00 | $10.00 | $25.00 | $50.00 | $61.00 | $5.00 |
| 10 | (490.17011018) | 1,249 | $22.00 | $20.00 | $35.00 | $25.00 | $30.00 | $24.00 | |
| 11 | (502.10010018) | LS | 1 | $150,000 | $250,000 | $100,000 | $50,000 | $80,000 | $26,500 |
| 12 | (502.90010018) | 13,510 | $8.00 | $8.50 | $10.00 | $10.00 | $12.00 | $10.00 | |
| 13 | Sealing Transverse Joints- Highway Joint Sealant (502.9210) | LF | 25,116 | $8.00 | $8.75 | $10.00 | $10.00 | $9.00 | $10.00 |
| 14 | Sealing Longitudinal Joints-Highway Joint Sealant (502.9310) | LF | 22,803 | $9.50 | $9.00 | $8.00 | $10.00 | $11.00 | $10.00 |
| 15 | Production Grinding – Pavement Preservation with Slurry Removal (505.0402) | SY | 26,600 | $13.25 | $14.00 | $10.20 | $10.75 | $13.00 | $18.00 |
| 16 | Smoothness Quality Adjustment (505.0403) | QUALITY UNIT | 2,660 | $12.00 | $12.00 | $12.00 | $12.00 | $12.00 | $12.00 |
| 17 | (510.00210018) | 3,634 | $755.00 | $1,543.00 | $1,100.00 | $1,355.00 | $880.00 | $1,000.00 | |
| 18 | (510.02210018) | 133 | $850.00 | $1,550.00 | $1,100.00 | $1,500.00 | $820.00 | $1,000.00 | |
| 19 | (510.20000018) | 16,947 | $150.00 | $20.00 | $150.00 | $100.00 | $110.00 | $60.00 | |
| 20 | (510.81000018) | 17,609 | $42.00 | $20.00 | $35.00 | $30.00 | $38.00 | $50.00 | |
| 21 | (510.91000018) | 3,892 | $11.00 | $15.00 | $20.00 | $25.00 | $7.00 | $25.00 | |
| 22 | (511.50000018) | 10,911 | $195.00 | $175.00 | $220.00 | $273.00 | $310.00 | $200.00 | |
| 23 | (520.05000010) | 1,000 | $5.00 | $8.00 | $6.00 | $6.00 | $4.00 | $4.50 | |
| 24 | (520.09000010) | 1,230 | $3.75 | $6.00 | $4.00 | $6.00 | $3.00 | $3.25 | |
| 25 | (604.07200110) | 52 | $3,250.00 | $2,150.00 | $2,500.00 | $2,500.00 | $700.00 | $2,400.00 | |
| 26 | (604.07290010) | 520 | $85.00 | $125.00 | $100.00 | $125.00 | $190.00 | $150.00 | |
| 27 | (609.04060510) | 10,189 | $42.00 | $75.00 | $95.00 | $85.00 | $64.00 | $60.00 | |
| 28 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $650,000 | $845,145 | $450,000 | $500,000 | $1,539,854 | $3,500,000 |
| 29 | Type III Construction Barricades (619.04) | EACH | 283 | $90.00 | $250.00 | $50.00 | $50.00 | $80.00 | $27.00 |
| 30 | (619.0901) | LF | 16,355 | $0.60 | $1.00 | $0.70 | $0.75 | $1.00 | $0.45 |
| 31 | (619.10050020) | 900 | $10.00 | $35.00 | $20.00 | $10.00 | $12.00 | $80.00 | |
| 32 | (619.110743) | EACH | 6 | $30,000 | $8,000.00 | $5,000.00 | $7,500.00 | $30,000 | $11,000 |
| 33 | (619.110943) | EACH | 8 | $30,000 | $6,000.00 | $5,000.00 | $7,500.00 | $28,000 | $11,000 |
| 34 | (619.111133) | EACH | 4 | $30,000 | $6,000.00 | $5,000.00 | $7,500.00 | $26,000 | $11,000 |
| 35 | Vehicle Arresting Barrier (619.23) | EACH | 9 | $4,000.00 | $8,500.00 | $4,000.00 | $10,000 | $3,800.00 | $4,500.00 |
| 36 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $520,000 | $75,000 | $200,000 | $350,000 | $270,000 | $655,000 |
| 37 | Traffic Control Supervisor (619.25) | MONTH | 14 | $100.00 | $10,000 | $100.00 | $1,000.00 | $35,000 | $2,500.00 |
| 38 | Pavement Patching (Tonnage) (619.2602) | TON | 200 | $455.00 | $100.00 | $800.00 | $350.00 | $765.00 | $300.00 |
| 39 | Cleaning Drainage Structures (621.04) | EACH | 175 | $728.00 | $800.00 | $850.00 | $1,200.00 | $750.00 | $750.00 |
| 40 | Survey Operations (625.01) | LS | 1 | $3,500.00 | $100,000 | $20,000 | $50,000 | $180,000 | $70,000 |
| 41 | (634.10010015) | LS | 1 | $25,000 | $25,000 | $25,000 | $50,000 | $25,000 | $25,000 |
| 42 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $4,000.00 | $4,500.00 | $2,500.00 | $2,000.00 | $9,500.00 | $3,000.00 |
| 43 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 18 | $7,500.00 | $7,000.00 | $4,500.00 | $4,000.00 | $10,000 | $10,000 |
| 44 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 45 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 46 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 47 | (637.41000115) | 18 | $198.00 | $150.00 | $200.00 | $1,000.00 | $200.00 | $210.00 | |
| 48 | (639.21010011) | LS | 1 | $75,000 | $75,000 | $75,000 | $75,000 | $75,000 | $75,000 |
| 49 | (645.03030015) | 6 | $4,380.00 | $4,500.00 | $1,000.00 | $2,500.00 | $7,600.00 | $1,600.00 | |
| 50 | (645.03040015) | 6 | $5,320.00 | $5,500.00 | $2,500.00 | $3,500.00 | $10,000 | $2,200.00 | |
| 51 | (655.07030010) | 52 | $1,983.72 | $1,500.00 | $1,800.00 | $2,250.00 | $1,000.00 | $2,750.00 | |
| 52 | (680.83200010) | LS | 1 | $29,000 | $45,000 | $5,000.00 | $2,500.00 | $3,000.00 | $20,000 |
| 53 | (685.02000010) | 91 | $17.94 | $100.00 | $65.00 | $200.00 | $178.00 | $45.00 | |
| 54 | (685.03130018) | 91 | $175.00 | $200.00 | $200.00 | $210.00 | $238.00 | $115.00 | |
| 55 | (685.07200110) | 23,060 | $0.78 | $1.00 | $1.00 | $1.00 | $0.50 | $0.65 | |
| 56 | (685.07200210) | 17 | $150.00 | $135.00 | $160.00 | $180.00 | $160.00 | $125.00 | |
| 57 | (685.07200310) | 3 | $175.00 | $320.00 | $200.00 | $220.00 | $185.00 | $300.00 | |
| 58 | (685.07200410) | 6,732 | $1.95 | $2.00 | $2.00 | $2.35 | $2.00 | $2.50 | |
| 59 | (685.07200510) | 962 | $2.50 | $2.00 | $2.70 | $3.00 | $2.50 | $2.25 | |
| 60 | (685.07200610) | 15,250 | $0.78 | $1.00 | $0.90 | $1.00 | $0.80 | $0.65 | |
| 61 | (685.07200710) | 18,945 | $1.95 | $2.00 | $2.00 | $2.35 | $2.00 | $2.75 | |
| 62 | (691.04000020) | 85,050 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 63 | Field Change Payment (FCP) (697.03) | DOL | 1,380,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 64 | Asphalt Price Adjustment (698.04) | DOL | 6,700 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 65 | Fuel Price Adjustment (698.05) | DOL | 540 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 66 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 67 | Mobilization (699.040001) | LS | 1 | $565,000 | $585,000 | $515,000 | $650,304 | $678,300 | $680,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of February 26, 2026. Compiled by Mirage Metrics.