NYSDOT contract D265699 bid tabulation

CONCRETE PAVEMENT RESTORATION SOUTHERN STATE PKWY (908M). Let by New York State DOT on February 26, 2026, Suffolk, Region 10. 7 bids received; low bid $14,971,643 by H & L Contracting LLC.

Owner
New York State DOT
Letting
26 FEB 2026
Pay items
67
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1H & L Contracting LLC$14,971,643Low
2Bove Industries Inc$15,392,862+3.0%
3Constar Inc$15,858,412+6.0%
4GGG Construction Corp$16,907,910+13%
5Peter Scalamandre & Sons Inc$17,636,713+18%
6Tully Construction Company Inc$17,968,899+20%
7Grace Industries LLC$19,596,089+31%
NYSDOT contract D265699: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. H & L Contracting LLC2. Bove Industries Inc3. Constar Inc4. GGG Construction Corp5. Peter Scalamandre & Sons Inc6. Tully Construction Company Inc
1Unclassified Excavation and Disposal (203.02)CY218$35.00$175.00$336.00$50.00$265.00$780.00
2 (209.11010024)20$240.00$1,000.00$500.00$50.00$300.00$100.00
3 (304.00010018)154,110$1.00$2.00$0.80$1.00$1.00$1.00
4 (304.10119917)176$80.00$30.00$77.00$125.00$50.00$45.00
5 (404.0189)TON74$275.00$200.00$250.00$300.00$275.00$545.00
6 (404.0981)TON21$1,500.00$300.00$250.00$300.00$714.00$340.00
7 (404.1989)TON74$160.00$300.00$250.00$300.00$400.00$340.00
8 (404.90710218)111$750.00$800.00$600.00$500.00$680.00$800.00
9Diluted Tack Coat (407.0102)GAL21$3.00$10.00$25.00$50.00$61.00$5.00
10 (490.17011018)1,249$22.00$20.00$35.00$25.00$30.00$24.00
11 (502.10010018)LS1$150,000$250,000$100,000$50,000$80,000$26,500
12 (502.90010018)13,510$8.00$8.50$10.00$10.00$12.00$10.00
13Sealing Transverse Joints- Highway Joint Sealant (502.9210)LF25,116$8.00$8.75$10.00$10.00$9.00$10.00
14Sealing Longitudinal Joints-Highway Joint Sealant (502.9310)LF22,803$9.50$9.00$8.00$10.00$11.00$10.00
15Production Grinding – Pavement Preservation with Slurry Removal (505.0402)SY26,600$13.25$14.00$10.20$10.75$13.00$18.00
16Smoothness Quality Adjustment (505.0403)QUALITY UNIT2,660$12.00$12.00$12.00$12.00$12.00$12.00
17 (510.00210018)3,634$755.00$1,543.00$1,100.00$1,355.00$880.00$1,000.00
18 (510.02210018)133$850.00$1,550.00$1,100.00$1,500.00$820.00$1,000.00
19 (510.20000018)16,947$150.00$20.00$150.00$100.00$110.00$60.00
20 (510.81000018)17,609$42.00$20.00$35.00$30.00$38.00$50.00
21 (510.91000018)3,892$11.00$15.00$20.00$25.00$7.00$25.00
22 (511.50000018)10,911$195.00$175.00$220.00$273.00$310.00$200.00
23 (520.05000010)1,000$5.00$8.00$6.00$6.00$4.00$4.50
24 (520.09000010)1,230$3.75$6.00$4.00$6.00$3.00$3.25
25 (604.07200110)52$3,250.00$2,150.00$2,500.00$2,500.00$700.00$2,400.00
26 (604.07290010)520$85.00$125.00$100.00$125.00$190.00$150.00
27 (609.04060510)10,189$42.00$75.00$95.00$85.00$64.00$60.00
28Basic Work Zone Traffic Control (619.01)LS1$650,000$845,145$450,000$500,000$1,539,854$3,500,000
29Type III Construction Barricades (619.04)EACH283$90.00$250.00$50.00$50.00$80.00$27.00
30 (619.0901)LF16,355$0.60$1.00$0.70$0.75$1.00$0.45
31 (619.10050020)900$10.00$35.00$20.00$10.00$12.00$80.00
32 (619.110743)EACH6$30,000$8,000.00$5,000.00$7,500.00$30,000$11,000
33 (619.110943)EACH8$30,000$6,000.00$5,000.00$7,500.00$28,000$11,000
34 (619.111133)EACH4$30,000$6,000.00$5,000.00$7,500.00$26,000$11,000
35Vehicle Arresting Barrier (619.23)EACH9$4,000.00$8,500.00$4,000.00$10,000$3,800.00$4,500.00
36Nighttime Operations (Entire Project) (619.24)LS1$520,000$75,000$200,000$350,000$270,000$655,000
37Traffic Control Supervisor (619.25)MONTH14$100.00$10,000$100.00$1,000.00$35,000$2,500.00
38Pavement Patching (Tonnage) (619.2602)TON200$455.00$100.00$800.00$350.00$765.00$300.00
39Cleaning Drainage Structures (621.04)EACH175$728.00$800.00$850.00$1,200.00$750.00$750.00
40Survey Operations (625.01)LS1$3,500.00$100,000$20,000$50,000$180,000$70,000
41 (634.10010015)LS1$25,000$25,000$25,000$50,000$25,000$25,000
42Concrete Cylinder Curing Equipment (637.04)EACH1$4,000.00$4,500.00$2,500.00$2,000.00$9,500.00$3,000.00
43Engineer’s Field Office – Type 3 (637.13)MONTH18$7,500.00$7,000.00$4,500.00$4,000.00$10,000$10,000
44Office Technology and Supplies (637.34)DOL5,000$1.00$1.00$1.00$1.00$1.00$1.00
45Partnering Workshop (637.35)DOL5,000$1.00$1.00$1.00$1.00$1.00$1.00
46Construction Testing supplies – Consumables (637.36)DOL100$1.00$1.00$1.00$1.00$1.00$1.00
47 (637.41000115)18$198.00$150.00$200.00$1,000.00$200.00$210.00
48 (639.21010011)LS1$75,000$75,000$75,000$75,000$75,000$75,000
49 (645.03030015)6$4,380.00$4,500.00$1,000.00$2,500.00$7,600.00$1,600.00
50 (645.03040015)6$5,320.00$5,500.00$2,500.00$3,500.00$10,000$2,200.00
51 (655.07030010)52$1,983.72$1,500.00$1,800.00$2,250.00$1,000.00$2,750.00
52 (680.83200010)LS1$29,000$45,000$5,000.00$2,500.00$3,000.00$20,000
53 (685.02000010)91$17.94$100.00$65.00$200.00$178.00$45.00
54 (685.03130018)91$175.00$200.00$200.00$210.00$238.00$115.00
55 (685.07200110)23,060$0.78$1.00$1.00$1.00$0.50$0.65
56 (685.07200210)17$150.00$135.00$160.00$180.00$160.00$125.00
57 (685.07200310)3$175.00$320.00$200.00$220.00$185.00$300.00
58 (685.07200410)6,732$1.95$2.00$2.00$2.35$2.00$2.50
59 (685.07200510)962$2.50$2.00$2.70$3.00$2.50$2.25
60 (685.07200610)15,250$0.78$1.00$0.90$1.00$0.80$0.65
61 (685.07200710)18,945$1.95$2.00$2.00$2.35$2.00$2.75
62 (691.04000020)85,050$1.00$1.00$1.00$1.00$1.00$1.00
63Field Change Payment (FCP) (697.03)DOL1,380,000$1.00$1.00$1.00$1.00$1.00$1.00
64Asphalt Price Adjustment (698.04)DOL6,700$1.00$1.00$1.00$1.00$1.00$1.00
65Fuel Price Adjustment (698.05)DOL540$1.00$1.00$1.00$1.00$1.00$1.00
66Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00$1.00$1.00
67Mobilization (699.040001)LS1$565,000$585,000$515,000$650,304$678,300$680,000
NYSDOT contract D265699: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of February 26, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way