Peter Scalamandre & Sons Inc submitted 16 bids on New York State DOT contracts in the data, from 10 MAR 2022 to 30 JUL 2026, and was the low bidder on 2 of them (13%). When it was not low, its total sat a median +29% above the low bid.

Owner
New York State DOT
Low bid volume
$56,019,426
Latest bid
30 JUL 2026
Data through
15 OCT 2026
16Bids
2Low bids
13Win rate, percent
+29%Median gap to the low bid when not low, 14 bids

By year

YearBidsLow bidsWin rate
2022100%
2023500%
2024200%
20255120%
20263133%
Peter Scalamandre & Sons Inc, NYSDOT: bids and low bids by year of letting

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Office Technology and Supplies637.34DOL1616 (100%)$1.00$1.00
Fuel Price Adjustment698.05DOL1515 (100%)$1.00$1.00
Steel/Iron Price Adjustment698.06DOL1515 (100%)$1.00$1.00
Construction Testing supplies – Consumables637.36DOL1515 (100%)$1.00$1.00
Field Change Payment (FCP)697.03DOL1414 (100%)$1.00$1.00
Asphalt Price Adjustment698.04DOL1414 (100%)$1.00$1.00
691.040000201414 (100%)$1.00$1.00
Pavement Patching (Force Acount)619.2601DOL88 (100%)$1.00$1.00
Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips608.000013QUALITY UNIT77 (100%)$125.00$90.00
Partnering Workshop637.35DOL66 (100%)$1.00$1.00
Post-Planting Care611.19EACH65 (83%)$1.00$12.00
Plant Production Quality Adjustment to Asphalt Items404.000011QUALITY UNIT55 (100%)$125.00$85.00
Peter Scalamandre & Sons Inc, NYSDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

Peter Scalamandre & Sons Inc, NYSDOT: the firms on the same contracts most often

Latest bids

LetContractRegionProjectRankIts bidAgainst the low bid
30 JUL 2026D265799Region 10Bridge Repairs at Long Island Expressway over Commack Rd1 of 7$11,331,713Low, 19% under the second
26 FEB 2026D265699Region 10CONCRETE PAVEMENT RESTORATION SOUTHERN STATE PKWY (908M).5 of 7$17,636,713+18%
22 JAN 2026D265655Region 10INTERSECTION IMPROVEMENTS - NY Rte 25 at Mt Sinai Coram Rd7 of 9$5,468,713+55%
10 APR 2025D265428Region 10BRIDGE IMPROVEMENTS - Routes CR 19, 906A, NY 110 & 4544 of 5$8,867,713+22%
10 APR 2025D265460Region 10WANTAGH STATE PARKWAY SB RAMPS IMPROVEMENT AT OLD COUNTRY RD7 of 11$9,457,713+40%
27 MAR 2025D265393Region 10Highway Safety and Mobility Improvements - NY 3471 of 6$44,687,713Low, 1.0% under the second
27 MAR 2025D265401Region 10Drainage Improvements Various Locations Suffolk County3 of 7$16,657,713+38%
20 FEB 2025D265382Region 10I-495 Sound Barrier Requirements, Exits 49-57,6 of 11$11,487,000+29%
10 OCT 2024D265303Region 10Bridge Where and When Contract Various Locations3 of 4$4,785,940+12%
26 SEP 2024D265214Region 10Drainage Enhancement Various Locations Nassau County4 of 7$11,926,730+26%
30 NOV 2023D265117Region 10CONCRETE REPAIRS NY25 TO NY25B BRUSH HOLLOW RD3 of 14$7,794,713+6.0%
09 NOV 2023D265106Region 10PM Bridge Repair Contract - BIN 1018249, BIN 10587808 of 8$15,785,713+84%
24 AUG 2023D265059Region 10CONCRETE REPAIRS NY27 FROM NY112 TO CR101 & ON SMSP/SGSP6 of 11$13,477,713+13%
13 JUL 2023D265043Region 10I-495 CONCRETE PAVEMENT REPAIRS7 of 13$15,977,713+28%
01 JUN 2023D265031Region 10CONCRETE PAVEMENT RESTORATION VARIOUS LOCATIONS11 of 12$12,877,713+42%
10 MAR 2022D264629Region 10OPERATIONAL IMPROVEMENTS LIE I-495 AND CROOKED HILL ROAD8 of 8$35,937,713+33%
Peter Scalamandre & Sons Inc: latest NYSDOT bids in the data

How this record was read

NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

  • Every bid counted here matched its published total to within one dollar; NYSDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy