NYSDOT contract D265382 bid tabulation
I-495 Sound Barrier Requirements, Exits 49-57,. Let by New York State DOT on February 20, 2025, Suffolk, Region 10. 11 bids received; low bid $8,888,495 by Grace Industries LLC.
- Owner
- New York State DOT
- Letting
- 20 FEB 2025
- Pay items
- 62
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Grace Industries LLC | $8,888,495 | Low |
| 2 | Citnalta Construction Corp | $9,970,956 | +12% |
| 3 | Rosemar Contracting Inc | $10,812,298 | +22% |
| 4 | Bove Industries Inc | $11,127,750 | +25% |
| 5 | Posillico Civil Inc | $11,249,533 | +27% |
| 6 | Peter Scalamandre & Sons Inc | $11,487,000 | +29% |
| 7 | Suffolk Paving Corp | $11,906,962 | +34% |
| 8 | Constar Inc | $13,364,839 | +50% |
| 9 | H & L Contracting LLC | $14,615,587 | +64% |
| 10 | Oliveira Contracting Inc | $16,287,772 | +83% |
| 11 | Quintal Contracting Corp | $19,785,060 | +123% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Grace Industries LLC | 2. Citnalta Construction Corp | 3. Rosemar Contracting Inc | 4. Bove Industries Inc | 5. Posillico Civil Inc | 6. Peter Scalamandre & Sons Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.07) | ACRE | 2 | $29,200 | $75,000 | $15,000 | $60,000 | $200,000 | $343,350 |
| 2 | Removal of Substructures (202.19) | CY | 45 | $1,150.00 | $1,000.00 | $1,750.00 | $2,000.00 | $5,400.00 | $2,600.00 |
| 3 | Unclassified Excavation and Disposal (203.02) | CY | 1,270 | $175.00 | $180.00 | $100.00 | $140.00 | $550.00 | $750.00 |
| 4 | Embankment In Place (203.03) | CY | 1,311 | $130.00 | $140.00 | $35.00 | $140.00 | $60.00 | $130.00 |
| 5 | Trench and Culvert Excavation (206.0201) | CY | 208 | $210.00 | $550.00 | $175.00 | $400.00 | $350.00 | $100.00 |
| 6 | Footing Concrete, Performance (555.0011) | CY | 174 | $1,100.00 | $1,750.00 | $2,200.00 | $2,200.00 | $1,300.00 | $900.00 |
| 7 | Performance Concrete Quality Adjustment – Footing Concrete (555.9901) | QUALITY UNIT | 1 | $6.00 | $6.00 | $6.00 | $6.00 | $6.00 | $6.00 |
| 8 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 12,685 | $14.00 | $3.10 | $4.00 | $5.00 | $3.00 | $3.00 |
| 9 | Resetting HPBO (Mod.) Corrugated Beam Guide Railing (606.58) | LF | 2,950 | $153.00 | $62.45 | $60.00 | $61.50 | $105.00 | $60.00 |
| 10 | (607.41010010) | 5,900 | $8.00 | $15.00 | $2.50 | $4.00 | $12.00 | $0.50 | |
| 11 | (607.98020010) | 185,000 | $11.50 | $15.00 | $33.00 | $23.00 | $23.50 | $23.00 | |
| 12 | (607.98030010) | 29,600 | $23.00 | $7.00 | $5.00 | $16.00 | $32.50 | $27.00 | |
| 13 | Mycorrhizal Fungi (610.0701) | LB | 930 | $15.00 | $11.50 | $10.00 | $23.75 | $10.00 | $25.00 |
| 14 | Moisture Retention Additive (610.08) | LB | 930 | $12.00 | $9.20 | $8.00 | $23.75 | $8.00 | $25.00 |
| 15 | Mulch for Planting Type A, B & D Wood Chips and Shredded Bark (610.1101) | CY | 1,092 | $105.00 | $82.80 | $72.00 | $42.75 | $72.00 | $45.00 |
| 16 | Weed Removal (610.13) | SY | 3,300 | $12.00 | $9.20 | $8.00 | $6.65 | $8.00 | $7.00 |
| 17 | Topsoil - Roadside (610.1402) | CY | 1,092 | $114.00 | $89.70 | $78.00 | $93.00 | $78.00 | $98.00 |
| 18 | Turf Establishment - Roadside (610.1601) | SY | 3,300 | $4.00 | $3.34 | $2.90 | $5.70 | $2.90 | $6.00 |
| 19 | Watering Vegetation (610.19) | 1,000 GALLONS | 955 | $110.00 | $101.20 | $88.00 | $1.00 | $88.00 | $1.00 |
| 20 | (611.0171) | EACH | 267 | $1,250.00 | $1,138.50 | $990.00 | $1,100.00 | $990.00 | $1,500.00 |
| 21 | (611.0201) | EACH | 267 | $950.00 | $793.50 | $690.00 | $902.00 | $690.00 | $950.00 |
| 22 | (611.0361) | EACH | 267 | $700.00 | $575.00 | $500.00 | $617.00 | $500.00 | $650.00 |
| 23 | (611.0441) | EACH | 250 | $120.00 | $103.50 | $90.00 | $42.50 | $90.00 | $45.00 |
| 24 | (611.0451) | EACH | 250 | $175.00 | $149.50 | $130.00 | $61.50 | $130.00 | $65.00 |
| 25 | (611.0461) | EACH | 250 | $300.00 | $253.00 | $220.00 | $75.00 | $220.00 | $79.00 |
| 26 | (611.0561) | EACH | 250 | $225.00 | $195.50 | $170.00 | $80.50 | $170.00 | $85.00 |
| 27 | (611.0651) | EACH | 1,968 | $45.00 | $36.80 | $32.00 | $26.50 | $32.00 | $28.00 |
| 28 | Post-Planting Care (611.19) | EACH | 3,769 | $9.00 | $6.60 | $6.00 | $1.00 | $6.00 | $1.00 |
| 29 | (611.19010024) | 267 | $29.00 | $22.00 | $20.00 | $1.00 | $20.00 | $1.00 | |
| 30 | (611.19020024) | 267 | $17.00 | $12.93 | $11.75 | $1.00 | $12.00 | $1.00 | |
| 31 | (611.19030024) | 267 | $17.00 | $12.93 | $11.75 | $1.00 | $12.00 | $1.00 | |
| 32 | (611.19040024) | 750 | $9.50 | $7.15 | $6.50 | $1.00 | $6.50 | $1.00 | |
| 33 | (611.19050024) | 250 | $11.00 | $8.25 | $7.50 | $1.00 | $7.50 | $1.00 | |
| 34 | (611.19060024) | 1,968 | $2.00 | $1.65 | $1.50 | $1.00 | $1.50 | $1.00 | |
| 35 | (614.060102) | EACH | 1,000 | $95.00 | $74.75 | $65.00 | $300.00 | $65.00 | $500.00 |
| 36 | (614.060202) | EACH | 175 | $204.00 | $161.00 | $140.00 | $760.00 | $140.00 | $900.00 |
| 37 | (614.060302) | EACH | 175 | $569.00 | $448.50 | $390.00 | $855.00 | $390.00 | $1,000.00 |
| 38 | (614.060402) | EACH | 75 | $1,738.00 | $1,368.50 | $1,190.00 | $941.00 | $1,190.00 | $1,100.00 |
| 39 | (614.060502) | EACH | 75 | $3,176.00 | $2,501.25 | $2,175.00 | $1,710.00 | $2,175.00 | $1,900.00 |
| 40 | (617.01010024) | 7,375 | $5.00 | $4.03 | $3.50 | $1.00 | $3.50 | $0.65 | |
| 41 | (617.01020024) | 7,375 | $8.50 | $6.79 | $5.90 | $7.00 | $5.90 | $8.00 | |
| 42 | (617.01030024) | 500 | $127.00 | $100.05 | $87.00 | $200.00 | $87.00 | $75.00 | |
| 43 | (617.10000024) | 500 | $80.00 | $63.25 | $55.00 | $71.25 | $55.00 | $75.00 | |
| 44 | (617.11000024) | LS | 1 | $2,920.00 | $2,300.00 | $2,000.00 | $4,750.00 | $2,000.00 | $5,000.00 |
| 45 | Basic Work Zone Traffic Control (Daily Operations) (619.0101) | LS | 1 | $850,911 | $2,100,291 | $500,000 | $781,367 | $400,000 | $20,000 |
| 46 | Type III Construction Barricades (619.04) | EACH | 20 | $397.00 | $400.00 | $75.00 | $500.00 | $130.00 | $100.00 |
| 47 | (619.10050020) | 600 | $8.50 | $5.22 | $50.00 | $19.00 | $30.00 | $50.00 | |
| 48 | (619.111133) | EACH | 2 | $23,800 | $45,000 | $25,000 | $50,000 | $30,000 | $50,000 |
| 49 | Survey Operations (625.01) | LS | 1 | $50,000 | $90,000 | $10,000 | $125,000 | $300,000 | $49,947 |
| 50 | (625.09010015) | LS | 1 | $14,600 | $65,000 | $2,000.00 | $30,000 | $10,000 | $50,000 |
| 51 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $3,650.00 | $1,500.00 | $2,500.00 | $9,000.00 | $5,000.00 | $2,000.00 |
| 52 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 27 | $11,000 | $9,000.00 | $4,500.00 | $8,500.00 | $7,000.00 | $10,000 |
| 53 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 54 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 55 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 56 | (643.99660010) | 2,324 | $225.00 | $250.00 | $275.00 | $500.00 | $230.00 | $240.00 | |
| 57 | (645.03040015) | 2 | $9,905.00 | $7,801.60 | $6,800.00 | $4,500.00 | $6,784.00 | $10,000 | |
| 58 | (680.83200010) | LS | 1 | $15,000 | $1,300.00 | $9,000.00 | $30,000 | $10,000 | $28,305 |
| 59 | (691.04000020) | 122,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 60 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 61 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 62 | Mobilization (699.040001) | LS | 1 | $340,000 | $373,000 | $410,000 | $425,000 | $432,674 | $441,800 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of February 20, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.