NYSDOT contract D265428 bid tabulation

BRIDGE IMPROVEMENTS - Routes CR 19, 906A, NY 110 & 454. Let by New York State DOT on April 10, 2025, Suffolk, Region 10. 5 bids received; low bid $7,245,000 by Bove Industries Inc.

Owner
New York State DOT
Letting
10 APR 2025
Pay items
60
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Bove Industries Inc$7,245,000Low
2H & L Contracting LLC$7,296,000+1.0%
3Grace Industries LLC$8,619,721+19%
4Peter Scalamandre & Sons Inc$8,867,713+22%
5Fos Development Corp$13,069,453+80%
NYSDOT contract D265428: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Bove Industries Inc2. H & L Contracting LLC3. Grace Industries LLC4. Peter Scalamandre & Sons Inc5. Fos Development Corp
1Clearing and Grubbing (201.06)LS1$200,000$20,000$41,300$20,000$98,964
2Removal of Steel Supported Structural Slabs (with shear connectors) – Type A (202.2201)SF2,747$100.00$170.00$225.00$425.00$217.00
3Unclassified Excavation and Disposal (203.02)CY18$500.00$140.00$176.00$12,250$546.00
4Embankment In Place (203.03)CY18$500.00$150.00$235.00$12,250$815.00
5Removal and Disposal of Bond Breaker/Filler ACM (BV14) (210.3312)SF28$2,500.00$786.00$350.00$1,000.00$836.00
6 (402.90710118)104$600.00$1,100.00$1,275.00$850.00$752.00
7 (404.4189)TON926$175.00$325.00$410.00$290.00$209.00
8 (490.17011018)740$85.00$96.00$93.00$60.00$27.00
9Concrete for Structures, Performance (555.0021)CY24$8,500.00$7,900.00$7,000.00$22,500$2,868.00
10Performance Concrete Quality Adjustment – Concrete for Structures (555.9902)QUALITY UNIT1$27.50$27.50$27.50$27.50$27.50
11Epoxy-Coated Bar Reinforcement for Structures (556.0202)LB46,739$4.00$1.50$6.00$2.75$9.00
12 (557.1011)SY102$3,500.00$1,400.00$650.00$1,250.00$910.00
13 (557.1111)SY321$2,000.00$2,288.68$890.00$2,000.00$587.00
14 (557.2019)SY40$850.00$1,100.00$650.00$825.00$997.00
15 (557.2119)SY40$1,500.00$2,000.00$900.00$2,925.00$1,025.00
16Sidewalks and Safety Walks (557.30)SY20$1,500.00$1,500.00$827.00$9,000.00$1,019.00
17 (557.67010511)115$300.00$1,500.00$860.00$1,000.00$1,099.00
18Performance Concrete Quality Adjustment – Superstructure and Approach Slab (557.9901)QUALITY UNIT1$23.82$23.82$23.82$23.82$23.82
19Performance Concrete Quality Adjustment – Sidewalks and Safety Walks (557.9902)QUALITY UNIT1$36.01$36.01$36.01$36.01$36.01
20Longitudinal Sawcut Grooving of Structural Slab Surface (558.02)SY23$550.00$500.00$410.00$9,000.00$211.00
21 (567.51000009)52$289.00$65.00$432.00$375.00$53.00
22Armorless Bridge Joint (567.60)LF989$1,194.44$500.00$753.00$700.00$585.00
23Bridge Joint Seal (567.63)LF151$55.00$400.00$157.00$185.00$191.00
24Single Slope (Half-Section) Concrete Bridge Barrier (569.04)LF8$2,500.00$3,400.00$777.00$3,900.00$779.00
25Performance Concrete Quality Adjustment–Cast-In-Place Concrete Barrier (569.99)QUALITY UNIT1$23.15$23.15$23.15$23.15$23.15
26Removal of Structural Concrete (580.01)CY50$11,360$6,000.00$9,072.00$8,000.00$2,597.00
27Removal of Concrete Approach Slab (580.04)SF1,513$85.00$155.00$349.00$375.00$119.00
28Removal of Bituminous Concrete Overlay (Bridge) (581.01)SF79,171$1.50$5.00$2.80$2.00$11.00
29 (582.99000016)2,215$25.00$30.00$72.00$25.00$94.00
30Drilling and Grouting Bolts or Reinforcing Bars (586.0201)EACH1,518$25.00$150.00$125.00$37.00$37.00
31Bridge Railing Removal and Storage (587.02)LF80$425.00$500.00$621.00$525.00$207.00
32Installation of Stored Bridge Railing (587.03)LF80$687.50$600.00$850.00$750.00$340.00
33Resetting Box Beam Guide Railing (606.53)LF40$300.00$296.00$400.00$375.00$224.00
34Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013)QUALITY UNIT1$100.00$100.00$100.00$100.00$100.00
35Concrete Sidewalks and Driveways (608.0101)CY2$3,500.00$2,800.00$1,497.00$300.00$7,924.00
36Stone Curb – Bridge (Type F1) (609.0302)LF44$75.00$1,500.00$150.00$225.00$1,127.00
37 (609.0401)LF16$250.00$600.00$225.00$80.00$1,248.00
38Basic Work Zone Traffic Control (619.01)LS1$1,445,220$1,422,407$1,826,020$874,938$4,569,664
39Type III Construction Barricades (619.04)EACH10$500.00$200.00$407.00$250.00$1,155.00
40Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803)LF885$7.60$7.60$11.00$9.25$13.00
41 (619.100103)LF950$6.80$6.80$10.00$8.50$12.00
42 (619.10050020)650$25.00$21.22$30.00$20.00$34.00
43 (619.111133)EACH2$25,000$68,000$24,400$75,000$55,422
44Nighttime Operations (Entire Project) (619.24)LS1$81,100$319,000$215,000$70,000$2,436,853
45Traffic Control Supervisor (619.25)MONTH10$1,000.00$200.00$43,600$45,000$36,754
46Survey Operations (625.01)LS1$50,000$55,000$122,000$15,000$83,531
47 (625.09010015)LS1$4,000.00$3,000.00$10,300$1,500.00$25,060
48Concrete Cylinder Curing Equipment (637.04)EACH1$5,000.00$3,500.00$4,867.00$2,500.00$9,189.00
49Engineer’s Field Office – Type 3 (637.13)MONTH17$8,500.00$6,500.00$13,000$10,000$17,605
50Office Technology and Supplies (637.34)DOL5,000$1.00$1.00$1.00$1.00$1.00
51Construction Testing supplies – Consumables (637.36)DOL100$1.00$1.00$1.00$1.00$1.00
52 (680.83200010)LS1$5,000.00$2,000.00$161,540$3,500.00$20,833
53 (685.07200110)880$12.94$6.50$21.00$8.00$11.00
54 (685.07200610)450$16.87$6.50$21.00$8.00$11.00
55 (691.04000020)51,000$1.00$1.00$1.00$1.00$1.00
56Field Change Payment (FCP) (697.03)DOL404,000$1.00$1.00$1.00$1.00$1.00
57Asphalt Price Adjustment (698.04)DOL1,288$1.00$1.00$1.00$1.00$1.00
58Fuel Price Adjustment (698.05)DOL290$1.00$1.00$1.00$1.00$1.00
59Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00$1.00
60Mobilization (699.040001)LS1$275,000$276,157$300,000$341,065$375,890
NYSDOT contract D265428: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of April 10, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy