NYSDOT contract D265803 bid tabulation

PARK/RIDE & BIKEWAY MAINTENANCE, GRAFFITI, TREE TRIMMING. Let by New York State DOT on August 27, 2026, Nassau, Suffolk, Region 10. 5 bids received; low bid $4,694,047 by Westmoreland Construction Inc.

Owner
New York State DOT
Letting
27 AUG 2026
Pay items
189
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Westmoreland Construction Inc$4,694,047Low
2Dragonetti Brothers Landscaping, Nursery & Florist Inc$5,285,902+13%
3Rosemar Contracting Inc$5,445,445+16%
4Constar Inc$5,722,217+22%
5Quintal Contracting Corp$5,813,431+24%
NYSDOT contract D265803: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Westmoreland Construction Inc2. Dragonetti Brothers Landscaping, Nursery & Florist Inc3. Rosemar Contracting Inc4. Constar Inc5. Quintal Contracting Corp
1Clearing and Grubbing (201.06)LS1$90,000$105,000$100,000$100,000$250,000
2Unclassified Excavation and Disposal (203.02)CY100$90.00$125.00$120.00$95.00$95.00
3Embankment In Place (203.03)CY10$90.00$95.00$100.00$95.00$50.00
4Trench and Culvert Excavation (206.0201)CY300$90.00$90.00$100.00$90.00$90.00
5Silt Fence - Temporary (209.13)LF200$5.00$22.00$12.00$12.00$12.00
6Sediment Filter Log – Temporary, 12″, Type A (209.1311)LF100$25.00$40.00$12.00$10.00$10.00
7Rolled Erosion Control Product, Class II Type A, Intermediate (209.1901)SY100$5.00$8.50$9.00$9.00$9.00
8Rolled Erosion Control Product, Class II Type D, Intermediate (209.1904)SY100$5.00$8.00$8.50$9.00$9.00
9 (304.10119917)50$50.00$90.00$100.00$90.00$250.00
10 (404.0981)TON4$500.00$450.00$400.00$500.00$500.00
11 (404.1989)TON4$500.00$450.00$400.00$500.00$500.00
12 (404.2589)TON4$500.00$450.00$400.00$500.00$500.00
13 (406.0189)TON2$500.00$450.00$400.00$500.00$500.00
14Diluted Tack Coat (407.0102)GAL30$10.00$30.00$32.00$25.00$30.00
15Miscellaneous Cold Milling of Bituminous Concrete (490.30)SY50$20.00$50.00$55.00$70.00$60.00
16 (520.05000010)5$50.00$15.00$16.00$15.00$20.00
17 (520.09000010)100$8.00$15.00$16.00$15.00$10.00
18Footing Concrete, Performance (555.0011)CY1$2,500.00$4,000.00$4,200.00$4,000.00$4,000.00
19Performance Concrete Quality Adjustment – Footing Concrete (555.9901)QUALITY UNIT1$7.50$7.50$7.50$7.50$7.50
20 (559.90200010)1,500$0.50$1.99$2.00$2.00$2.50
21 (559.91100010)1,000$0.50$1.76$1.75$1.80$2.50
22 (559.92050010)3,000$0.50$1.25$1.40$1.25$2.25
23 (559.92150010)90,000$1.25$1.35$1.40$1.40$2.35
24 (559.92200010)30,000$1.25$1.45$1.50$1.50$2.20
25 (559.92350010)4,000$1.00$1.00$1.25$1.00$1.25
26 (559.92450010)50$8.00$7.50$8.00$8.00$9.00
27 (559.92500010)1,500$2.00$2.00$2.25$2.00$3.00
28 (559.92600010)10$350.00$500.00$550.00$500.00$500.00
29 (568.11010010)20$100.00$900.00$950.00$900.00$1,200.00
30 (601.04050011)10$100.00$50.00$60.00$20.00$300.00
31 (607.0521)LF100$20.00$90.00$95.00$90.00$90.00
32 (607.0522)LF100$20.00$90.00$100.00$90.00$138.00
33 (607.08060010)500$50.00$75.00$105.00$150.00$135.00
34 (607.25000009)600$5.00$60.00$8.00$6.00$18.00
35 (607.31010010)100$20.00$75.00$80.00$75.00$65.00
36 (607.31020010)100$20.00$100.00$110.00$100.00$120.00
37 (607.36000011)200$10.00$100.00$105.00$100.00$120.00
38 (607.36191310)300$10.00$120.00$125.00$120.00$160.00
39 (607.36191410)75$10.00$68.00$300.00$70.00$80.00
40 (607.36201310)50$20.00$275.00$300.00$300.00$300.00
41 (607.36201410)12$20.00$225.00$250.00$225.00$250.00
42 (607.36220010)75$5.00$11.00$12.00$11.00$20.00
43 (607.41010010)75$5.00$12.00$13.00$12.00$12.50
44 (607.62000010)75$5.00$18.00$20.00$17.00$30.00
45 (607.86000010)284$50.00$20.00$22.00$20.00$23.00
46 (607.97000007)500$50.00$85.00$120.00$125.00$150.00
47Concrete Sidewalks and Driveways (608.0101)CY3$2,000.00$2,650.00$2,700.00$2,750.00$2,575.00
48Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON40$400.00$395.00$375.00$400.00$675.00
49 (609.40000015)1$500.00$550.00$575.00$550.00$575.00
50Mycorrhizal Fungi (610.0701)LB300$15.00$8.00$8.50$8.00$10.00
51Moisture Retention Additive (610.08)LB200$15.00$8.00$8.50$8.00$10.00
52Compost (610.10)CY200$45.00$85.00$80.00$80.00$65.00
53Mulch for Planting Type A, B & D Wood Chips and Shredded Bark (610.1101)CY800$5.00$63.00$45.00$45.00$40.00
54Permeable Weed Control Landscape Fabric (610.1201)SY500$5.00$8.00$9.00$8.00$8.00
55 (610.12030005)100$10.00$55.00$56.00$55.00$65.00
56Weed Removal (610.13)SY45,000$5.50$7.00$6.25$6.00$7.00
57Topsoil - Roadside (610.1402)CY500$35.00$88.00$70.00$65.00$60.00
58Topsoil - Lawns (610.1403)CY100$35.00$88.00$70.00$65.00$60.00
59Turf Establishment - Roadside (610.1601)SY1,835$4.00$4.50$5.00$5.00$4.00
60Turf Establishment -Lawns (610.1602)SY478$4.00$5.00$5.00$5.00$4.00
61Wildflower Seeding (610.17)SY2,000$3.00$22.00$18.50$18.00$16.00
62Watering Vegetation (610.19)1,000 GALLONS600$75.00$195.00$180.00$175.00$250.00
63Mowing (610.21)SY1,500$1.00$4.50$4.75$5.00$4.50
64 (611.0121)EACH50$350.00$525.00$550.00$525.00$450.00
65 (611.0161)EACH175$500.00$650.00$625.00$575.00$575.00
66 (611.0201)EACH175$400.00$525.00$475.00$450.00$575.00
67 (611.0271)EACH6$550.00$600.00$625.00$575.00$425.00
68 (611.0332)EACH10$350.00$285.00$300.00$275.00$279.00
69 (611.0341)EACH100$300.00$385.00$400.00$375.00$369.00
70 (611.0361)EACH100$450.00$460.00$475.00$450.00$449.00
71 (611.0381)EACH50$500.00$560.00$600.00$550.00$549.00
72 (611.0441)EACH38$75.00$78.00$85.00$80.00$78.00
73 (611.0451)EACH600$75.00$95.00$90.00$85.00$110.00
74 (611.0461)EACH500$85.00$105.00$100.00$95.00$120.00
75 (611.0541)EACH25$70.00$80.00$80.00$75.00$89.00
76 (611.0551)EACH38$80.00$100.00$110.00$100.00$110.00
77 (611.0561)EACH160$95.00$110.00$100.00$95.00$155.00
78 (611.0581)EACH100$95.00$120.00$100.00$95.00$200.00
79 (611.0651)EACH50$50.00$25.00$26.00$25.00$25.00
80 (611.0721)EACH10$50.00$70.00$72.00$70.00$90.00
81 (611.0751)EACH300$30.00$28.00$30.00$28.00$29.00
82Post-Planting Care (611.19)EACH100$1.00$10.00$10.00$10.00$10.00
83 (611.19000110)10$100.00$100.00$110.00$100.00$100.00
84 (611.19010024)10$1.00$175.00$180.00$175.00$200.00
85 (611.19020024)20$1.00$100.00$100.00$100.00$100.00
86Care of Trees up to 12” Diam. at Breast Height – Pruning (614.0411)EACH20$100.00$250.00$250.00$250.00$275.00
87Care of Trees Over 12” to 24” Diam. at Breast Height - Pruning (614.0421)EACH15$100.00$375.00$380.00$375.00$375.00
88Care of Trees Over 24” to 36” Diam. at Breast Height - Pruning (614.0431)EACH1$100.00$950.00$950.00$900.00$500.00
89Care of Trees Over 36” to 48” Diam. at Breast Height – Pruning (614.0441)EACH1$100.00$950.00$975.00$900.00$500.00
90Care of Trees Over 48” to 60” Diam. at Breast Height – Pruning (614.0451)EACH1$100.00$950.00$975.00$900.00$500.00
91Care of Trees Over 60” Diam. at Breast Height – Pruning (614.0461)EACH1$100.00$950.00$1,000.00$900.00$500.00
92 (614.04710001)10,000$5.00$5.00$5.00$5.00$5.00
93 (614.04810001)7,000$4.00$4.00$4.00$4.00$4.00
94 (614.04910001)200$8.00$10.00$10.00$10.00$10.00
95Improvement of Vegetated Areas (614.05)SY2,000$6.00$6.00$6.50$6.00$6.00
96 (614.060102)EACH40$150.00$125.00$130.00$125.00$125.00
97 (614.060104)EACH5$150.00$300.00$310.00$300.00$300.00
98 (614.060202)EACH35$250.00$250.00$260.00$250.00$300.00
99 (614.060204)EACH5$250.00$525.00$540.00$525.00$550.00
100 (614.060302)EACH10$450.00$750.00$760.00$750.00$700.00
101 (614.060402)EACH10$450.00$950.00$960.00$950.00$895.00
102 (614.060502)EACH5$500.00$1,900.00$2,000.00$1,900.00$1,900.00
103 (614.060602)EACH1$500.00$4,500.00$4,600.00$4,500.00$4,500.00
104 (614.060702)EACH1$500.00$5,800.00$5,900.00$6,000.00$4,500.00
105 (614.060802)EACH1$500.00$6,500.00$6,600.00$7,000.00$4,500.00
106Pre-Existing Stump Removal up to 24” diameter at 6 inches above grade (614.0701)EACH3$500.00$450.00$460.00$450.00$450.00
107Pre-Existing Stump Removal over 24” to 48” diameter at 6 inches above grade (614.0702)EACH3$200.00$500.00$525.00$500.00$450.00
108Pre-Existing Stump Removal over 48” diameter at 6 inches above grade (614.0703)EACH3$200.00$500.00$525.00$525.00$500.00
109 (615.01010110)1$500.00$1,800.00$2,200.00$1,800.00$3,000.00
110 (615.01010210)1$500.00$3,600.00$3,800.00$3,600.00$4,000.00
111 (615.01010310)1$500.00$1,800.00$2,200.00$1,800.00$3,000.00
112 (615.02020124)1$350.00$1,000.00$1,100.00$1,000.00$500.00
113 (615.02020224)1$350.00$1,000.00$1,100.00$1,000.00$500.00
114 (615.02020324)1$350.00$1,000.00$1,100.00$1,000.00$500.00
115 (615.08010005)2$500.00$3,500.00$3,750.00$3,500.00$4,000.00
116 (615.08020005)2$1,000.00$3,900.00$3,750.00$5,000.00$5,000.00
117 (615.27020010)1$500.00$3,000.00$3,200.00$3,000.00$3,000.00
118 (617.01010024)1,000$5.00$1.30$1.50$1.35$2.00
119 (617.01020024)1,000$4.00$4.00$4.50$4.00$5.50
120 (617.01030024)50$75.00$100.00$120.00$100.00$100.00
121 (617.10000024)50$75.00$100.00$120.00$100.00$100.00
122 (617.11000024)LS1$2,000.00$2,000.00$2,500.00$2,000.00$2,000.00
123Basic Work Zone Traffic Control (Daily Operations) (619.0101)LS1$150,000$100,000$130,000$500,000$125,000
124Type III Construction Barricades (619.04)EACH100$50.00$75.00$60.00$95.00$10.00
125 (619.111133)EACH1$1,000.00$7,500.00$8,000.00$5,000.00$6,000.00
126Truck Mounted Variable Message Signs (TMVMS) (619.1113)EACH3$500.00$1,000.00$1,200.00$1,000.00$1,000.00
127Nighttime Operations (Entire Project) (619.24)LS1$90,000$100,000$75,000$100,000$50,000
128Pavement Patching (Force Acount) (619.2601)DOL1,500$1.00$1.00$1.00$1.00$1.00
129Stone Filling (Fine) (620.02)CY15$25.00$130.00$150.00$130.00$135.00
130Clean, Grade and Shape Existing Roadside Section (621.05)LF300$5.00$15.00$14.00$15.00$15.00
131Survey Operations (625.01)LS1$2,500.00$7,500.00$10,000$8,000.00$5,000.00
132Cleaning, Sealing and/or Filling Joints (633.13)LF750$5.00$5.00$6.00$5.00$6.00
133Cleaning and Preparation of Pavement Surfaces-Lines (635.0103)LF8,000$1.00$2.00$2.50$2.00$2.50
134Cleaning and Preparation of Pavement Surfaces-Symbols (635.0303)EACH5$20.00$150.00$160.00$150.00$300.00
135Concrete Cylinder Curing Equipment (637.04)EACH1$1,000.00$3,000.00$2,800.00$2,500.00$1,000.00
136Engineer’s Field Office – Type 3 (637.13)MONTH20$6,000.00$5,000.00$5,000.00$5,000.00$5,000.00
137Office Technology and Supplies (637.34)DOL5,000$1.00$1.00$1.00$1.00$1.00
138Construction Testing supplies – Consumables (637.36)DOL100$1.00$1.00$1.00$1.00$1.00
139White Paint Reflectorized Pavement Stripes – 15 mils (640.10)LF315$1.00$3.50$3.60$3.50$4.00
140Yellow Paint Reflectorized Pavement Stripes - 15 mils (640.11)LF200$1.00$3.50$3.60$3.50$4.00
141White Paint Reflectorized Pavement Letters - 15 mils (640.12)EACH75$1.00$100.00$110.00$100.00$125.00
142White Paint Reflectorized Pavement Symbols - 15 mils (640.13)EACH2$1.00$350.00$360.00$350.00$500.00
143 (640.25000010)500$1.00$6.00$6.50$6.00$6.00
144 (642.02000010)1$500.00$500.00$550.00$500.00$500.00
145 (642.05960024)50$50.00$50.00$55.00$50.00$50.00
146 (642.11020010)56$700.00$875.00$900.00$875.00$1,125.00
147 (642.11030010)162$650.00$600.00$620.00$600.00$600.00
148 (642.11040010)LS1$470,000$410,000$425,000$500,000$450,000
149 (642.11110010)1,656$125.00$138.00$150.00$138.00$138.00
150 (642.12010010)1,392$175.00$195.00$225.00$195.00$195.00
151 (642.12020010)192$350.00$325.00$350.00$325.00$429.00
152 (642.12030010)394$150.00$110.00$175.00$150.00$150.00
153 (642.12040010)4,095$150.00$140.00$140.00$150.00$130.00
154 (642.13010010)1,440$130.00$130.00$150.00$130.00$145.00
155 (642.13020010)54$600.00$650.00$675.00$650.00$565.00
156 (642.13030010)144$400.00$375.00$450.00$395.00$400.00
157 (642.14010010)1,716$100.00$85.00$95.00$85.00$110.00
158 (642.15000010)10$550.00$950.00$1,000.00$950.00$950.00
159 (642.15010010)2,145$75.00$60.00$70.00$60.00$85.00
160 (645.10010010)6$200.00$150.00$160.00$150.00$200.00
161 (645.17010008)5$50.00$250.00$260.00$250.00$275.00
162 (645.17020008)1$100.00$300.00$325.00$300.00$395.00
163 (645.17030008)1$100.00$650.00$660.00$650.00$650.00
164 (645.35010010)30$50.00$260.00$270.00$260.00$300.00
165Ground-Mounted Sign Panels without Z-bars (645.5101)SF10$20.00$85.00$90.00$90.00$100.00
166Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF10$50.00$78.00$80.00$90.00$100.00
167Ground-Mounted Sign Panels greater than 32 SF with Z-bars (645.5103)SF10$50.00$90.00$92.00$90.00$80.00
168Type A Sign Posts (645.81)EACH10$50.00$200.00$250.00$300.00$200.00
169Soil Plate for Type A Sign Post (645.8105)EACH5$50.00$200.00$225.00$250.00$200.00
170High-Capacity Type A Sign Posts with Soil Plates Only (645.8106)EACH2$50.00$750.00$800.00$800.00$750.00
171Concrete Footing for Type A, or Breakaway Wooden Sign Posts with Steel Tube Inserts (645.8107)EACH2$250.00$900.00$950.00$900.00$1,200.00
172Flexible Delineator, Single Unit, Back to Back (646.41)EACH50$50.00$175.00$200.00$175.00$395.00
173Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31)EACH2$50.00$500.00$525.00$500.00$500.00
174Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61)EACH2$50.00$500.00$525.00$500.00$500.00
175 (655.07030010)1$2,000.00$3,500.00$2,500.00$3,500.00$4,000.00
176Cast Frame F3, UnMountable Curb Box CU3 & Reticuline Grate G3 (655.0706)EACH1$1,000.00$3,500.00$2,500.00$3,500.00$4,000.00
177 (680.83200010)LS1$1,000.00$5,000.00$5,000.00$7,000.00$5,000.00
178 (685.07150110)500$1.00$4.00$4.25$4.00$5.00
179 (685.07200110)1,000$0.50$4.00$4.25$4.00$4.00
180 (685.07200610)1,000$0.50$4.00$4.25$4.00$4.00
181White Thermoplastic Reflectorized Pavement Stripes (687.0101)LF2,000$0.49$3.85$4.00$4.00$4.00
182Yellow Thermoplastic Reflectorized Pavement Stripes (687.0201)LF175$0.50$5.00$4.00$5.00$7.00
183White Preformed Reflectorized Pavement Stripes (688.01)LF100$0.50$7.50$7.60$7.50$8.00
184White Preformed Reflectorized Pavement Symbols (688.04)EACH8$0.50$405.00$350.00$400.00$500.00
185Field Change Payment (FCP) (697.03)DOL342,361$1.00$1.00$1.00$1.00$1.00
186Asphalt Price Adjustment (698.04)DOL342$1.00$1.00$1.00$1.00$1.00
187Fuel Price Adjustment (698.05)DOL236$1.00$1.00$1.00$1.00$1.00
188Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00$1.00
189Mobilization (699.040001)LS1$180,000$203,304$208,377$200,000$223,593
NYSDOT contract D265803: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of August 27, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy