NYSDOT contract D265527 bid tabulation

GUIDERAIL REHABILITATION VARIOUS LOCATIONS. Let by New York State DOT on July 10, 2025, Nassau, Suffolk, Region 10. 3 bids received; low bid $2,599,159 by United Fence and Guard Rail Corp.

Owner
New York State DOT
Letting
10 JUL 2025
Pay items
97
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1United Fence and Guard Rail Corp$2,599,159Low
2H & L Contracting LLC$2,615,489+1.0%
3Constar Inc$3,342,018+29%
NYSDOT contract D265527: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. United Fence and Guard Rail Corp2. H & L Contracting LLC3. Constar Inc
1Clearing and Grubbing (201.06)LS1$15,000$15,000$25,000
2Unclassified Excavation and Disposal (203.02)CY298$240.00$250.00$100.00
3 (206.03100010)20$200.00$50.00$100.00
4Test Pit Excavation (206.05)EACH2$500.00$950.00$100.00
5 (304.00010018)271$5.00$1.00$5.00
6 (304.10119917)10$400.00$70.00$200.00
7 (404.0001)TON2$125.00$125.00$125.00
8 (404.0981)TON7$500.00$750.00$400.00
9 (404.1989)TON12$400.00$650.00$400.00
10 (404.2589)TON18$400.00$550.00$400.00
11Diluted Tack Coat (407.0102)GAL7$25.00$5.00$10.00
12Asphalt Pavement Joint Adhesive (418.7603)LF528$10.00$9.00$8.00
13Sealing Transverse Joints- Highway Joint Sealant (502.9210)LF46$70.00$40.00$12.00
14Sealing Longitudinal Joints-Highway Joint Sealant (502.9310)LF64$70.00$29.00$10.00
15 (510.02210018)8$3,200.00$2,000.00$1,500.00
16 (510.20000018)31$350.00$400.00$200.00
17 (510.81000018)36$100.00$160.00$75.00
18 (520.09000010)829$5.00$4.10$8.00
19Drilling and Grouting Bolts or Reinforcing Bars (586.0201)EACH12$100.00$75.00$100.00
20 (604.07200110)3$2,500.00$4,000.00$3,500.00
21Box Beam Guide Railing (606.10)LF611$125.00$66.00$140.00
22Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002)LF96$135.00$82.00$160.00
23Box Beam End Piece (606.120101)EACH3$1,800.00$750.00$1,200.00
24Box Beam Guide Railing End Assembly Type I (606.120102)EACH2$7,500.00$5,000.00$10,000
25Weak-Post, Corrugated Beam Guide Rail (606.18)LF832$45.00$41.00$60.00
26Anchorage Units for Corrugated Beam Guide Railing (606.22)EACH2$2,500.00$2,900.00$5,000.00
27HPBO (Mod.) Corrugated Beam Guide Railing End Terminal (Energy-Absorbing) (606.27)EACH4$5,400.00$5,600.00$6,000.00
28HPBO (Mod.) Corrugated Beam Guide Railing (606.2701)LF7,489$50.00$45.00$60.00
29HPBO (Mod.) Corrugated Beam Guide Railing with Extra Long Posts (606.2702)LF75$65.00$60.00$75.00
30Anchorage Units for HPBO (Mod.) Corrugated Beam Guide Railing (606.2703)EACH17$3,700.00$3,600.00$5,000.00
31HPBO (Mod.) Corrugated Beam Median Barrier End Terminal (Energy-Absorbing) (606.28)EACH3$14,500$10,000$12,500
32HPBO (Mod.) Corrugated Beam Median Barrier (606.2801)LF2,050$65.00$56.00$70.00
33Anchorage Units for HPBO (Mod.) Corrugated Beam Median Barrier (606.2802)EACH1$4,500.00$6,000.00$5,500.00
34Single-Slope Concrete Median Barrier (Optional) (606.3041)LF80$925.00$185.00$300.00
35I-Beam Posts for Existing Box Beam Guide Railing (606.4809)EACH5$125.00$123.00$400.00
36I-Beam posts for Existing HPBO (Mod.) Corrugated Beam Guide Railing (606.4818)EACH11$100.00$100.00$400.00
37Removing and Disposing Corrugated Beam Guide Railing (606.71)LF1,110$10.00$14.00$15.00
38Removing and Disposing HPBO (Mod.) Corrugated Beam Guide Railing (606.7101)LF6,173$10.00$14.00$15.00
39Removing and Disposing Box Beam Guide Railing (606.73)LF1,668$12.00$14.00$15.00
40Removing and Disposing Box Beam Median Barrier (606.74)LF2,025$12.00$14.00$20.00
41Removing and Disposing of Guide Posts, Guide Rail Posts, and Median Barrier Posts (606.76)EACH15$10.00$100.00$50.00
42Removing and Disposing Anchorage Units for Corrugated Beam Guide Railing and Median Barrier (606.7910)EACH3$300.00$350.00$600.00
43Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920)EACH15$300.00$350.00$600.00
44Removing and Disposing Box Beam Median Barrier End Assembly-Type A (606.7930)EACH4$300.00$350.00$2,000.00
45Removing and Disposing Box Beam Median Barrier End Assembly--Type B (606.7931)EACH2$300.00$350.00$1,000.00
46Removing and Disposing Anchorage Units for HPBO(Mod) Corrugated Beam Guide Railing (606.7941)EACH12$300.00$350.00$800.00
47Transition: HPBO (Mod.) Corrugated Beam Guide Railing to Weak Post Corrugated Beam Guide Railing (606.8902)EACH1$9,000.00$4,500.00$15,000
48Transition: HPBO (Mod.) Corrugated Beam Guide Railing to Single Slope Concrete Half Section Barrier (606.8903)EACH2$12,500$6,500.00$15,000
49Transition between Standard (NJ) Concrete Barrier and Single-Slope Concrete Barrier (606.9001)EACH3$25,000$15,000$15,000
50 (607.31020010)900$65.00$44.00$110.00
51 (607.62000010)900$9.00$12.00$20.00
52Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013)QUALITY UNIT40$125.00$125.00$125.00
53Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON790$325.00$600.00$475.00
54 (609.04070510)1,270$85.00$66.00$125.00
55 (609.06000008)1,270$15.00$25.00$40.00
56Topsoil - Roadside (610.1402)CY270$100.00$98.00$60.00
57Turf Establishment - Roadside (610.1601)SY2,428$6.00$5.00$5.00
58Basic Work Zone Traffic Control (619.01)LS1$225,000$165,000$425,000
59Type III Construction Barricades (619.04)EACH6$50.00$160.00$120.00
60 (619.10050020)374$2.00$20.00$20.00
61 (619.111133)EACH4$6,000.00$14,000$5,000.00
62Nighttime Operations (Entire Project) (619.24)LS1$2,500.00$8,500.00$75,000
63Traffic Control Supervisor (619.25)MONTH9$100.00$100.00$100.00
64Pavement Patching (Force Acount) (619.2601)DOL10,000$1.00$1.00$1.00
65 (621.05020004)11,911$2.00$5.50$2.00
66Survey Operations (625.01)LS1$2,500.00$7,500.00$25,000
67 (625.09010015)LS1$2,500.00$2,000.00$5,000.00
68 (634.10010015)LS1$600.00$550.00$50,000
69Engineer’s Field Office – Type 2 (637.12)MONTH12$5,500.00$8,000.00$4,000.00
70Office Technology and Supplies (637.34)DOL5,000$1.00$1.00$1.00
71Construction Testing supplies – Consumables (637.36)DOL100$1.00$1.00$1.00
72Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF5$80.00$76.00$75.00
73Type A Sign Posts (645.81)EACH45$250.00$260.00$275.00
74 (645.81090003)5$50.00$51.00$75.00
75Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23)EACH132$25.00$21.00$50.00
76Reference Marker, Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels Relocation (646.24)EACH3$125.00$44.00$100.00
77Steel Post, 1.1 lb/ft (646.31)EACH3$250.00$42.00$100.00
78Steel Post, 2.0 lb/ft (646.32)EACH105$250.00$62.00$200.00
79Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31)EACH25$350.00$90.00$400.00
80Relocate Sign Panel, Sign Panel Assembly Size II (30-100 Square Feet) (647.32)EACH1$1,250.00$690.00$2,000.00
81Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41)EACH25$100.00$110.00$500.00
82Remove and Store Sign Panel, Sign Panel Assembly Size II (30-100 Square Feet) (647.42)EACH1$500.00$350.00$1,200.00
83 (647.83001002)15$50.00$19.00$50.00
84Relocate Impact Attenuator (654.08)EACH1$7,500.00$24,000$20,000
85Cast Frame F3, Mountable Curb Box CM3 & Reticuline Grate G3 (655.0703)EACH3$5,000.00$2,130.00$3,000.00
86 (670.14480010)1$3,000.00$200.00$2,000.00
87 (680.520203)LF20$30.00$20.00$25.00
88Inductance Loop Installation (680.54)LF52$50.00$45.00$40.00
89Inductance Loop Wire (680.72)LF104$2.00$2.00$4.00
90 (680.83200010)LS1$15,000$5,000.00$50,000
91 (685.07200310)2$500.00$500.00$250.00
92 (685.07200610)438$9.00$9.00$10.00
93Field Change Payment (FCP) (697.03)DOL244,000$1.00$1.00$1.00
94Asphalt Price Adjustment (698.04)DOL100$1.00$1.00$1.00
95Fuel Price Adjustment (698.05)DOL182$1.00$1.00$1.00
96Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00
97Mobilization (699.040001)LS1$99,968$91,800$128,500
NYSDOT contract D265527: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of July 10, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy