Low bidders on NYSDOT contracts carried a median of $500.00 per EACH for this item, over the 24 months to 15 OCT 2026, across 53 low bids. Half of all 200 bids fell between $314.19 and $750.00.
- Owner
- New York State DOT
- Item
- 606.7910
- Unit
- EACH
- Data through
- 15 OCT 2026
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2022 | 37 | 37 | $260.00 | 138 | $300.00 |
| 2023 | 14 | 14 | $375.00 | 56 | $418.62 |
| 2024 | 23 | 23 | $500.00 | 93 | $500.00 |
| 2025 | 26 | 25 | $415.00 | 103 | $500.00 |
| 2026 | 23 | 23 | $600.00 | 72 | $500.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| Region 04 | 9 | $400.00 | 40 | $500.00 |
| Region 09 | 11 | $500.00 | 39 | $450.00 |
| Region 03 | 7 | $640.00 | 26 | $500.00 |
| Region 01 | 8 | $407.50 | 22 | $407.50 |
| Region 05 | 6 | $382.50 | 22 | $500.00 |
| Region 08 | 5 | $600.00 | 22 | $525.00 |
| Region 10 | 3 | $450.00 | 16 | $500.00 |
Regions with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 13 | $640.00 |
| 2 to 4 | 13 | $415.00 |
| 4 to 10 | 13 | $725.00 |
| 10 to 110 | 14 | $325.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Elderlee Inc | 19 | 12 (63%) |
| McLaughlin Construction Corp/DBA Edbauer Construction | 16 | 12 (75%) |
| Cold Spring Construction Company | 27 | 11 (41%) |
| Rifenburg Construction Inc | 16 | 9 (56%) |
| Callanan Industries Inc | 9 | 7 (78%) |
| Economy Paving Co Inc | 11 | 6 (55%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 27 AUG 2026 | D265794 | Region 09 | 4 | $900.00 | $750.00 | 6 | Bothar Construction LLC | NYSDOT |
| 27 AUG 2026 | D265825 | Region 01 | 110 | $400.00 | $375.00 | 3 | Emi Guide Rail LLC | NYSDOT |
| 13 AUG 2026 | D265689 | Region 04 | 12 | $400.00 | $437.50 | 8 | Ramsey Constructors Inc | NYSDOT |
| 16 JUL 2026 | D265796 | Region 03 | 10 | $732.00 | $547.50 | 6 | Winn Construction Services Inc | NYSDOT |
| 21 MAY 2026 | D265781 | Region 08 | 2 | $792.00 | $792.00 | 5 | Hylan Datacom & Electrical LLC | NYSDOT |
| 07 MAY 2026 | D265753 | Region 09 | 2 | $856.00 | $870.35 | 2 | Lancaster Development and Tully Construction Co LLC | NYSDOT |
| 07 MAY 2026 | D265789 | Region 05 | 6 | $800.00 | $2,732.57 | 2 | Concrete Applied Technologies Corp/DBA:Catco | NYSDOT |
| 09 APR 2026 | D265760 | Region 03 | 82 | $80.00 | $290.00 | 2 | Elderlee Inc | NYSDOT |
| 26 MAR 2026 | D265718 | Region 07 | 72 | $50.00 | $400.00 | 2 | Elderlee Inc | NYSDOT |
| 26 MAR 2026 | D265735 | Region 09 | 6 | $1,214.12 | $1,214.12 | 1 | Callanan Industries Inc | NYSDOT |
| 26 MAR 2026 | D265744 | Region 09 | 4 | $800.00 | $818.50 | 2 | Cobleskill Stone Products Inc. | NYSDOT |
| 12 MAR 2026 | D265705 | Region 01 | 6 | $1,600.00 | $1,255.00 | 2 | Rifenburg Construction Inc | NYSDOT |
| 12 MAR 2026 | D265720 | Region 09 | 2 | $853.50 | $853.50 | 1 | Bothar Construction LLC | NYSDOT |
| 12 MAR 2026 | D265736 | Region 09 | 6 | $320.00 | $355.50 | 2 | Dalrymple Gravel & Contracting Co Inc | NYSDOT |
| 12 MAR 2026 | D265758 | Region 05 | 25 | $110.00 | $325.00 | 3 | McLaughlin Construction Corp/DBA Edbauer Construction | NYSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the NYSDOT explorer.
How these prices were read
NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are NYSDOT's own: this item is compared with NYSDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the NYSDOT letting of 15 OCT 2026 and was rebuilt on 26 NOV 2026.