NYSDOT contract D265794 bid tabulation

Large Culvert Replacement. Let by New York State DOT on August 27, 2026, Broome, Chenango, Delaware, Sullivan, Region 09. 6 bids received; low bid $9,323,525 by Bothar Construction LLC.

Owner
New York State DOT
Letting
27 AUG 2026
Pay items
144
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Bothar Construction LLC$9,323,525Low
2Economy Paving Co Inc$9,699,997+4.0%
3BP Excavation LLC$9,781,650+5.0%
4Vector Construction Corp$10,355,970+11%
5Maple Ridge Civil LLC$10,525,000+13%
6Lancaster Development and Tully Construction Co LLC$12,822,851+38%
NYSDOT contract D265794: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Bothar Construction LLC2. Economy Paving Co Inc3. BP Excavation LLC4. Vector Construction Corp5. Maple Ridge Civil LLC6. Lancaster Development and Tully Construction Co LLC
1Clearing and Grubbing (201.07)ACRE1.50$32,000$1,000.00$81,000$30,000$19,000$10,000
2 (203.01990006)729$105.00$105.00$76.00$60.00$115.00$110.00
3Unclassified Excavation and Disposal (203.02)CY1,637$24.80$35.00$21.00$45.00$28.00$83.80
4Embankment In Place (203.03)CY9,364$37.00$25.00$25.00$30.00$57.00$33.30
5Select Granular Fill (203.07)CY1,609$77.65$75.00$64.00$65.00$58.00$116.00
6 (203.24010017)156$42.00$30.00$85.00$90.00$130.00$160.00
7 (203.51990006)251$14.00$10.00$21.00$23.00$33.00$32.90
8Structure Excavation (206.01)CY12,242$37.50$25.00$28.00$35.00$30.00$46.30
9Trench and Culvert Excavation (206.0201)CY327$14.00$10.00$42.00$45.00$38.00$108.00
10Geotextile Bedding (207.20)SY1,504$4.00$3.20$5.50$6.00$5.50$6.50
11Geotextile Drainage (207.22)SY100$10.00$10.00$18.00$12.00$4.50$6.35
12Prefabricated Composite Structural Drain (207.26)SY776$17.00$7.75$21.00$19.00$15.00$46.40
13 (208.01000809)84$110.00$100.00$150.00$100.00$71.00$213.00
14Seed and Mulch – Temporary (209.1003)SY3,598$4.50$1.50$4.00$1.00$0.85$2.20
15Check Dam (Ditch Bottom Width 0.0 to 3′), Stone – Temporary (209.110101)EACH7$1,000.00$500.00$700.00$225.00$1,150.00$1,840.00
16Check Dam, (Ditch Bottom Width 0.0 to 3′), Stone – Permanent (209.110601)EACH9$1,500.00$500.00$550.00$225.00$1,250.00$1,280.00
17Sediment Filter Log – Temporary, 12″, Type A (209.1311)LF1,360$7.50$8.00$11.00$8.00$6.50$10.20
18Rolled Erosion Control Product, Class II Type A, Intermediate (209.1901)SY3,598$3.50$5.00$7.50$4.00$5.50$7.35
19Soil Stabilizers, Class IV Type C (209.2103)SY3,506$2.30$2.50$2.00$4.00$1.50$4.50
20Stabilized Construction Access (209.22)SY1,071$21.40$10.00$36.00$30.00$8.00$88.00
21Subbase Course, Type 1 (304.11)CY326$37.00$55.00$114.00$125.00$86.00$165.00
22Subbase Course, Optional Type (304.15)CY967$77.00$95.00$79.00$110.00$78.00$158.00
23 (404.0189)TON1,052$189.00$195.00$175.00$190.00$140.00$232.00
24 (404.0982)TON994$191.00$195.00$185.00$190.00$150.00$232.00
25 (404.2589)TON878$199.00$195.00$175.00$185.00$150.00$195.00
26 (404.4489)TON1,545$158.00$155.00$175.00$190.00$140.00$172.00
27 (407.01040009)826$8.25$3.00$17.00$15.00$9.00$38.70
28Asphalt Pavement Joint Adhesive (418.7603)LF8,215$1.35$0.50$15.00$15.00$0.55$2.40
29Miscellaneous Cold Milling of Bituminous Concrete (490.30)SY8,890$10.35$7.50$9.00$8.00$7.50$16.90
30Interim Steel Sheeting (552.15)SF14,809$55.00$45.00$61.00$37.00$57.00$74.10
31 (553.030001)EACH1$38,500$2,000.00$32,000$5,000.00$115,000$41,400
32 (553.030002)EACH1$15,800$2,000.00$32,000$20,000$115,000$41,400
33 (553.030003)EACH1$15,800$2,000.00$32,000$20,000$115,000$41,400
34 (553.030004)EACH1$18,800$2,000.00$50,000$40,000$115,000$41,400
35 (553.030005)EACH1$18,800$2,000.00$80,000$30,000$115,000$41,400
36 (553.030006)EACH1$28,300$2,000.00$50,000$30,000$115,000$41,400
37 (554.3001)SF1,970$47.75$10.00$20.00$80.00$58.00$128.00
38Steel Bridge Railing (Three-Rail) (568.54)LF36$350.75$300.00$310.00$310.00$345.00$562.00
39Transition Bridge Railing (568.70)LF116$319.70$300.00$282.00$300.00$275.00$388.00
40 (595.50000018)4,717$3.00$8.00$5.00$5.00$4.50$26.10
41 (603.63060515)58$1,998.65$5,000.00$2,274.00$2,900.00$1,800.00$2,700.00
42 (603.63100715)79$2,591.65$7,000.00$3,242.00$3,300.00$2,350.00$3,150.00
43 (603.63120715)57$2,954.35$6,000.00$3,580.00$4,000.00$2,600.00$3,770.00
44 (603.63140515)35$5,256.45$10,000$5,980.00$4,000.00$5,100.00$5,570.00
45 (603.63140815)88$3,302.75$6,500.00$4,096.00$4,300.00$3,100.00$4,180.00
46 (603.64140815)97$3,259.35$7,500.00$3,961.00$4,200.00$2,850.00$4,320.00
47 (603.67000001)505$1,733.85$850.00$1,651.00$1,100.00$1,400.00$2,170.00
48 (605.1602)LF392$1.75$15.00$25.00$9.00$24.00$17.60
49Box Beam Guide Railing (606.10)LF3,465$65.55$55.00$60.00$60.00$47.00$79.60
50Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002)LF110$76.50$65.00$68.00$70.00$66.00$92.90
51 (606.10010004)18$115.00$100.00$125.00$110.00$93.00$140.00
52Box Beam End Piece (606.120101)EACH1$948.75$900.00$900.00$1,000.00$760.00$1,150.00
53Box Beam Guide Railing End Assembly Type I (606.120102)EACH3$6,325.00$6,000.00$5,800.00$6,500.00$4,400.00$7,680.00
54Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH15$2,875.00$3,000.00$2,600.00$3,000.00$2,150.00$3,490.00
55Box Beam End Assembly Type III (606.1203)EACH2$9,200.00$8,000.00$8,500.00$9,000.00$6,150.00$11,200
56Removing and Storing Box Beam Guide Railing (606.63)LF1,399$7.70$5.00$6.00$8.00$4.50$7.00
57Removing and Storing Box Beam Guide Railing End Assembly (606.6920)EACH10$900.00$100.00$175.00$130.00$36.00$209.00
58Removing and Disposing Corrugated Beam Guide Railing (606.71)LF1,138$7.75$5.00$4.00$8.00$5.00$4.55
59Removing and Disposing Box Beam Guide Railing (606.73)LF515$4.00$5.00$6.00$8.00$8.00$7.00
60Removing and Disposing Anchorage Units for Corrugated Beam Guide Railing and Median Barrier (606.7910)EACH4$900.00$100.00$850.00$130.00$650.00$1,080.00
61Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920)EACH8$900.00$100.00$200.00$130.00$170.00$209.00
62Right-of Way Fencing (607.19)LF281$62.10$55.00$40.00$60.00$120.00$75.40
63 (607.41010010)41$23.00$10.00$20.00$11.00$27.00$25.90
64 (607.99980007)281$23.00$5.00$25.00$5.00$52.00$27.90
65Concrete Sidewalks and Driveways (608.0101)CY3$2,200.00$2,000.00$4,000.00$1,600.00$2,500.00$1,500.00
66Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON142$205.00$300.00$500.00$550.00$225.00$370.00
67 (610.10020309)92$105.00$65.00$90.00$80.00$175.00$323.00
68Weed Removal (610.13)SY9,154$0.65$0.50$2.00$0.50$3.00$0.73
69Topsoil – Reuse On-Site Materials (610.1401)CY1,105$63.00$5.00$32.00$70.00$43.00$178.00
70Topsoil – On-Site Wetland Materials (610.1406)CY36$73.00$100.00$130.00$70.00$130.00$204.00
71 (610.15120208)1,072$4.25$1.00$4.00$3.50$3.00$5.45
72Turf Establishment - Roadside (610.1601)SY8,197$1.75$1.50$3.00$1.60$1.50$3.75
73Turf Establishment -Lawns (610.1602)SY1,511$1.75$1.50$8.00$1.60$2.00$5.05
74Watering Vegetation (610.19)1,000 GALLONS1,379$2.30$2.50$23.00$2.00$19.00$2.90
75Mowing (610.21)SY9,154$0.60$0.50$0.75$0.50$1.00$0.73
76 (611.0151)EACH12$920.00$950.00$850.00$800.00$720.00$1,170.00
77 (611.0292)EACH35$805.00$750.00$800.00$700.00$530.00$1,020.00
78 (611.0351)EACH9$575.00$550.00$860.00$500.00$535.00$730.00
79 (611.0451)EACH141$138.00$125.00$100.00$120.00$74.00$175.00
80 (611.19010024)12$23.00$25.00$250.00$20.00$100.00$29.20
81 (611.19020024)35$23.00$25.00$250.00$20.00$75.00$29.20
82 (611.19030024)9$23.00$25.00$275.00$20.00$110.00$29.20
83 (611.19040024)141$5.75$5.00$35.00$5.00$27.00$7.30
84 (613.04000001)636$108.00$20.00$45.00$46.00$105.00$150.00
85 (614.060204)EACH5$900.00$50.00$225.00$400.00$650.00$1,260.00
86 (614.060304)EACH2$2,500.00$100.00$275.00$600.00$850.00$1,820.00
87 (614.060404)EACH3$2,500.00$150.00$400.00$1,200.00$1,500.00$2,230.00
88 (614.060504)EACH1$9,500.00$250.00$600.00$1,600.00$2,500.00$3,630.00
89 (616.08000024)30$23.00$25.00$100.00$20.00$13.00$29.20
90 (617.10000024)118$75.00$10.00$58.00$65.00$59.00$201.00
91 (617.11000024)LS1$3,500.00$1,000.00$5,000.00$2,000.00$865.00$3,740.00
92 (617.11100009)LS1$3,500.00$1,000.00$10,000$1,500.00$865.00$3,600.00
93Basic Work Zone Traffic Control (619.01)LS1$530,000$990,000$188,550$1,580,000$1,085,000$510,000
94Type III Construction Barricades (619.04)EACH84$115.00$10.00$100.00$160.00$170.00$138.00
95Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803)LF8,599$7.50$6.50$7.00$6.50$6.50$9.10
96 (619.100104)LF22,000$6.35$5.50$6.00$5.50$5.50$7.70
97 (619.111113)EACH14$5,135.00$1,500.00$3,500.00$8,000.00$6,200.00$10,300
98 (619.130101)EACH1$81,650$75,000$155,000$130,000$80,000$80,300
99 (619.130102)EACH1$139,150$125,000$215,000$180,000$80,000$155,000
100Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711)LF1,840$40.75$60.00$90.00$35.00$58.00$77.20
101Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716)LF3,560$62.50$60.00$90.00$40.00$70.00$87.50
102Warning Lights on Temporary Positive Barriers (619.1719)EACH131$60.00$10.00$50.00$22.00$30.00$117.00
103Temporary Impact Attenuator - Redirective (Test Level 2) (619.1802)EACH33$2,200.00$3,000.00$7,800.00$9,000.00$4,750.00$16,800
104Temporary Rumble Strips (619.22)LF1,150$24.15$5.00$22.00$21.00$21.00$21.40
105Mailboxes (619.27)EACH11$300.00$600.00$225.00$280.00$345.00$597.00
106Stone Filling (Heavy) (620.05)CY456$196.00$135.00$150.00$150.00$155.00$228.00
107Bedding Material, Type 1 (620.0801)CY104$144.75$115.00$90.00$100.00$115.00$217.00
108Bedding Material, Type 2 (620.0802)CY104$143.00$115.00$90.00$100.00$110.00$217.00
109 (620.14020009)553$245.75$155.00$180.00$175.00$210.00$209.00
110 (621.05020004)6,311$5.10$1.00$8.00$5.00$5.50$9.45
111Crushed Stone (In-Place Measure) (623.12)CY294$137.20$95.00$122.00$150.00$160.00$224.00
112 (623.12110001)18$139.00$125.00$235.00$150.00$250.00$159.00
113 (623.12120001)28$139.00$125.00$235.00$150.00$235.00$161.00
114Survey Operations (625.01)LS1$275,000$100,000$145,335$200,000$690,000$339,989
115Concrete Right of Way Markers Type L (Low) (625.04)EACH4$1,690.00$5,000.00$6,800.00$1,100.00$1,000.00$1,240.00
116Steel Pin and Cap Right of Way Markers (625.05)EACH2$941.00$3,000.00$3,100.00$400.00$400.00$819.00
117Permanent Survey Markers (625.06)EACH10$4,670.00$4,000.00$5,000.00$900.00$2,000.00$3,320.00
118 (627.50140008)1,598$8.15$1.00$5.00$5.20$2.00$15.30
119 (634.99010017)LS1$12,600$5,000.00$20,000$4,000.00$10,000$26,100
120 (634.99020017)LS1$3,300.00$2,500.00$10,000$1,100.00$5,000.00$9,250.00
121Concrete Cylinder Curing Equipment (637.04)EACH1$2,800.00$6,000.00$1,500.00$5,000.00$5,550.00$7,840.00
122Engineer’s Field Office – Type 2 (637.12)MONTH26$2,500.00$3,000.00$2,400.00$2,500.00$3,000.00$8,140.00
123Office Technology and Supplies (637.34)DOL500$1.00$1.00$1.00$1.00$1.00$1.00
124Construction Testing supplies – Consumables (637.36)DOL500$1.00$1.00$1.00$1.00$1.00$1.00
125 (637.41000115)26$145.00$100.00$150.00$70.00$300.00$166.00
126 (637.41000215)26$145.00$100.00$150.00$70.00$300.00$166.00
127White Paint Reflectorized Pavement Stripes – 20 mils (640.20)LF3,587$0.70$0.65$1.50$1.40$0.60$0.82
128Yellow Paint Reflectorized Pavement Stripes - 20 mils (640.21)LF1,757$0.70$0.65$2.00$1.40$0.60$0.82
129Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF83$48.30$45.00$45.00$45.00$30.00$58.70
130Type A Sign Posts (645.81)EACH10$276.00$245.00$250.00$250.00$79.00$335.00
131Reference Marker Panel (646.21)EACH7$51.75$45.00$50.00$45.00$28.00$62.80
132Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23)EACH30$33.35$35.00$35.00$30.00$13.00$40.50
133Steel Post, 2.0 lb/ft (646.32)EACH33$96.60$95.00$90.00$85.00$50.00$117.00
134Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61)EACH9$57.50$50.00$55.00$40.00$10.00$69.80
135 (647.83001002)28$11.50$10.00$15.00$12.00$10.00$14.00
136Centerline Audible Roadway Delineators (CARDs) (649.11)LF1,515$2.50$8.50$2.00$6.00$2.00$9.80
137White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102)LF4,474$2.05$3.75$8.00$7.00$2.00$2.50
138Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202)LF379$2.05$3.75$9.00$7.00$1.00$2.50
139 (691.04000020)110,000$1.00$1.00$1.00$1.00$1.00$1.00
140Field Change Payment (FCP) (697.03)DOL450,000$1.00$1.00$1.00$1.00$1.00$1.00
141Asphalt Price Adjustment (698.04)DOL1,200$1.00$1.00$1.00$1.00$1.00$1.00
142Fuel Price Adjustment (698.05)DOL1,700$1.00$1.00$1.00$1.00$1.00$1.00
143Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00$1.00$1.00
144Mobilization (699.040001)LS1$300,115$370,554$375,000$396,000$401,287$492,001
NYSDOT contract D265794: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of August 27, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way