NYSDOT contract D265781 bid tabulation

INTERCHANGE IMPROVEMENTS - CROSS COUNTY PARKWAY EXIT 3. Let by New York State DOT on May 21, 2026, Westchester, Region 08. 5 bids received; low bid $3,042,241 by Hylan Datacom & Electrical LLC.

Owner
New York State DOT
Letting
21 MAY 2026
Pay items
117
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Hylan Datacom & Electrical LLC$3,042,241Low
2Westmoreland Construction Inc$3,366,235+11%
3Petrillo Contracting Inc$3,422,979+13%
4Montesano Bros Inc$3,772,961+24%
5Tully Construction Company Inc$5,702,170+87%
NYSDOT contract D265781: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Hylan Datacom & Electrical LLC2. Westmoreland Construction Inc3. Petrillo Contracting Inc4. Montesano Bros Inc5. Tully Construction Company Inc
1Clearing and Grubbing (201.06)LS1$23,760$100,000$36,000$250,000$40,000
2Unclassified Excavation and Disposal (203.02)CY320$184.80$250.00$300.00$120.00$200.00
3Embankment In Place (203.03)CY155$89.76$270.00$100.00$60.00$260.00
4Select Granular Fill (203.07)CY70$89.76$180.00$120.00$100.00$345.00
5Controlled Low Strength Material (CLSM) (204.01)CY10$2,059.20$275.00$240.00$350.00$1,545.00
6Trench and Culvert Excavation (206.0201)CY110$100.32$250.00$200.00$230.00$300.00
7Conduit Excavation and Backfill including Surface Restoration (206.03)LF1,500$132.00$50.00$150.00$80.00$53.00
8Mulch – Temporary (209.100101)SY3,880$15.84$4.00$3.00$4.00$3.65
9Seed – Temporary (209.100102)SY3,880$9.51$3.00$4.00$1.00$3.65
10Silt Fence - Temporary (209.13)LF350$12.67$10.00$14.00$15.00$18.25
11Drainage Structure Inlet Protection, Gravel Bag – Temporary (209.1702)CY5$343.20$400.00$2,000.00$390.00$4,250.00
12Stabilized Construction Access (209.22)SY160$58.08$40.00$50.00$190.00$335.00
13 (209.23010009)700$15.84$15.00$30.00$15.00$43.00
14 (304.11000008)125$167.80$180.00$120.00$100.00$250.00
15Pavement Density Quality Adjustment to Asphalt Items (404.0002)QUALITY UNIT29$140.00$140.00$140.00$140.00$140.00
16 (404.0189)TON20$158.40$180.00$280.00$175.00$1,670.00
17 (404.1251)TON575$237.60$220.00$205.00$190.00$310.00
18 (404.2579)TON725$221.76$190.00$230.00$250.00$340.00
19 (404.3779)TON90$290.40$250.00$400.00$400.00$620.00
20Straight Tack Coat (407.0103)GAL550$26.40$20.00$15.00$15.00$29.00
21Asphalt Pavement Joint Adhesive (418.7603)LF3,300$2.64$4.00$3.00$1.50$2.00
22Production Cold-Mill Surface Planing of Bituminous Concrete (490.15)SY5,100$8.45$22.00$22.00$18.00$24.00
23Shields and Shoring (552.17)SF1,100$4.23$10.00$24.00$7.00$52.00
24 (603.171614)EACH1$1,900.80$3,500.00$4,000.00$3,500.00$5,200.00
25 (603.9818)LF48$264.00$53.00$180.00$225.00$230.00
26 (603.9824)LF32$528.00$65.00$200.00$335.00$330.00
27 (604.070801)EACH1$6,864.00$1,200.00$3,200.00$2,700.00$12,500
28 (604.07290010)45$475.20$400.00$200.00$160.00$280.00
29 (604.301772)LF12$1,003.20$1,100.00$1,500.00$1,300.00$1,100.00
30 (604.301873)LF6.50$1,531.20$1,300.00$1,700.00$1,290.00$1,840.00
31Box Beam Guide Railing (606.10)LF925$105.60$107.00$80.00$87.00$72.00
32Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002)LF210$153.12$116.00$90.00$93.00$210.00
33Box Beam End Piece (606.120101)EACH3$8,976.00$1,400.00$1,100.00$1,340.00$450.00
34Box Beam Guide Railing End Assembly Type I (606.120102)EACH1$9,504.00$11,000$2,200.00$6,900.00$4,500.00
35Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH1$7,392.00$8,000.00$4,000.00$3,575.00$8,500.00
36Box Beam End Assembly Type III (606.1203)EACH1$6,864.00$18,000$10,000$11,150$12,000
37Box Beam Median Barrier End Assembly, Type C (606.1403)EACH1$13,728$22,000$10,000$12,300$12,000
38Removing and Disposing Corrugated Beam Guide Railing (606.71)LF265$15.84$10.00$15.00$15.00$10.00
39Removing and Disposing Box Beam Guide Railing (606.73)LF825$10.56$30.00$15.00$19.00$10.00
40Removing and Disposing Anchorage Units for Corrugated Beam Guide Railing and Median Barrier (606.7910)EACH2$792.00$500.00$1,100.00$1,000.00$250.00
41Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920)EACH4$792.00$115.00$3,000.00$800.00$250.00
42Removing and Disposing Box Beam Median Barrier End Assembly--Type B (606.7931)EACH1$1,056.00$700.00$1,100.00$1,500.00$400.00
43Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON6$7,920.00$1,000.00$600.00$1,000.00$1,360.00
44 (608.13000102)410$211.20$100.00$40.00$170.00$120.00
45 (609.0405)LF115$369.60$110.00$200.00$124.00$245.00
46 (609.0407)LF740$158.40$110.00$110.00$75.00$97.00
47Compost (610.10)CY35$264.00$50.00$150.00$55.00$155.00
48Weed Removal (610.13)SY1,970$2.12$6.00$2.00$5.00$12.50
49Topsoil - Roadside (610.1402)CY130$132.00$105.00$150.00$175.00$155.00
50 (610.15030108)1,680$7.92$5.00$6.00$6.00$7.50
51Turf Establishment - Roadside (610.1601)SY1,175$5.28$3.00$8.00$5.00$7.50
52Wildflower Seeding (610.17)SY1,680$10.56$5.00$5.00$3.65$7.50
53Watering Vegetation (610.19)1,000 GALLONS80$316.80$160.00$150.00$165.00$1.25
54Mowing (610.21)SY980$2.11$2.00$3.00$1.50$1.25
55Mowing Limits Markers (610.22)EACH9$158.40$110.00$250.00$185.00$390.00
56Improvement of Vegetated Areas (614.05)SY50$31.68$30.00$25.00$5.50$30.00
57 (617.11000024)LS1$6,336.00$500.00$20,000$4,400.00$120.00
58Basic Work Zone Traffic Control (619.01)LS1$211,200$700,000$345,000$500,000$1,500,000
59Type III Construction Barricades (619.04)EACH12$369.60$5,000.00$600.00$1,250.00$840.00
60 (619.080101)LF6,100$2.12$3.50$2.00$2.80$3.50
61 (619.080201)EACH3$179.52$200.00$130.00$165.00$120.00
62 (619.110513)EACH3$6,336.00$15,000$14,000$16,500$74,000
63Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716)LF920$63.36$180.00$250.00$260.00$185.00
64Warning Lights on Temporary Positive Barriers (619.1719)EACH47$42.24$110.00$200.00$115.00$230.00
65Nighttime Operations (Entire Project) (619.24)LS1$64,015$95,000$150,000$110,000$460,000
66Traffic Control Supervisor (619.25)MONTH8$18,290$12,000$15,000$37,000$6,750.00
67Survey Operations (625.01)LS1$5,280.00$25,000$110,000$250,000$600,000
68 (627.50140008)1,500$15.84$7.00$6.00$14.00$25.00
69 (633.05040008)LS1$264,000$25,000$18,000$45,000$43,210
70Concrete Cylinder Curing Equipment (637.04)EACH1$6,500.00$2,000.00$5,000.00$6,150.00$6,100.00
71Engineer’s Field Office – Type 2 (637.12)MONTH8$1,597.00$8,000.00$8,000.00$11,000$12,100
72Office Technology and Supplies (637.34)DOL2,000$1.00$1.00$1.00$1.00$1.00
73 (637.41000115)8$105.60$200.00$6,000.00$560.00$455.00
74 (637.41000215)8$105.60$200.00$7,000.00$560.00$455.00
75Ground-Mounted Sign Panels without Z-bars (645.5101)SF4$84.48$90.00$100.00$115.00$100.00
76Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF208$89.76$90.00$100.00$56.00$100.00
77Type A Sign Posts (645.81)EACH42$660.00$500.00$350.00$465.00$220.00
78 (645.81090003)14$79.20$125.00$100.00$140.00$275.00
79Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22)EACH20$105.60$60.00$80.00$45.00$75.00
80Steel Post, 2.0 lb/ft (646.32)EACH10$237.60$500.00$60.00$198.00$200.00
81Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31)EACH6$1,003.20$800.00$400.00$360.00$400.00
82Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41)EACH9$1,003.20$500.00$100.00$600.00$490.00
83Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61)EACH11$1,900.80$500.00$200.00$300.00$305.00
84 (649.31000008)755$2.12$15.00$3.00$19.00$33.00
85Cast Frame F2, Mountable Curb Box CM2 & Reticuline Grate G2 (655.0702)EACH2$3,168.00$3,500.00$3,600.00$7,300.00$8,100.00
86Cast Frame F3, Mountable Curb Box CM3 & Reticuline Grate G3 (655.0703)EACH1$3,168.00$3,800.00$4,000.00$7,300.00$8,100.00
87 (670.0106)EACH12$2,820.10$2,800.00$7,400.00$3,300.00$1,900.00
88 (670.01120302)13$680.84$1,100.00$1,100.00$1,050.00$1,250.00
89 (670.03070008)1$728.06$3,000.00$1,800.00$2,000.00$10,000
90 (670.1130)EACH12$2,916.86$4,500.00$4,600.00$4,500.00$4,900.00
91 (670.1206)EACH10$662.40$1,200.00$1,200.00$1,150.00$1,240.00
92 (670.1320)EACH3$2,438.78$2,800.00$3,000.00$2,825.00$3,000.00
93Breakaway Transformer Base (Aluminum) (670.19)EACH12$1,440.00$1,300.00$1,500.00$1,330.00$1,200.00
94 (670.2602)LF1,600$29.61$20.00$20.00$18.00$20.00
95Pullboxes 5 to 7 1/2 cubic feet, inside volume (Lighting) (670.3006)EACH2$1,707.26$6,200.00$11,500$5,600.00$5,200.00
96Photoelectric Controls (670.60)EACH13$302.98$300.00$250.00$235.00$250.00
97 (670.7004)LF6,100$5.95$6.00$6.00$5.30$5.00
98Ground Wire No. 6 AWG. (670.7501)LF2,100$5.95$6.00$6.00$5.30$5.00
99Remove and Dispose of Lamppost Assembly (670.81)EACH10$728.06$2,000.00$600.00$1,450.00$1,565.00
100Remove Lamppost Foundation (670.82)EACH12$1,092.10$2,500.00$3,000.00$1,060.00$2,000.00
101Performance Concrete Quality Adjustment (670.99)QUALITY UNIT1$12.89$12.89$12.89$12.89$12.89
102Pole Excavation and Concrete Foundation (680.5001)CY4$4,224.00$2,000.00$7,500.00$3,300.00$8,100.00
103 (680.6816)EACH2$2,613.89$4,500.00$5,000.00$4,500.00$4,860.00
104Solar Power System (680.81)EACH2$2,456.06$15,000$12,000$12,000$12,975
105Flashing Beacon Sign Assembly (680.8220)EACH2$4,760.07$11,000$10,000$9,350.00$10,100
106Breakaway Transformer Base (680.8223)EACH2$1,440.00$1,500.00$6,000.00$1,340.00$1,450.00
107Performance Concrete Quality Adjustment (680.99)QUALITY UNIT1$27.50$27.50$27.50$27.50$27.50
108 (685.16010014)6,100$2.39$2.00$3.00$1.70$2.00
109 (685.17010014)2,800$2.39$2.00$3.00$1.70$2.00
110White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104)LF7,000$2.39$3.10$2.00$3.00$2.00
111White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304)EACH5$237.60$200.00$300.00$167.00$150.00
112White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404)EACH4$237.60$250.00$300.00$250.00$175.00
113Field Change Payment (FCP) (697.03)DOL103,000$1.00$1.00$1.00$1.00$1.00
114Asphalt Price Adjustment (698.04)DOL1,235.78$1.00$1.00$1.00$1.00$1.00
115Fuel Price Adjustment (698.05)DOL100$1.00$1.00$1.00$1.00$1.00
116Steel/Iron Price Adjustment (698.06)DOL200$1.00$1.00$1.00$1.00$1.00
117Mobilization (699.040001)LS1$117,009$129,400$131,653$140,000$190,000
NYSDOT contract D265781: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of May 21, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy