Montesano Bros Inc: NYSDOT bid record
Montesano Bros Inc submitted 22 bids on New York State DOT contracts in the data, from 19 JAN 2023 to 21 MAY 2026, and was the low bidder on 1 of them (5%). When it was not low, its total sat a median +28% above the low bid.
- Owner
- New York State DOT
- Low bid volume
- $4,890,205
- Latest bid
- 21 MAY 2026
- Data through
- 15 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2023 | 7 | 0 | 0% |
| 2024 | 3 | 1 | 33% |
| 2025 | 4 | 0 | 0% |
| 2026 | 8 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Field Change Payment (FCP) | 697.03 | DOL | 22 | 22 (100%) | $1.00 | $1.00 |
| Office Technology and Supplies | 637.34 | DOL | 22 | 22 (100%) | $1.00 | $1.00 |
| Fuel Price Adjustment | 698.05 | DOL | 22 | 22 (100%) | $1.00 | $1.00 |
| Asphalt Price Adjustment | 698.04 | DOL | 22 | 22 (100%) | $1.00 | $1.00 |
| Steel/Iron Price Adjustment | 698.06 | DOL | 19 | 19 (100%) | $1.00 | $1.00 |
| Pavement Density Quality Adjustment to Asphalt Items | 404.0002 | QUALITY UNIT | 12 | 12 (100%) | $140.00 | $110.00 |
| Longitudinal Joint Density Quality Adjustment to Asphalt Items | 404.0003 | QUALITY UNIT | 10 | 10 (100%) | $140.00 | $110.00 |
| Plant Production Quality Adjustment to Asphalt Items | 404.000011 | QUALITY UNIT | 8 | 8 (100%) | $105.00 | $85.00 |
| Pavement Density Quality Adjustment to Asphalt Items | 404.000021 | QUALITY UNIT | 8 | 8 (100%) | $105.00 | $85.00 |
| Plant Production Quality Adjustment to 624.020101 | 624.020110 | QUALITY UNIT | 7 | 7 (100%) | $110.00 | $110.00 |
| Unclassified Excavation and Disposal | 203.02 | CY | 19 | 6 (32%) | $179.00 | $71.00 |
| 404.0001 | TON | 6 | 6 (100%) | $120.00 | $95.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Elq Industries Inc | 16 | 13 of 16 |
| Morano Brothers Corp | 15 | 13 of 15 |
| Jrcruz Corp | 9 | 4 of 9 |
| Grace Industries LLC | 9 | 7 of 9 |
| Yonkers Contracting Company Inc | 9 | 7 of 9 |
| Northbrook Contracting Corp | 4 | 4 of 4 |
| Petrillo Contracting Inc | 4 | 4 of 4 |
| Paleen Construction Corp | 3 | 3 of 3 |
| Tilcon New York Inc | 3 | 3 of 3 |
| Transit Construction Corp | 2 | 2 of 2 |
Latest bids
| Let | Contract | Region | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 21 MAY 2026 | D265781 | Region 08 | INTERCHANGE IMPROVEMENTS - CROSS COUNTY PARKWAY EXIT 3 | 4 of 5 | $3,772,961 | +24% |
| 21 MAY 2026 | D265783 | Region 08 | WALL REPAIR: ROUTE 22 - SCARSDALE | 2 of 3 | $5,812,231 | +16% |
| 26 MAR 2026 | D265748 | Region 08 | PMI: RESURFACING OF ROUTE 117 AND ROUTE 9A | 6 of 6 | $17,899,594 | +32% |
| 26 MAR 2026 | D265749 | Region 08 | PAVEMENT MAINTENANCE - Various Routes | 4 of 4 | $4,610,744 | +41% |
| 26 FEB 2026 | D265647 | Region 08 | Wall Repair, Drainage and Pavement Improvements. | 3 of 3 | $4,889,666 | +15% |
| 22 JAN 2026 | D265654 | Region 08 | PAVEMENT RESURFACING - US ROUTE 1 AND PUTNAM AVENUE | 7 of 9 | $10,984,908 | +28% |
| 22 JAN 2026 | D265679 | Region 08 | PAVEMENT RESURFACING - Routes 133 & 100B | 6 of 6 | $9,515,002 | +23% |
| 08 JAN 2026 | D265648 | Region 08 | ROADWAY RESURFACING - Route 303, SH 8448, 5002 | 8 of 8 | $13,351,384 | +45% |
| 24 APR 2025 | D265484 | Region 08 | ROUTE 134 RESURFACING ROUTE 9A | 6 of 6 | $3,301,073 | +61% |
| 20 MAR 2025 | D265471 | Region 08 | RESURFACING - Route 312 | 6 of 6 | $2,997,749 | +43% |
| 27 FEB 2025 | D265424 | Region 08 | Replacement and Relining of Culverts - Various locations | 4 of 5 | $16,581,083 | +24% |
| 20 FEB 2025 | D265427 | Region 08 | ROUTE 52 - RESURFACING PUTNAM COUNTY | 7 of 7 | $4,816,447 | +21% |
| 12 SEP 2024 | D265312 | Region 08 | RESURFACING - ROUTES 100A 100B TO 100C/100 | 1 of 6 | $4,890,205 | Low, 0.0% under the second |
| 09 MAY 2024 | D265254 | Region 08 | ROUTE 9A RESURFACING ROUTE 133 TO MAIDEN LANE | 3 of 6 | $16,984,555 | +6.0% |
| 28 MAR 2024 | D265217 | Region 08 | Highway Reconstruction US Rt 6 at Annsville Circle | 6 of 6 | $36,975,816 | +54% |
| 13 JUL 2023 | D265052 | Region 08 | Route 35/202 Resurfacing, TSP to Route 118 | 3 of 4 | $4,799,012 | +16% |
| 04 MAY 2023 | D265029 | Region 08 | PMI PAVING: ROUTE 1 AND NEW ROCHELLE REFERENCE ROUTES | 4 of 6 | $13,803,370 | +35% |
| 20 APR 2023 | D265009 | Region 08 | HIGHWAY - SAFETY IMPROVEMENTS - Various Locations | 3 of 3 | $7,612,451 | +35% |
| 23 MAR 2023 | D264989 | Region 08 | RT6 & RT125 PAVE/PED IMPROVEMENTS TOWN CORTLANDT/MAMARONECK | 5 of 5 | $6,954,961 | +37% |
| 23 MAR 2023 | D265003 | Region 08 | ROUTE 52 PAVING | 3 of 3 | $4,511,060 | +16% |
| 16 FEB 2023 | D264937 | Region 08 | PMI ROUTE 9, GREENGURGH, WESTCHESTER COUNTY | 2 of 6 | $9,391,732 | +3.0% |
| 19 JAN 2023 | D264967 | Region 08 | TACONIC STATE PARKWAY | 8 of 8 | $4,850,000 | +158% |
How this record was read
NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
- Every bid counted here matched its published total to within one dollar; NYSDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.