Elq Industries Inc: NYSDOT bid record

Elq Industries Inc submitted 50 bids on New York State DOT contracts in the data, from 06 JAN 2022 to 27 AUG 2026, and was the low bidder on 7 of them (14%). When it was not low, its total sat a median +15% above the low bid.

Owner
New York State DOT
Low bid volume
$39,789,378
Latest bid
27 AUG 2026
Data through
15 OCT 2026
50Bids
7Low bids
14Win rate, percent
+15%Median gap to the low bid when not low, 43 bids

By year

YearBidsLow bidsWin rate
20229222%
20239333%
202410110%
20251000%
20261218%
Elq Industries Inc, NYSDOT: bids and low bids by year of letting

By region

RegionBidsLow bidsWin rate
Region 0849714%
Region 01, 02, 03, 04, 05, 06, 07, 08, 09, 10100%
Elq Industries Inc, NYSDOT: bids and low bids by region

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Office Technology and Supplies637.34DOL4747 (100%)$1.00$1.00
Field Change Payment (FCP)697.03DOL3939 (100%)$1.00$1.00
Fuel Price Adjustment698.05DOL3939 (100%)$1.00$1.00
Asphalt Price Adjustment698.04DOL3939 (100%)$1.00$1.00
Steel/Iron Price Adjustment698.06DOL3636 (100%)$1.00$1.00
Pavement Density Quality Adjustment to Asphalt Items404.0002QUALITY UNIT2020 (100%)$120.00$110.00
Longitudinal Joint Density Quality Adjustment to Asphalt Items404.0003QUALITY UNIT1818 (100%)$130.00$110.00
Plant Production Quality Adjustment to Asphalt Items404.000011QUALITY UNIT1616 (100%)$107.50$85.00
Pavement Density Quality Adjustment to Asphalt Items404.000021QUALITY UNIT1515 (100%)$105.00$85.00
404.0001TON1313 (100%)$120.00$95.00
619.0901LF3212 (38%)$0.40$0.40
Plant Production Quality Adjustment to 624.020101624.020110QUALITY UNIT1111 (100%)$110.00$110.00
Elq Industries Inc, NYSDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

Elq Industries Inc, NYSDOT: the firms on the same contracts most often

Latest bids

LetContractRegionProjectRankIts bidAgainst the low bid
27 AUG 2026D265828Region 08Standby Where & When Highway1 of 6$5,752,921Low, 5.0% under the second
30 JUL 2026D265821Region 082027-2028 Structures Where & When4 of 6$3,192,626+2.0%
30 JUL 2026D265822Region 082027-2028 Structures Where & When.5 of 5$3,267,626+4.0%
26 MAR 2026D265748Region 08PMI: RESURFACING OF ROUTE 117 AND ROUTE 9A5 of 6$16,047,105+19%
26 MAR 2026D265749Region 08PAVEMENT MAINTENANCE - Various Routes3 of 4$4,093,778+25%
12 MAR 2026D265713Region 08ROUTE 9 PAVING ROUTE 113 TO WEST DORSEY LANE2 of 2$14,887,753+9.0%
26 FEB 2026D265712Region 08CORRIDOR PAVING RTE 304: ROCKLAND COUNTY3 of 6$23,777,841+26%
26 FEB 2026D265714Region 08ROUTE 376 PAVING ROUTE 82 TO BOARDMAN ROAD DUTCHESS COUNTY2 of 4$8,788,831+4.0%
05 FEB 2026D265653Region 08PAVEMENT PREVENTATIVE MAINTENANCE - I-2875 of 6$36,296,197+40%
22 JAN 2026D265654Region 08PAVEMENT RESURFACING - US ROUTE 1 AND PUTNAM AVENUE6 of 9$9,973,914+16%
22 JAN 2026D265679Region 08PAVEMENT RESURFACING - Routes 133 & 100B5 of 6$9,297,303+20%
08 JAN 2026D265648Region 08ROADWAY RESURFACING - Route 303, SH 8448, 50027 of 8$12,373,607+34%
06 NOV 2025D265616Region 08Job Order Contract Highway Maintenance, Various Locations4 of 4$2,700,000+15%
11 SEP 2025D265557Region 08Standby Where & When Highway, Region-Wide4 of 6$6,416,341+9.0%
24 APR 2025D265484Region 08ROUTE 134 RESURFACING ROUTE 9A3 of 6$2,243,081+10%
20 MAR 2025D265471Region 08RESURFACING - Route 3125 of 6$2,643,720+26%
13 MAR 2025D265463Region 08CATCH BASIN REPAIRS - Hutchinson River Parkway, Rt 907W6 of 7$6,957,441+70%
27 FEB 2025D265424Region 08Replacement and Relining of Culverts - Various locations5 of 5$17,242,369+29%
27 FEB 2025D265442Region 08PAVEMENT RESURFACING - Route 176 of 7$12,497,007+29%
20 FEB 2025D265427Region 08ROUTE 52 - RESURFACING PUTNAM COUNTY6 of 7$4,687,505+17%
23 JAN 2025D265415Region 08RESURFACING - TACONIC STATE PARKWAY- Route 55 to Tyrrel Road5 of 7$7,408,726+30%
09 JAN 2025D265367Region 08Bridge Deck Replacement3 of 7$8,950,183+21%
24 OCT 2024D265349Region 08PAVEMENT RESURFACING - Route 452 of 5$4,727,284+13%
12 SEP 2024D265295Region 08Standby Where & When Highway Region_Wide1 of 6$5,341,559Low, 1.0% under the second
12 SEP 2024D265312Region 08RESURFACING - ROUTES 100A 100B TO 100C/1002 of 6$4,896,8210.0%
Elq Industries Inc: latest NYSDOT bids in the data

How this record was read

NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

  • Every bid counted here matched its published total to within one dollar; NYSDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy