NYSDOT contract D265484 bid tabulation

ROUTE 134 RESURFACING ROUTE 9A. Let by New York State DOT on April 24, 2025, Westchester, Region 08. 6 bids received; low bid $2,044,228 by Morano Brothers Corp.

Owner
New York State DOT
Letting
24 APR 2025
Pay items
36
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Morano Brothers Corp$2,044,228Low
2Yonkers Contracting Company Inc$2,211,356+8.0%
3Elq Industries Inc$2,243,081+10%
4Grace Industries LLC$2,615,135+28%
5Petrillo Contracting Inc$2,620,763+28%
6Montesano Bros Inc$3,301,073+61%
NYSDOT contract D265484: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Morano Brothers Corp2. Yonkers Contracting Company Inc3. Elq Industries Inc4. Grace Industries LLC5. Petrillo Contracting Inc6. Montesano Bros Inc
1 (203.24010017)100$170.00$325.00$121.35$270.00$100.00$550.00
2 (304.11000008)19$170.00$35.00$240.00$290.00$250.00$550.00
3 (404.0001)TON256$120.00$120.00$120.00$120.00$120.00$120.00
4Pavement Density Quality Adjustment to Asphalt Items (404.0002)QUALITY UNIT1$120.00$120.00$120.00$120.00$120.00$120.00
5Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003)QUALITY UNIT80$120.00$120.00$120.00$120.00$120.00$120.00
6 (404.0179)TON104$177.00$150.00$160.00$210.00$220.00$195.00
7 (404.1979)TON679$165.00$200.00$202.00$220.00$220.00$225.00
8 (406.1261)TON4,325$137.00$150.00$160.00$210.00$220.00$185.00
9Straight Tack Coat (407.0103)GAL2,322$12.00$11.00$10.25$4.50$20.00$17.00
10Asphalt Pavement Joint Adhesive (418.7603)LF27,474$1.40$1.55$1.00$0.11$1.00$1.39
11Production Cold-Mill Surface Planing of Bituminous Concrete (490.15)SY40,254$5.50$8.75$7.60$9.00$9.40$10.35
12 (604.070801)EACH1$2,500.00$20,000$2,200.00$3,800.00$3,200.00$5,555.00
13 (604.07290010)96$80.00$125.00$91.00$85.00$180.00$280.00
14Basic Work Zone Traffic Control (Daily Operations) (619.0101)LS1$250,000$244,000$310,000$434,310$280,000$325,000
15 (619.0901)LF33,240$0.40$0.40$0.40$0.45$1.00$0.40
16 (619.110532)EACH5$13,000$10,000$6,100.00$6,000.00$10,000$42,000
17Nighttime Operations (Entire Project) (619.24)LS1$145,000$55,000$174,000$90,000$75,000$325,000
18Traffic Control Supervisor (619.25)MONTH3$28,000$1,000.00$10,000$20,000$15,000$45,000
19Cleaning Closed Drainage Systems (621.03)LF225$25.00$12.00$25.00$13.00$40.00$180.00
20Cleaning Drainage Structures (621.04)EACH9$640.00$1,700.00$830.00$1,000.00$1,000.00$4,760.00
21Clean, Grade and Shape Existing Roadside Section (621.05)LF3,087$4.00$10.00$6.00$11.00$10.00$15.30
22Asphalt Gutter (624.020101)TON13$570.00$1,500.00$615.00$1,000.00$500.00$2,200.00
23Plant Production Quality Adjustment to 624.020101 (624.020110)QUALITY UNIT1$110.00$110.00$110.00$110.00$110.00$110.00
24Survey Operations (625.01)LS1$30,000$20,000$18,000$20,000$35,000$125,000
25 (627.50140008)170$6.00$15.00$19.00$23.00$20.00$28.00
26Engineer’s Field Office – Type 3 (637.13)MONTH10$6,000.00$12,500$5,500.00$5,000.00$8,000.00$5,500.00
27Office Technology and Supplies (637.34)DOL2,000$1.00$1.00$1.00$1.00$1.00$1.00
28Adjust Existing Valve Box Elevation (663.33)EACH10$200.00$1,000.00$500.00$320.00$500.00$980.00
29 (685.16010014)33,905$1.30$1.40$1.32$1.50$1.40$1.30
30 (685.17010014)23,268$1.30$1.40$1.32$1.50$1.40$1.30
31White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104)LF154$3.00$3.60$3.00$3.50$10.00$3.15
32Field Change Payment (FCP) (697.03)DOL126,000$1.00$1.00$1.00$1.00$1.00$1.00
33Asphalt Price Adjustment (698.04)DOL4,990$1.00$1.00$1.00$1.00$1.00$1.00
34Fuel Price Adjustment (698.05)DOL239$1.00$1.00$1.00$1.00$1.00$1.00
35Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00$1.00$1.00
36Mobilization (699.040001)LS1$73,000$80,000$84,000$90,000$92,000$125,000
NYSDOT contract D265484: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of April 24, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy