NYSDOT contract D265415 bid tabulation
RESURFACING - TACONIC STATE PARKWAY- Route 55 to Tyrrel Road. Let by New York State DOT on January 23, 2025, Dutchess, Region 08. 7 bids received; low bid $5,699,824 by Peckham Road Corp.
- Owner
- New York State DOT
- Letting
- 23 JAN 2025
- Pay items
- 48
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Peckham Road Corp | $5,699,824 | Low |
| 2 | A Colarusso & Son Inc | $5,922,714 | +4.0% |
| 3 | Yonkers Contracting Company Inc | $6,511,110 | +14% |
| 4 | Paleen Construction Corp | $6,534,934 | +15% |
| 5 | Elq Industries Inc | $7,408,726 | +30% |
| 6 | Morano Brothers Corp | $7,717,061 | +35% |
| 7 | Tilcon New York Inc | $8,130,000 | +43% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Peckham Road Corp | 2. A Colarusso & Son Inc | 3. Yonkers Contracting Company Inc | 4. Paleen Construction Corp | 5. Elq Industries Inc | 6. Morano Brothers Corp |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Unclassified Excavation and Disposal (203.02) | CY | 246 | $50.10 | $35.00 | $125.00 | $160.00 | $255.00 | $125.00 |
| 2 | Embankment In Place (203.03) | CY | 110 | $76.00 | $95.00 | $135.00 | $100.00 | $104.00 | $255.00 |
| 3 | (203.24010017) | 1,967 | $15.75 | $20.00 | $80.00 | $60.00 | $54.75 | $80.00 | |
| 4 | (304.11000008) | 18 | $379.65 | $545.00 | $100.00 | $250.00 | $537.00 | $218.00 | |
| 5 | (404.0001) | TON | 1,600 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 6 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 1,000 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 7 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 400 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 8 | (404.0179) | TON | 1,000 | $156.60 | $120.00 | $125.00 | $190.00 | $125.75 | $170.00 |
| 9 | (404.1979) | TON | 84 | $313.25 | $328.00 | $575.00 | $534.00 | $490.00 | $525.00 |
| 10 | (406.1251) | TON | 18,662 | $135.75 | $142.00 | $125.00 | $148.43 | $148.00 | $155.00 |
| 11 | Straight Tack Coat (407.0103) | GAL | 8,475 | $3.37 | $8.50 | $7.00 | $9.00 | $8.20 | $12.00 |
| 12 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 56,700 | $1.01 | $1.20 | $1.00 | $1.00 | $1.50 | $2.70 |
| 13 | Production Cold-Mill Surface Planing of Bituminous Concrete (490.15) | SY | 156,368 | $3.57 | $3.50 | $4.50 | $5.40 | $5.00 | $5.10 |
| 14 | (604.07290010) | 849 | $83.00 | $127.00 | $85.00 | $25.00 | $104.00 | $51.00 | |
| 15 | (604.07600008) | 25 | $4,450.00 | $8,000.00 | $7,000.00 | $5,500.00 | $9,263.00 | $3,330.00 | |
| 16 | Box Beam Guide Railing (606.10) | LF | 70 | $102.50 | $70.00 | $85.00 | $118.00 | $132.00 | $110.00 |
| 17 | Box Beam Median Barrier (606.11) | LF | 225 | $85.00 | $75.00 | $99.00 | $98.00 | $139.00 | $92.00 |
| 18 | Box Beam End Piece (606.120101) | EACH | 5 | $915.00 | $980.00 | $900.00 | $1,052.00 | $1,125.00 | $990.00 |
| 19 | Removing and Disposing Box Beam Median Barrier (606.74) | LF | 82 | $6.00 | $14.00 | $16.00 | $7.00 | $54.90 | $7.00 |
| 20 | Removing and Disposing Box Beam Median Barrier End Assembly-Type C (606.7932) | EACH | 1 | $700.00 | $940.00 | $200.00 | $805.00 | $2,743.00 | $1,800.00 |
| 21 | (609.12290008) | 436 | $130.00 | $152.00 | $165.00 | $60.00 | $183.00 | $40.00 | |
| 22 | Turf Establishment – Performance (610.1605) | SY | 873 | $25.00 | $14.50 | $45.00 | $20.00 | $29.25 | $4.00 |
| 23 | Basic Work Zone Traffic Control (Daily Operations) (619.0101) | LS | 1 | $334,886 | $267,000 | $350,000 | $400,000 | $832,000 | $790,000 |
| 24 | (619.0901) | LF | 127,845 | $0.45 | $0.40 | $0.40 | $0.40 | $0.40 | $0.40 |
| 25 | (619.110511) | EACH | 6 | $7,200.00 | $4,000.00 | $6,500.00 | $6,000.00 | $15,000 | $35,000 |
| 26 | Cleaning Closed Drainage Systems (621.03) | LF | 3,700 | $9.50 | $11.00 | $10.00 | $13.00 | $15.00 | $15.00 |
| 27 | Cleaning Drainage Structures (621.04) | EACH | 148 | $500.00 | $558.00 | $800.00 | $600.00 | $846.00 | $950.00 |
| 28 | Clean, Grade and Shape Existing Roadside Section (621.05) | LF | 13,609 | $2.75 | $4.60 | $6.00 | $6.00 | $5.40 | $5.00 |
| 29 | Survey Operations (625.01) | LS | 1 | $25,000 | $5,000.00 | $40,000 | $10,000 | $70,000 | $200,000 |
| 30 | (625.09010015) | LS | 1 | $6,050.00 | $9,500.00 | $2,500.00 | $1,000.00 | $500.00 | $100.00 |
| 31 | (627.50140008) | 809 | $1.00 | $8.50 | $20.00 | $10.00 | $16.00 | $9.00 | |
| 32 | (633.05040008) | LS | 1 | $149,500 | $135,000 | $447,008 | $132,600 | $180,000 | $190,000 |
| 33 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 10 | $2,675.00 | $5,000.00 | $15,000 | $4,000.00 | $6,148.00 | $8,100.00 |
| 34 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 35 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 20 | $70.20 | $60.00 | $95.00 | $30.00 | $384.00 | $165.00 |
| 36 | Remove and Store Sign Panel, Sign Panel Assembly Size II (30-100 Square Feet) (647.42) | EACH | 23 | $103.50 | $98.00 | $1,050.00 | $100.00 | $220.00 | $110.00 |
| 37 | Pavement Ride Quality Adjustment to Asphalt Level 1 (653.1010) | QUALITY UNIT | 8 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 38 | Welded Frame & Rectangular Grate 3 (655.1003) | EACH | 26 | $589.25 | $1,000.00 | $700.00 | $615.50 | $1,652.00 | $3,900.00 |
| 39 | (685.07200810) | 4 | $50.00 | $103.00 | $95.00 | $104.50 | $104.00 | $100.00 | |
| 40 | (685.16010014) | 84,163 | $1.39 | $1.30 | $1.25 | $1.38 | $1.37 | $1.35 | |
| 41 | (685.17010014) | 89,777 | $1.39 | $1.30 | $1.25 | $1.38 | $1.37 | $1.35 | |
| 42 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 3,968 | $2.79 | $1.90 | $1.75 | $1.93 | $1.90 | $1.90 |
| 43 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 2 | $215.00 | $163.00 | $150.00 | $165.00 | $165.00 | $165.00 |
| 44 | Field Change Payment (FCP) (697.03) | DOL | 350,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 45 | Asphalt Price Adjustment (698.04) | DOL | 19,068 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 46 | Fuel Price Adjustment (698.05) | DOL | 845 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 47 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 48 | Mobilization (699.040001) | LS | 1 | $190,000 | $220,000 | $250,000 | $240,000 | $283,000 | $275,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of January 23, 2025. Compiled by Mirage Metrics.