NYSDOT contract D265463 bid tabulation
CATCH BASIN REPAIRS - Hutchinson River Parkway, Rt 907W. Let by New York State DOT on March 13, 2025, Westchester, Region 08. 7 bids received; low bid $4,084,801 by Morano Brothers Corp.
- Owner
- New York State DOT
- Letting
- 13 MAR 2025
- Pay items
- 32
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Morano Brothers Corp | $4,084,801 | Low |
| 2 | Doyle Contracting Inc | $4,497,608 | +10% |
| 3 | Jrcruz Corp | $4,777,808 | +17% |
| 4 | Perfetto Enterprises Company Inc | $5,468,615 | +34% |
| 5 | Northbrook Contracting Corp | $5,997,688 | +47% |
| 6 | Elq Industries Inc | $6,957,441 | +70% |
| 7 | Scape-Tech Landscape Technology Inc. | $7,945,000 | +95% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Morano Brothers Corp | 2. Doyle Contracting Inc | 3. Jrcruz Corp | 4. Perfetto Enterprises Company Inc | 5. Northbrook Contracting Corp | 6. Elq Industries Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Unclassified Excavation and Disposal (203.02) | CY | 108 | $140.00 | $300.00 | $65.00 | $400.00 | $200.00 | $322.00 |
| 2 | (404.0001) | TON | 47 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 3 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 2 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 4 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 1 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 5 | (404.1261) | TON | 207 | $680.00 | $225.00 | $350.00 | $400.00 | $325.00 | $730.00 |
| 6 | (404.1969) | TON | 731 | $230.00 | $200.00 | $350.00 | $400.00 | $225.00 | $715.00 |
| 7 | Straight Tack Coat (407.0103) | GAL | 520 | $53.00 | $30.00 | $10.00 | $50.00 | $30.00 | $45.00 |
| 8 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 1,685 | $42.00 | $1.00 | $5.00 | $15.00 | $2.00 | $32.00 |
| 9 | (604.070801) | EACH | 85 | $3,200.00 | $7,400.00 | $10,500 | $2,500.00 | $6,500.00 | $6,900.00 |
| 10 | (604.07290010) | 4,620 | $64.00 | $260.00 | $50.00 | $225.00 | $55.00 | $120.00 | |
| 11 | (604.07600008) | 40 | $3,100.00 | $7,400.00 | $7,000.00 | $8,000.00 | $4,500.00 | $9,800.00 | |
| 12 | (609.0404) | LF | 375 | $83.00 | $90.00 | $250.00 | $300.00 | $125.00 | $262.00 |
| 13 | Turf Establishment – Performance (610.1605) | SY | 206 | $3.00 | $10.00 | $5.00 | $75.00 | $25.00 | $59.00 |
| 14 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $550,000 | $750,000 | $400,000 | $300,000 | $1,885,369 | $1,600,000 |
| 15 | (619.110512) | EACH | 8 | $15,000 | $7,000.00 | $10,000 | $25,000 | $25,000 | $25,000 |
| 16 | Nighttime Operations (Entire Project) (619.24) | LS | 1 | $389,000 | $80,000 | $300,000 | $300,000 | $980,000 | $670,000 |
| 17 | Traffic Control Supervisor (619.25) | MONTH | 10 | $29,000 | $18,000 | $25,000 | $24,000 | $21,500 | $10,000 |
| 18 | Cleaning Closed Drainage Systems (621.03) | LF | 20,910 | $10.00 | $8.00 | $10.00 | $15.00 | $11.00 | $14.00 |
| 19 | Cleaning Drainage Structures (621.04) | EACH | 697 | $570.00 | $300.00 | $1,300.00 | $1,200.00 | $600.00 | $900.00 |
| 20 | Survey Operations (625.01) | LS | 1 | $80,000 | $40,000 | $50,000 | $50,000 | $35,000 | $150,000 |
| 21 | (625.09010015) | LS | 1 | $100.00 | $1,000.00 | $50,000 | $50,000 | $10,000 | $1,000.00 |
| 22 | (627.50140008) | 776 | $48.00 | $8.00 | $10.00 | $15.00 | $14.00 | $51.00 | |
| 23 | Engineer’s Field Office – Type 4 (637.14) | MONTH | 16 | $6,000.00 | $7,000.00 | $8,500.00 | $14,000 | $8,000.00 | $8,100.00 |
| 24 | Office Technology and Supplies (637.34) | DOL | 2,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 25 | Cast Frame F3, Mountable Curb Box CM3 & Reticuline Grate G3 (655.0703) | EACH | 30 | $2,400.00 | $1,800.00 | $2,500.00 | $3,000.00 | $2,000.00 | $2,800.00 |
| 26 | Parallel Bar Frame 10 PCB & Parallel Bar Grate 10 PCB (655.0901) | EACH | 115 | $3,000.00 | $1,000.00 | $1,000.00 | $2,500.00 | $1,000.00 | $1,650.00 |
| 27 | Welded Frame & Reticuline Grate 3 (655.1103) | EACH | 15 | $3,000.00 | $950.00 | $650.00 | $2,500.00 | $1,000.00 | $1,400.00 |
| 28 | Field Change Payment (FCP) (697.03) | DOL | 150,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 29 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 30 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 31 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 32 | Mobilization (699.040001) | LS | 1 | $150,000 | $150,000 | $183,573 | $200,000 | $226,000 | $265,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.