Northbrook Contracting Corp submitted 15 bids on New York State DOT contracts in the data, from 01 DEC 2022 to 05 MAR 2026, and was the low bidder on 4 of them (27%). When it was not low, its total sat a median +14% above the low bid.
- Owner
- New York State DOT
- Low bid volume
- $26,909,520
- Latest bid
- 05 MAR 2026
- Data through
- 15 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 1 | 0 | 0% |
| 2023 | 3 | 1 | 33% |
| 2024 | 2 | 0 | 0% |
| 2025 | 4 | 1 | 25% |
| 2026 | 5 | 2 | 40% |
By region
| Region | Bids | Low bids | Win rate |
|---|---|---|---|
| Region 08 | 14 | 4 | 29% |
| Region 09 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Field Change Payment (FCP) | 697.03 | DOL | 15 | 15 (100%) | $1.00 | $1.00 |
| Fuel Price Adjustment | 698.05 | DOL | 15 | 15 (100%) | $1.00 | $1.00 |
| Asphalt Price Adjustment | 698.04 | DOL | 15 | 15 (100%) | $1.00 | $1.00 |
| Office Technology and Supplies | 637.34 | DOL | 14 | 14 (100%) | $1.00 | $1.00 |
| Steel/Iron Price Adjustment | 698.06 | DOL | 14 | 14 (100%) | $1.00 | $1.00 |
| Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips | 608.000013 | QUALITY UNIT | 9 | 9 (100%) | $120.00 | $90.00 |
| Asphalt Pavement Joint Adhesive | 418.7603 | LF | 15 | 6 (40%) | $3.00 | $1.00 |
| Construction Testing supplies – Consumables | 637.36 | DOL | 6 | 6 (100%) | $1.00 | $1.00 |
| Plant Production Quality Adjustment to Asphalt Items | 404.000011 | QUALITY UNIT | 6 | 6 (100%) | $107.50 | $85.00 |
| Partnering Workshop | 637.35 | DOL | 6 | 6 (100%) | $1.00 | $1.00 |
| Silt Fence - Temporary | 209.13 | LF | 7 | 5 (71%) | $6.00 | $7.00 |
| Temporary Positive Barrier – Category 6 (Pinning Required) | 619.1716 | LF | 7 | 5 (71%) | $60.00 | $50.50 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Morano Brothers Corp | 8 | 4 of 8 |
| A Servidone Inc/B Anthony Construction Corp JV | 6 | 3 of 6 |
| Jrcruz Corp | 6 | 4 of 6 |
| D A Collins Construction Co Inc | 4 | 2 of 4 |
| Montesano Bros Inc | 4 | 0 of 4 |
| Transit Construction Corp | 3 | 2 of 3 |
| Elq Industries Inc | 3 | 0 of 3 |
| Gianfia Corp | 3 | 2 of 3 |
| A Colarusso & Son Inc | 3 | 1 of 3 |
| Argenio Brothers Inc | 2 | 2 of 2 |
Latest bids
| Let | Contract | Region | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 05 MAR 2026 | D265730 | Region 08 | Rt 52 Retaining Wall Drainage Guide Rail & Shoulder | 1 of 2 | $8,933,000 | Low, 84% under the second |
| 22 JAN 2026 | D265529 | Region 08 | HIGHWAY PEDESTRIAN SAFETY IMPROVEMENTS | 2 of 4 | $6,938,000 | +3.0% |
| 22 JAN 2026 | D265531 | Region 08 | PEDESTRIAN SAFETY IMPROVEMENTS | 3 of 3 | $5,325,000 | +14% |
| 22 JAN 2026 | D265638 | Region 08 | CULVERT REPLACEMENTS & REHABILITATIONS | 1 of 3 | $7,221,520 | Low, 10% under the second |
| 22 JAN 2026 | D265674 | Region 09 | RETAINING WALL IMPROVEMENT - NY Route 52 | 5 of 5 | $4,840,000 | +40% |
| 27 MAR 2025 | D265440 | Region 08 | Culvert Replacements, Orange and Ulster Counties | 1 of 6 | $5,665,000 | Low, 1.0% under the second |
| 13 MAR 2025 | D265463 | Region 08 | CATCH BASIN REPAIRS - Hutchinson River Parkway, Rt 907W | 5 of 7 | $5,997,688 | +47% |
| 27 FEB 2025 | D265424 | Region 08 | Replacement and Relining of Culverts - Various locations | 2 of 5 | $13,775,000 | +3.0% |
| 20 FEB 2025 | D265386 | Region 08 | Culvert Replacements and Rehabilitations - Various Locations | 2 of 5 | $9,923,000 | +6.0% |
| 28 MAR 2024 | D265217 | Region 08 | Highway Reconstruction US Rt 6 at Annsville Circle | 3 of 6 | $26,235,000 | +9.0% |
| 08 FEB 2024 | D265201 | Region 08 | RT 376 (Raymond Ave) at Hooker Ave Intersection Improvements | 9 of 11 | $14,443,080 | +27% |
| 23 MAR 2023 | D264989 | Region 08 | RT6 & RT125 PAVE/PED IMPROVEMENTS TOWN CORTLANDT/MAMARONECK | 1 of 5 | $5,090,000 | Low, 3.0% under the second |
| 09 MAR 2023 | D264982 | Region 08 | RT 9 CATCH BASIN REPAIRS, RT 9, RT 113 TO WEST DORSEY LN | 2 of 4 | $2,110,000 | +1.0% |
| 19 JAN 2023 | D264967 | Region 08 | TACONIC STATE PARKWAY | 7 of 8 | $4,040,000 | +115% |
| 01 DEC 2022 | D264887 | Region 08 | Culvert Replacement Project, Orange and Ulster Counties | 7 of 10 | $7,795,000 | +40% |
How this record was read
NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
- Every bid counted here matched its published total to within one dollar; NYSDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.