NYSDOT contract D265440 bid tabulation

Culvert Replacements, Orange and Ulster Counties. Let by New York State DOT on March 27, 2025, Orange, Ulster, Region 08. 6 bids received; low bid $5,665,000 by Northbrook Contracting Corp.

Owner
New York State DOT
Letting
27 MAR 2025
Pay items
104
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Northbrook Contracting Corp$5,665,000Low
2D A Collins Construction Co Inc$5,731,665+1.0%
3A Colarusso & Son Inc$6,299,000+11%
4Jrcruz Corp$6,955,814+23%
5A Servidone Inc/B Anthony Construction Corp JV$7,779,000+37%
6C.A.C. Industries Inc$9,324,000+65%
NYSDOT contract D265440: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Northbrook Contracting Corp2. D A Collins Construction Co Inc3. A Colarusso & Son Inc4. Jrcruz Corp5. A Servidone Inc/B Anthony Construction Corp JV6. C.A.C. Industries Inc
1Clearing and Grubbing (201.06)LS1$35,517$39,050$150,000$50,000$233,623$27,000
2Removal of Substructures (202.19)CY370$320.00$83.00$128.00$150.00$210.00$630.00
3Unclassified Excavation and Disposal (203.02)CY584$60.00$70.00$36.00$100.00$250.00$360.00
4Embankment In Place (203.03)CY868$53.00$38.50$83.00$100.00$75.00$72.00
5Select Structural Fill (203.21)CY880$92.00$52.00$128.00$100.00$350.00$108.00
6 (203.24010017)50$50.00$150.00$224.00$500.00$220.00$252.00
7 (205.0201)LS1$3,000.00$8,600.00$13,500$7,000.00$20,000$20,700
8Field Organic Vapor Monitoring of Contaminated Soil (205.03)HR36$200.00$185.00$305.00$150.00$230.00$270.00
9Petroleum Contamination Parameter Analysis (205.0401)EACH5$900.00$370.00$444.00$700.00$3,500.00$1,980.00
10 (205.050201)TON105$75.00$135.00$230.00$85.00$280.00$72.00
11 (205.97200011)LS1$50,000$1,050.00$1,000.00$5,000.00$70,000$90,000
12Structure Excavation (206.01)CY2,767$63.00$69.00$38.00$100.00$175.00$72.00
13Trench and Culvert Excavation (206.0201)CY300$75.00$32.00$74.00$100.00$140.00$378.00
14Geotextile Bedding (207.20)SY614$7.00$7.95$4.00$5.00$4.00$72.00
15Prefabricated Composite Structural Drain (207.26)SY20$30.00$11.50$88.00$100.00$100.00$54.00
16Silt Fence - Temporary (209.13)LF1,530$5.00$5.90$9.00$5.00$15.00$27.00
17Stabilized Construction Access (209.22)SY935$22.00$17.00$30.00$25.00$25.00$27.00
18 (304.11000008)680$115.00$89.00$131.00$125.00$120.00$162.00
19 (404.0001)TON70$120.00$120.00$120.00$120.00$120.00$120.00
20 (404.0189)TON40$300.00$250.00$308.00$300.00$215.00$630.00
21 (404.1283)TON285$250.00$240.00$304.00$300.00$215.00$270.00
22 (404.1989)TON270$240.00$245.00$161.00$300.00$205.00$351.00
23 (404.3789)TON820$235.00$190.00$160.00$300.00$205.00$297.00
24Diluted Tack Coat (407.0102)GAL290$6.00$47.50$29.00$10.00$5.00$45.00
25Asphalt Pavement Joint Adhesive (418.7603)LF2,070$1.00$8.65$3.00$3.00$1.00$27.00
26Miscellaneous Cold Milling of Bituminous Concrete (490.30)SY580$45.00$32.00$34.00$100.00$45.00$72.00
27Shields and Shoring (552.17)SF900$83.00$1.00$137.00$30.00$1.00$72.00
28 (552.2001)LF292$185.00$1.00$181.00$25.00$235.00$180.00
29 (552.2002)LF1,240$185.00$1.00$177.00$25.00$0.00$90.00
30 (552.2003)LF49$250.00$1.00$310.00$25.00$450.00$90.00
31 (552.2101)LF12$600.00$1.00$555.00$2,100.00$1,000.00$540.00
32 (552.2103)LF20$600.00$1.00$555.00$2,100.00$1,000.00$540.00
33 (552.2201)LF275$100.00$1.00$183.00$125.00$150.00$63.00
34 (552.2202)LF1,240$100.00$1.00$152.00$125.00$0.01$63.00
35 (552.2203)LF74$215.00$1.00$226.00$125.00$150.00$63.00
36 (552.230201)SF625$6.00$1.00$49.00$5.00$18.00$4.50
37 (552.230202)SF3,036$8.00$1.00$45.00$5.00$0.01$4.50
38 (552.230203)SF245$10.00$1.00$56.00$5.00$18.00$4.50
39 (553.030001)EACH1$160,000$42,000$170,000$75,000$200,000$360,000
40 (553.030002)EACH1$345,000$72,000$195,000$100,000$200,000$360,000
41 (553.030003)EACH1$100,000$87,000$120,000$100,000$200,000$450,000
42 (553.030004)EACH1$140,000$55,000$120,000$75,000$200,000$270,000
43 (560.13060108)60$175.00$215.00$314.00$120.00$250.00$450.00
44 (560.13200008)4$3,000.00$2,150.00$3,600.00$2,850.00$2,900.00$10,800
45Steel Bridge Railing (Four-Rail) (568.51)LF120$425.00$490.00$372.00$550.00$340.00$720.00
46Transition Bridge Railing (568.70)LF347$185.00$275.00$162.00$300.00$150.00$405.00
47 (595.50000018)7,202$5.00$4.00$7.00$4.00$21.00$36.00
48 (603.63160615)55$4,500.00$4,400.00$5,110.00$7,500.00$8,500.00$7,200.00
49 (603.64080515)61$2,500.00$4,600.00$5,580.00$6,750.00$4,000.00$5,400.00
50 (603.64100715)173$3,300.00$4,800.00$3,490.00$7,000.00$6,000.00$6,300.00
51 (603.67000001)35$3,500.00$4,600.00$5,760.00$5,000.00$2,500.00$1,980.00
52Box Beam Guide Railing (606.10)LF205$70.00$73.00$60.00$80.00$60.00$90.00
53Box Beam Guide Railing With Extra Long Posts (606.1001)LF30$105.00$83.00$93.00$90.00$90.00$153.00
54Box Beam End Piece (606.120101)EACH4$1,100.00$970.00$988.00$1,000.00$900.00$1,080.00
55Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH5$3,100.00$3,450.00$2,763.00$3,800.00$2,500.00$2,700.00
56Box Beam End Assembly Type III (606.1203)EACH2$11,000$9,300.00$9,883.00$10,000$9,000.00$8,100.00
57HPBO (Mod.) Corrugated Beam Guide Railing (606.2701)LF100$38.00$46.00$32.00$50.00$35.00$63.00
58HPBO (Mod.) Corrugated Beam Guide Railing with Extra Long Posts (606.2702)LF10$56.00$85.00$240.00$95.00$300.00$63.00
59HPBO (Mod.) Corrugated Beam Guide Railing with Extra Long Posts (Shop Curved) (606.270201)LF10$62.00$93.00$111.00$100.00$135.00$63.00
60Anchorage Units for HPBO (Mod.) Corrugated Beam Guide Railing (606.2703)EACH2$5,000.00$3,750.00$2,700.00$4,000.00$4,000.00$10,800
61HPBO (Mod.) Corrugated Beam Median Barrier (Shop Curved) (606.280101)LF30$75.00$78.00$67.00$85.00$83.00$144.00
62Removing and Disposing Corrugated Beam Guide Railing (606.71)LF140$18.00$26.00$12.00$20.00$25.00$18.00
63Removing and Disposing Box Beam Guide Railing (606.73)LF576$25.00$16.00$12.00$20.00$20.00$27.00
64Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013)QUALITY UNIT4$120.00$120.00$120.00$120.00$120.00$120.00
65Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON50$245.00$480.00$358.00$500.00$215.00$1,404.00
66Turf Establishment – Performance (610.1605)SY1,390$18.00$16.00$40.00$12.00$18.00$45.00
67Wildflower Seeding (610.17)SY71$18.00$16.00$29.00$10.00$75.00$54.00
68 (613.04000001)145$140.00$195.00$143.00$200.00$300.00$180.00
69 (615.01010108)372$220.00$53.00$188.00$150.00$130.00$171.00
70 (617.11000024)LS1$5,000.00$1,450.00$5,500.00$5,000.00$30,000$20,700
71Basic Work Zone Traffic Control (619.01)LS1$220,000$1,178,000$350,000$250,000$600,000$404,698
72Type III Construction Barricades (619.04)EACH46$175.00$93.00$234.00$200.00$700.00$270.00
73Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803)LF4,388$3.00$4.50$5.50$5.00$5.00$4.50
74 (619.100101)LF5,550$1.00$0.57$0.60$1.00$1.00$0.90
75 (619.110513)EACH12$10,000$4,000.00$7,200.00$12,500$10,000$18,000
76 (619.1301)EACH4$16,000$8,700.00$30,000$50,000$8,000.00$11,070
77Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711)LF284$50.00$82.00$62.00$100.00$65.00$126.00
78Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716)LF730$30.00$51.00$65.00$100.00$60.00$90.00
79Temporary Impact Attenuator - Redirective (Test Level 2) (619.1802)EACH4$8,500.00$3,350.00$11,000$7,500.00$4,000.00$16,200
80 (619.99230103)32$6,800.00$10,920$3,650.00$10,920$5,000.00$11,700
81Stone Filling (Light) (620.03)CY85$125.00$93.00$200.00$175.00$300.00$207.00
82Stone Filling (Medium) (620.04)CY60$160.00$120.00$230.00$175.00$300.00$261.00
83Stone Filling (Heavy) (620.05)CY85$190.00$125.00$239.00$225.00$300.00$297.00
84Bedding Material, Type 1 (620.0801)CY72$175.00$87.00$217.00$150.00$300.00$198.00
85Cleaning Culverts with Span of More Than 50 in. (621.02)LF35$80.00$160.00$167.00$250.00$200.00$900.00
86Clean, Grade and Shape Existing Roadside Section (621.05)LF820$8.00$8.50$10.00$35.00$15.00$36.00
87 (621.51010010)1,140$11.00$5.70$11.00$5.00$25.00$18.00
88 (623.12000008)196$210.00$125.00$250.00$150.00$200.00$180.00
89Survey Operations (625.01)LS1$127,590$121,000$150,000$115,000$200,000$185,400
90 (627.50140008)560$10.00$5.30$12.00$5.00$25.00$9.00
91Cleaning Existing Pavement and/or Shoulder (633.11)SY2,360$1.00$9.55$6.00$5.00$3.00$13.50
92 (634.99010017)LS1$20,000$2,150.00$11,000$25,000$25,000$18,000
93Cleaning and Preparation of Pavement Surfaces-Lines (635.0103)LF5,310$1.00$1.60$2.00$2.00$3.00$1.80
94Engineer’s Field Office – Type 3 (637.13)MONTH22$3,800.00$3,400.00$4,000.00$6,500.00$9,000.00$17,100
95Office Technology and Supplies (637.34)DOL2,000$1.00$1.00$1.00$1.00$1.00$1.00
96Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22)EACH51$35.00$145.00$28.00$150.00$25.00$90.00
97Steel Post, 1.1 lb/ft (646.31)EACH51$160.00$145.00$138.00$150.00$150.00$81.00
98White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102)LF3,950$3.00$2.10$1.80$2.50$5.00$2.07
99Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202)LF7,620$3.00$2.10$1.75$2.50$5.00$2.07
100Field Change Payment (FCP) (697.03)DOL410,000$1.00$1.00$1.00$1.00$1.00$1.00
101Asphalt Price Adjustment (698.04)DOL400$1.00$1.00$1.00$1.00$1.00$1.00
102Fuel Price Adjustment (698.05)DOL400$1.00$1.00$1.00$1.00$1.00$1.00
103Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00$1.00$1.00
104Mobilization (699.040001)LS1$215,000$215,000$240,000$267,531$290,000$342,000
NYSDOT contract D265440: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of March 27, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way