NYSDOT contract D265440 bid tabulation
Culvert Replacements, Orange and Ulster Counties. Let by New York State DOT on March 27, 2025, Orange, Ulster, Region 08. 6 bids received; low bid $5,665,000 by Northbrook Contracting Corp.
- Owner
- New York State DOT
- Letting
- 27 MAR 2025
- Pay items
- 104
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Northbrook Contracting Corp | $5,665,000 | Low |
| 2 | D A Collins Construction Co Inc | $5,731,665 | +1.0% |
| 3 | A Colarusso & Son Inc | $6,299,000 | +11% |
| 4 | Jrcruz Corp | $6,955,814 | +23% |
| 5 | A Servidone Inc/B Anthony Construction Corp JV | $7,779,000 | +37% |
| 6 | C.A.C. Industries Inc | $9,324,000 | +65% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Northbrook Contracting Corp | 2. D A Collins Construction Co Inc | 3. A Colarusso & Son Inc | 4. Jrcruz Corp | 5. A Servidone Inc/B Anthony Construction Corp JV | 6. C.A.C. Industries Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $35,517 | $39,050 | $150,000 | $50,000 | $233,623 | $27,000 |
| 2 | Removal of Substructures (202.19) | CY | 370 | $320.00 | $83.00 | $128.00 | $150.00 | $210.00 | $630.00 |
| 3 | Unclassified Excavation and Disposal (203.02) | CY | 584 | $60.00 | $70.00 | $36.00 | $100.00 | $250.00 | $360.00 |
| 4 | Embankment In Place (203.03) | CY | 868 | $53.00 | $38.50 | $83.00 | $100.00 | $75.00 | $72.00 |
| 5 | Select Structural Fill (203.21) | CY | 880 | $92.00 | $52.00 | $128.00 | $100.00 | $350.00 | $108.00 |
| 6 | (203.24010017) | 50 | $50.00 | $150.00 | $224.00 | $500.00 | $220.00 | $252.00 | |
| 7 | (205.0201) | LS | 1 | $3,000.00 | $8,600.00 | $13,500 | $7,000.00 | $20,000 | $20,700 |
| 8 | Field Organic Vapor Monitoring of Contaminated Soil (205.03) | HR | 36 | $200.00 | $185.00 | $305.00 | $150.00 | $230.00 | $270.00 |
| 9 | Petroleum Contamination Parameter Analysis (205.0401) | EACH | 5 | $900.00 | $370.00 | $444.00 | $700.00 | $3,500.00 | $1,980.00 |
| 10 | (205.050201) | TON | 105 | $75.00 | $135.00 | $230.00 | $85.00 | $280.00 | $72.00 |
| 11 | (205.97200011) | LS | 1 | $50,000 | $1,050.00 | $1,000.00 | $5,000.00 | $70,000 | $90,000 |
| 12 | Structure Excavation (206.01) | CY | 2,767 | $63.00 | $69.00 | $38.00 | $100.00 | $175.00 | $72.00 |
| 13 | Trench and Culvert Excavation (206.0201) | CY | 300 | $75.00 | $32.00 | $74.00 | $100.00 | $140.00 | $378.00 |
| 14 | Geotextile Bedding (207.20) | SY | 614 | $7.00 | $7.95 | $4.00 | $5.00 | $4.00 | $72.00 |
| 15 | Prefabricated Composite Structural Drain (207.26) | SY | 20 | $30.00 | $11.50 | $88.00 | $100.00 | $100.00 | $54.00 |
| 16 | Silt Fence - Temporary (209.13) | LF | 1,530 | $5.00 | $5.90 | $9.00 | $5.00 | $15.00 | $27.00 |
| 17 | Stabilized Construction Access (209.22) | SY | 935 | $22.00 | $17.00 | $30.00 | $25.00 | $25.00 | $27.00 |
| 18 | (304.11000008) | 680 | $115.00 | $89.00 | $131.00 | $125.00 | $120.00 | $162.00 | |
| 19 | (404.0001) | TON | 70 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 20 | (404.0189) | TON | 40 | $300.00 | $250.00 | $308.00 | $300.00 | $215.00 | $630.00 |
| 21 | (404.1283) | TON | 285 | $250.00 | $240.00 | $304.00 | $300.00 | $215.00 | $270.00 |
| 22 | (404.1989) | TON | 270 | $240.00 | $245.00 | $161.00 | $300.00 | $205.00 | $351.00 |
| 23 | (404.3789) | TON | 820 | $235.00 | $190.00 | $160.00 | $300.00 | $205.00 | $297.00 |
| 24 | Diluted Tack Coat (407.0102) | GAL | 290 | $6.00 | $47.50 | $29.00 | $10.00 | $5.00 | $45.00 |
| 25 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 2,070 | $1.00 | $8.65 | $3.00 | $3.00 | $1.00 | $27.00 |
| 26 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 580 | $45.00 | $32.00 | $34.00 | $100.00 | $45.00 | $72.00 |
| 27 | Shields and Shoring (552.17) | SF | 900 | $83.00 | $1.00 | $137.00 | $30.00 | $1.00 | $72.00 |
| 28 | (552.2001) | LF | 292 | $185.00 | $1.00 | $181.00 | $25.00 | $235.00 | $180.00 |
| 29 | (552.2002) | LF | 1,240 | $185.00 | $1.00 | $177.00 | $25.00 | $0.00 | $90.00 |
| 30 | (552.2003) | LF | 49 | $250.00 | $1.00 | $310.00 | $25.00 | $450.00 | $90.00 |
| 31 | (552.2101) | LF | 12 | $600.00 | $1.00 | $555.00 | $2,100.00 | $1,000.00 | $540.00 |
| 32 | (552.2103) | LF | 20 | $600.00 | $1.00 | $555.00 | $2,100.00 | $1,000.00 | $540.00 |
| 33 | (552.2201) | LF | 275 | $100.00 | $1.00 | $183.00 | $125.00 | $150.00 | $63.00 |
| 34 | (552.2202) | LF | 1,240 | $100.00 | $1.00 | $152.00 | $125.00 | $0.01 | $63.00 |
| 35 | (552.2203) | LF | 74 | $215.00 | $1.00 | $226.00 | $125.00 | $150.00 | $63.00 |
| 36 | (552.230201) | SF | 625 | $6.00 | $1.00 | $49.00 | $5.00 | $18.00 | $4.50 |
| 37 | (552.230202) | SF | 3,036 | $8.00 | $1.00 | $45.00 | $5.00 | $0.01 | $4.50 |
| 38 | (552.230203) | SF | 245 | $10.00 | $1.00 | $56.00 | $5.00 | $18.00 | $4.50 |
| 39 | (553.030001) | EACH | 1 | $160,000 | $42,000 | $170,000 | $75,000 | $200,000 | $360,000 |
| 40 | (553.030002) | EACH | 1 | $345,000 | $72,000 | $195,000 | $100,000 | $200,000 | $360,000 |
| 41 | (553.030003) | EACH | 1 | $100,000 | $87,000 | $120,000 | $100,000 | $200,000 | $450,000 |
| 42 | (553.030004) | EACH | 1 | $140,000 | $55,000 | $120,000 | $75,000 | $200,000 | $270,000 |
| 43 | (560.13060108) | 60 | $175.00 | $215.00 | $314.00 | $120.00 | $250.00 | $450.00 | |
| 44 | (560.13200008) | 4 | $3,000.00 | $2,150.00 | $3,600.00 | $2,850.00 | $2,900.00 | $10,800 | |
| 45 | Steel Bridge Railing (Four-Rail) (568.51) | LF | 120 | $425.00 | $490.00 | $372.00 | $550.00 | $340.00 | $720.00 |
| 46 | Transition Bridge Railing (568.70) | LF | 347 | $185.00 | $275.00 | $162.00 | $300.00 | $150.00 | $405.00 |
| 47 | (595.50000018) | 7,202 | $5.00 | $4.00 | $7.00 | $4.00 | $21.00 | $36.00 | |
| 48 | (603.63160615) | 55 | $4,500.00 | $4,400.00 | $5,110.00 | $7,500.00 | $8,500.00 | $7,200.00 | |
| 49 | (603.64080515) | 61 | $2,500.00 | $4,600.00 | $5,580.00 | $6,750.00 | $4,000.00 | $5,400.00 | |
| 50 | (603.64100715) | 173 | $3,300.00 | $4,800.00 | $3,490.00 | $7,000.00 | $6,000.00 | $6,300.00 | |
| 51 | (603.67000001) | 35 | $3,500.00 | $4,600.00 | $5,760.00 | $5,000.00 | $2,500.00 | $1,980.00 | |
| 52 | Box Beam Guide Railing (606.10) | LF | 205 | $70.00 | $73.00 | $60.00 | $80.00 | $60.00 | $90.00 |
| 53 | Box Beam Guide Railing With Extra Long Posts (606.1001) | LF | 30 | $105.00 | $83.00 | $93.00 | $90.00 | $90.00 | $153.00 |
| 54 | Box Beam End Piece (606.120101) | EACH | 4 | $1,100.00 | $970.00 | $988.00 | $1,000.00 | $900.00 | $1,080.00 |
| 55 | Box Beam Guide Railing End Assembly Type IIA (606.120201) | EACH | 5 | $3,100.00 | $3,450.00 | $2,763.00 | $3,800.00 | $2,500.00 | $2,700.00 |
| 56 | Box Beam End Assembly Type III (606.1203) | EACH | 2 | $11,000 | $9,300.00 | $9,883.00 | $10,000 | $9,000.00 | $8,100.00 |
| 57 | HPBO (Mod.) Corrugated Beam Guide Railing (606.2701) | LF | 100 | $38.00 | $46.00 | $32.00 | $50.00 | $35.00 | $63.00 |
| 58 | HPBO (Mod.) Corrugated Beam Guide Railing with Extra Long Posts (606.2702) | LF | 10 | $56.00 | $85.00 | $240.00 | $95.00 | $300.00 | $63.00 |
| 59 | HPBO (Mod.) Corrugated Beam Guide Railing with Extra Long Posts (Shop Curved) (606.270201) | LF | 10 | $62.00 | $93.00 | $111.00 | $100.00 | $135.00 | $63.00 |
| 60 | Anchorage Units for HPBO (Mod.) Corrugated Beam Guide Railing (606.2703) | EACH | 2 | $5,000.00 | $3,750.00 | $2,700.00 | $4,000.00 | $4,000.00 | $10,800 |
| 61 | HPBO (Mod.) Corrugated Beam Median Barrier (Shop Curved) (606.280101) | LF | 30 | $75.00 | $78.00 | $67.00 | $85.00 | $83.00 | $144.00 |
| 62 | Removing and Disposing Corrugated Beam Guide Railing (606.71) | LF | 140 | $18.00 | $26.00 | $12.00 | $20.00 | $25.00 | $18.00 |
| 63 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 576 | $25.00 | $16.00 | $12.00 | $20.00 | $20.00 | $27.00 |
| 64 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 4 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 65 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 50 | $245.00 | $480.00 | $358.00 | $500.00 | $215.00 | $1,404.00 |
| 66 | Turf Establishment – Performance (610.1605) | SY | 1,390 | $18.00 | $16.00 | $40.00 | $12.00 | $18.00 | $45.00 |
| 67 | Wildflower Seeding (610.17) | SY | 71 | $18.00 | $16.00 | $29.00 | $10.00 | $75.00 | $54.00 |
| 68 | (613.04000001) | 145 | $140.00 | $195.00 | $143.00 | $200.00 | $300.00 | $180.00 | |
| 69 | (615.01010108) | 372 | $220.00 | $53.00 | $188.00 | $150.00 | $130.00 | $171.00 | |
| 70 | (617.11000024) | LS | 1 | $5,000.00 | $1,450.00 | $5,500.00 | $5,000.00 | $30,000 | $20,700 |
| 71 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $220,000 | $1,178,000 | $350,000 | $250,000 | $600,000 | $404,698 |
| 72 | Type III Construction Barricades (619.04) | EACH | 46 | $175.00 | $93.00 | $234.00 | $200.00 | $700.00 | $270.00 |
| 73 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 4,388 | $3.00 | $4.50 | $5.50 | $5.00 | $5.00 | $4.50 |
| 74 | (619.100101) | LF | 5,550 | $1.00 | $0.57 | $0.60 | $1.00 | $1.00 | $0.90 |
| 75 | (619.110513) | EACH | 12 | $10,000 | $4,000.00 | $7,200.00 | $12,500 | $10,000 | $18,000 |
| 76 | (619.1301) | EACH | 4 | $16,000 | $8,700.00 | $30,000 | $50,000 | $8,000.00 | $11,070 |
| 77 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 284 | $50.00 | $82.00 | $62.00 | $100.00 | $65.00 | $126.00 |
| 78 | Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716) | LF | 730 | $30.00 | $51.00 | $65.00 | $100.00 | $60.00 | $90.00 |
| 79 | Temporary Impact Attenuator - Redirective (Test Level 2) (619.1802) | EACH | 4 | $8,500.00 | $3,350.00 | $11,000 | $7,500.00 | $4,000.00 | $16,200 |
| 80 | (619.99230103) | 32 | $6,800.00 | $10,920 | $3,650.00 | $10,920 | $5,000.00 | $11,700 | |
| 81 | Stone Filling (Light) (620.03) | CY | 85 | $125.00 | $93.00 | $200.00 | $175.00 | $300.00 | $207.00 |
| 82 | Stone Filling (Medium) (620.04) | CY | 60 | $160.00 | $120.00 | $230.00 | $175.00 | $300.00 | $261.00 |
| 83 | Stone Filling (Heavy) (620.05) | CY | 85 | $190.00 | $125.00 | $239.00 | $225.00 | $300.00 | $297.00 |
| 84 | Bedding Material, Type 1 (620.0801) | CY | 72 | $175.00 | $87.00 | $217.00 | $150.00 | $300.00 | $198.00 |
| 85 | Cleaning Culverts with Span of More Than 50 in. (621.02) | LF | 35 | $80.00 | $160.00 | $167.00 | $250.00 | $200.00 | $900.00 |
| 86 | Clean, Grade and Shape Existing Roadside Section (621.05) | LF | 820 | $8.00 | $8.50 | $10.00 | $35.00 | $15.00 | $36.00 |
| 87 | (621.51010010) | 1,140 | $11.00 | $5.70 | $11.00 | $5.00 | $25.00 | $18.00 | |
| 88 | (623.12000008) | 196 | $210.00 | $125.00 | $250.00 | $150.00 | $200.00 | $180.00 | |
| 89 | Survey Operations (625.01) | LS | 1 | $127,590 | $121,000 | $150,000 | $115,000 | $200,000 | $185,400 |
| 90 | (627.50140008) | 560 | $10.00 | $5.30 | $12.00 | $5.00 | $25.00 | $9.00 | |
| 91 | Cleaning Existing Pavement and/or Shoulder (633.11) | SY | 2,360 | $1.00 | $9.55 | $6.00 | $5.00 | $3.00 | $13.50 |
| 92 | (634.99010017) | LS | 1 | $20,000 | $2,150.00 | $11,000 | $25,000 | $25,000 | $18,000 |
| 93 | Cleaning and Preparation of Pavement Surfaces-Lines (635.0103) | LF | 5,310 | $1.00 | $1.60 | $2.00 | $2.00 | $3.00 | $1.80 |
| 94 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 22 | $3,800.00 | $3,400.00 | $4,000.00 | $6,500.00 | $9,000.00 | $17,100 |
| 95 | Office Technology and Supplies (637.34) | DOL | 2,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 96 | Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22) | EACH | 51 | $35.00 | $145.00 | $28.00 | $150.00 | $25.00 | $90.00 |
| 97 | Steel Post, 1.1 lb/ft (646.31) | EACH | 51 | $160.00 | $145.00 | $138.00 | $150.00 | $150.00 | $81.00 |
| 98 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 3,950 | $3.00 | $2.10 | $1.80 | $2.50 | $5.00 | $2.07 |
| 99 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 7,620 | $3.00 | $2.10 | $1.75 | $2.50 | $5.00 | $2.07 |
| 100 | Field Change Payment (FCP) (697.03) | DOL | 410,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 101 | Asphalt Price Adjustment (698.04) | DOL | 400 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 102 | Fuel Price Adjustment (698.05) | DOL | 400 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 103 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 104 | Mobilization (699.040001) | LS | 1 | $215,000 | $215,000 | $240,000 | $267,531 | $290,000 | $342,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 27, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.