NYSDOT contract D265730 bid tabulation
Rt 52 Retaining Wall Drainage Guide Rail & Shoulder. Let by New York State DOT on March 5, 2026, Ulster, Region 08. 2 bids received; low bid $8,933,000 by Northbrook Contracting Corp.
- Owner
- New York State DOT
- Letting
- 05 MAR 2026
- Pay items
- 101
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Northbrook Contracting Corp | $8,933,000 | Low |
| 2 | A Servidone Inc/B Anthony Construction Corp JV | $16,419,181 | +84% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Northbrook Contracting Corp | 2. A Servidone Inc/B Anthony Construction Corp JV |
|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $99,000 | $450,000 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 7,245 | $65.00 | $150.00 |
| 3 | Embankment In Place (203.03) | CY | 1,359 | $50.00 | $110.00 |
| 4 | Select Granular Fill (203.07) | CY | 1,100 | $90.00 | $230.00 |
| 5 | (203.51990006) | 75 | $110.00 | $58.00 | |
| 6 | Trench and Culvert Excavation (206.0201) | CY | 103 | $500.00 | $130.00 |
| 7 | Geotextile Bedding (207.20) | SY | 65 | $25.00 | $130.00 |
| 8 | (207.96000017) | 1,783 | $10.00 | $10.00 | |
| 9 | Mulch – Temporary (209.100101) | SY | 600 | $3.00 | $12.00 |
| 10 | Seed and Mulch – Temporary (209.1003) | SY | 300 | $4.00 | $18.00 |
| 11 | Rolled Erosion Control Product, Class II Type A, Intermediate (209.1901) | SY | 1,618 | $7.00 | $7.00 |
| 12 | Stabilized Construction Access (209.22) | SY | 132 | $30.00 | $83.00 |
| 13 | (209.23010009) | 16,315 | $7.00 | $10.00 | |
| 14 | Subbase Course, Type 2 (304.12) | CY | 2,391 | $130.00 | $500.00 |
| 15 | (404.0189) | TON | 3 | $800.00 | $1,100.00 |
| 16 | (404.1272) | TON | 5,377 | $183.00 | $200.00 |
| 17 | (404.1979) | TON | 1,056 | $345.00 | $370.00 |
| 18 | (404.3779) | TON | 650 | $300.00 | $330.00 |
| 19 | Straight Tack Coat (407.0103) | GAL | 2,224 | $35.00 | $46.00 |
| 20 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 12,942 | $4.00 | $9.00 |
| 21 | Production Cold Milling of Bituminous Concrete (490.10) | SY | 34,972 | $8.00 | $9.00 |
| 22 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 123 | $20.00 | $71.00 |
| 23 | (554.20000017) | 677 | $47.00 | $260.00 | |
| 24 | (554.3002) | SF | 7,259 | $65.00 | $300.00 |
| 25 | Geosynthetically Reinforced Soil System Slope (554.31) | SF | 1,988 | $46.00 | $150.00 |
| 26 | Tuck Pointing (560.08) | LF | 22 | $100.00 | $100.00 |
| 27 | (560.13060108) | 22 | $275.00 | $2,900.00 | |
| 28 | Removal of Structural Concrete (580.01) | CY | 52 | $270.00 | $1,500.00 |
| 29 | Removal of Structural Concrete- Replacement with Vertical and Overhead Patching Material (582.0061) | SF | 370 | $50.00 | $220.00 |
| 30 | Structural Paving of Inverts with Portland Cement Concrete (602.2002) | SF | 340 | $30.00 | $700.00 |
| 31 | (602.3624) | LF | 92 | $100.00 | $880.00 |
| 32 | (602.3636) | LF | 76 | $550.00 | $1,200.00 |
| 33 | (602.3648) | LF | 285 | $750.00 | $1,100.00 |
| 34 | Concrete Collars (603.77) | EACH | 2 | $2,500.00 | $4,200.00 |
| 35 | (603.9550) | LF | 20 | $350.00 | $910.00 |
| 36 | (604.07290010) | 150 | $150.00 | $690.00 | |
| 37 | (604.301132) | LF | 10 | $500.00 | $940.00 |
| 38 | Underdrain Filter, Type I (605.0901) | CY | 63 | $70.00 | $310.00 |
| 39 | (605.1701) | LF | 345 | $9.00 | $80.00 |
| 40 | Box Beam Guide Railing (606.10) | LF | 231 | $77.00 | $84.00 |
| 41 | Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002) | LF | 30 | $93.00 | $100.00 |
| 42 | Box Beam Guide Railing End Assembly Type IIA (606.120201) | EACH | 1 | $4,000.00 | $3,900.00 |
| 43 | HPBO (Mod.) Corrugated Beam Guide Railing End Terminal (Energy-Absorbing) (606.27) | EACH | 2 | $8,000.00 | $8,200.00 |
| 44 | HPBO (Mod.) Corrugated Beam Guide Railing with Extra Long Posts (606.2702) | LF | 5,910 | $63.00 | $67.00 |
| 45 | HPBO (Mod.) Corrugated Beam Guide Railing with Extra Long Posts (Shop Curved) (606.270201) | LF | 41 | $85.00 | $90.00 |
| 46 | Anchorage Units for HPBO (Mod.) Corrugated Beam Guide Railing (606.2703) | EACH | 9 | $6,000.00 | $6,100.00 |
| 47 | Anchorage Units for HPBO (Mod.) Corrugated Beam Guide Railing Buried in Back Slope (606.2704) | EACH | 1 | $7,000.00 | $6,500.00 |
| 48 | Removing and Disposing HPBO (Mod.) Corrugated Beam Guide Railing (606.7101) | LF | 5,500 | $5.00 | $5.50 |
| 49 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 2,101 | $9.00 | $7.00 |
| 50 | Removing and Disposing Weak- and Heavy-Post Corrugated Beam Energy-Absorbing Terminals (606.7911) | EACH | 1 | $1,000.00 | $1,000.00 |
| 51 | Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920) | EACH | 5 | $900.00 | $270.00 |
| 52 | Removing and Disposing Anchorage Units for HPBO(Mod) Corrugated Beam Median Barrier (606.7946) | EACH | 6 | $800.00 | $1,000.00 |
| 53 | Transition: HPBO (Mod.) Corrugated Guide Railing to Beam Box Beam Guide Railing (606.8901) | EACH | 2 | $7,000.00 | $11,000 |
| 54 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 1 | $140.00 | $140.00 |
| 55 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 317 | $400.00 | $280.00 |
| 56 | Turf Establishment – Performance (610.1605) | SY | 1,178 | $20.00 | $48.00 |
| 57 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $812,489 | $1,105,000 |
| 58 | (619.080101) | LF | 34,859 | $1.80 | $2.00 |
| 59 | (619.080102) | LF | 18,479 | $1.80 | $2.00 |
| 60 | (619.100103) | LF | 432 | $3.50 | $4.00 |
| 61 | (619.100105) | LF | 59,271 | $1.00 | $1.50 |
| 62 | (619.110522) | EACH | 10 | $25,000 | $29,000 |
| 63 | (619.130201) | EACH | 1 | $18,000 | $84,000 |
| 64 | (619.130202) | EACH | 1 | $18,000 | $84,000 |
| 65 | (619.130203) | EACH | 1 | $18,000 | $84,000 |
| 66 | (619.130204) | EACH | 1 | $18,000 | $84,000 |
| 67 | (619.130205) | EACH | 1 | $18,000 | $8,500.00 |
| 68 | (619.130206) | EACH | 1 | $18,000 | $8,500.00 |
| 69 | (619.130207) | EACH | 1 | $18,000 | $8,500.00 |
| 70 | (619.130208) | EACH | 1 | $18,000 | $8,500.00 |
| 71 | (619.17060005) | 5,175 | $3.50 | $12.00 | |
| 72 | Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716) | LF | 9,852 | $62.00 | $57.00 |
| 73 | Temporary Impact Attenuator - Redirective (Test Level 3) (619.1803) | EACH | 14 | $6,500.00 | $29,000 |
| 74 | Temporary Rumble Strips (619.22) | LF | 768 | $8.00 | $80.00 |
| 75 | Stone Filling (Light) (620.03) | CY | 1,260 | $192.00 | $400.00 |
| 76 | Cleaning Closed Drainage Systems (621.03) | LF | 813 | $10.00 | $50.00 |
| 77 | Cleaning Drainage Structures (621.04) | EACH | 14 | $700.00 | $960.00 |
| 78 | (621.51000015) | 265 | $63.00 | $250.00 | |
| 79 | Crushed Gravel (By Weight) (623.02) | TON | 10 | $100.00 | $290.00 |
| 80 | Crushed Stone (In-Place Measure) (623.12) | CY | 108 | $160.00 | $410.00 |
| 81 | Survey Operations (625.01) | LS | 1 | $200,390 | $350,000 |
| 82 | (627.50140008) | 6,977 | $4.00 | $11.00 | |
| 83 | (634.35000011) | 1,503 | $19.00 | $63.00 | |
| 84 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 22 | $2,900.00 | $21,000 |
| 85 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 |
| 86 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 |
| 87 | Construction Testing supplies – Consumables (637.36) | DOL | 100 | $1.00 | $1.00 |
| 88 | Type A Sign Posts (645.81) | EACH | 20 | $450.00 | $480.00 |
| 89 | Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22) | EACH | 15 | $33.00 | $35.00 |
| 90 | Steel Post, 2.0 lb/ft (646.32) | EACH | 10 | $200.00 | $190.00 |
| 91 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 21 | $450.00 | $310.00 |
| 92 | Centerline Audible Roadway Delineators (CARDs) (649.11) | LF | 11,250 | $2.00 | $1.50 |
| 93 | Manhole Frame & Cover (655.1202) | EACH | 1 | $1,900.00 | $2,300.00 |
| 94 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 34,200 | $1.00 | $0.80 |
| 95 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 22,800 | $1.00 | $0.80 |
| 96 | (691.04000020) | 112,000 | $1.00 | $1.00 | |
| 97 | Field Change Payment (FCP) (697.03) | DOL | 790,000 | $1.00 | $1.00 |
| 98 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 |
| 99 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 |
| 100 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 |
| 101 | Mobilization (699.040001) | LS | 1 | $340,000 | $600,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of March 5, 2026. Compiled by Mirage Metrics.