NYSDOT contract D265386 bid tabulation
Culvert Replacements and Rehabilitations - Various Locations. Let by New York State DOT on February 20, 2025, Orange, Rockland, Region 08. 5 bids received; low bid $9,364,279 by Jrcruz Corp.
- Owner
- New York State DOT
- Letting
- 20 FEB 2025
- Pay items
- 118
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Jrcruz Corp | $9,364,279 | Low |
| 2 | Northbrook Contracting Corp | $9,923,000 | +6.0% |
| 3 | D A Collins Construction Co Inc | $11,174,196 | +19% |
| 4 | A Servidone Inc/B Anthony Construction Corp JV | $12,336,048 | +32% |
| 5 | Morano Brothers Corp | $14,836,946 | +58% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Jrcruz Corp | 2. Northbrook Contracting Corp | 3. D A Collins Construction Co Inc | 4. A Servidone Inc/B Anthony Construction Corp JV | 5. Morano Brothers Corp |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $75,000 | $110,000 | $40,300 | $280,000 | $100,000 |
| 2 | (201.06000007) | LS | 1 | $15,000 | $25,000 | $8,350.00 | $10,000 | $13,000 |
| 3 | Removal of Substructures (202.19) | CY | 385 | $300.00 | $120.00 | $150.00 | $210.00 | $270.00 |
| 4 | Unclassified Excavation and Disposal (203.02) | CY | 4,120 | $98.00 | $50.00 | $74.50 | $250.00 | $101.00 |
| 5 | Embankment In Place (203.03) | CY | 3,810 | $28.00 | $35.00 | $49.50 | $55.00 | $46.00 |
| 6 | Select Structural Fill (203.21) | CY | 1,620 | $130.00 | $95.00 | $71.50 | $155.00 | $128.00 |
| 7 | (203.24010017) | 110 | $150.00 | $65.00 | $205.00 | $140.00 | $85.00 | |
| 8 | Structure Excavation (206.01) | CY | 5,707 | $66.00 | $45.00 | $37.50 | $50.00 | $120.00 |
| 9 | Trench and Culvert Excavation (206.0201) | CY | 700 | $78.00 | $45.00 | $37.00 | $58.00 | $148.00 |
| 10 | Geotextile Bedding (207.20) | SY | 1,090 | $4.25 | $5.00 | $4.80 | $5.00 | $4.50 |
| 11 | Prefabricated Composite Structural Drain (207.26) | SY | 110 | $35.00 | $14.00 | $18.00 | $60.00 | $23.00 |
| 12 | Silt Fence - Temporary (209.13) | LF | 2,155 | $8.25 | $6.00 | $8.95 | $9.00 | $4.80 |
| 13 | (209.15200009) | 4 | $2,500.00 | $800.00 | $535.00 | $6,300.00 | $6,700.00 | |
| 14 | Drainage Structure Inlet Protection, Silt Fence – Temporary (209.1701) | LF | 180 | $40.00 | $5.00 | $37.50 | $40.00 | $10.00 |
| 15 | Stabilized Construction Access (209.22) | SY | 1,465 | $35.00 | $13.00 | $24.50 | $27.00 | $30.00 |
| 16 | (209.31000010) | 4 | $275.00 | $2,000.00 | $745.00 | $5,200.00 | $27,000 | |
| 17 | (210.481201) | SF | 4,050 | $25.00 | $42.00 | $44.00 | $102.00 | $104.00 |
| 18 | (304.00010018) | 2,800 | $2.00 | $1.00 | $1.00 | $2.00 | $4.50 | |
| 19 | (304.11000008) | 2,568 | $65.00 | $90.00 | $54.00 | $170.00 | $87.00 | |
| 20 | (404.0001) | TON | 208 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 21 | (404.0189) | TON | 110 | $120.00 | $220.00 | $290.00 | $222.00 | $172.00 |
| 22 | (404.1283) | TON | 320 | $120.00 | $250.00 | $305.00 | $222.00 | $162.00 |
| 23 | (404.1989) | TON | 300 | $120.00 | $230.00 | $305.00 | $201.00 | $298.00 |
| 24 | (404.3789) | TON | 940 | $220.00 | $200.00 | $265.00 | $170.00 | $175.00 |
| 25 | (404.4289) | TON | 640 | $120.00 | $215.00 | $205.00 | $190.00 | $190.00 |
| 26 | (404.4389) | TON | 850 | $120.00 | $205.00 | $200.00 | $188.00 | $176.00 |
| 27 | (404.4589) | TON | 1,190 | $220.00 | $200.00 | $225.00 | $189.00 | $165.00 |
| 28 | Diluted Tack Coat (407.0102) | GAL | 7,490 | $6.50 | $3.00 | $6.80 | $5.00 | $14.00 |
| 29 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 1,715 | $1.50 | $8.00 | $9.45 | $10.00 | $14.00 |
| 30 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 610 | $95.00 | $50.00 | $295.00 | $32.00 | $85.00 |
| 31 | (502.32010018) | 530 | $85.00 | $60.00 | $70.00 | $40.00 | $78.00 | |
| 32 | (502.33010018) | 420 | $110.00 | $95.00 | $78.00 | $13.00 | $80.00 | |
| 33 | (502.36030018) | 180 | $815.00 | $900.00 | $1,300.00 | $830.00 | $1,000.00 | |
| 34 | (502.37010018) | 530 | $24.00 | $45.00 | $50.00 | $25.00 | $27.00 | |
| 35 | (502.38010018) | 830 | $24.00 | $30.00 | $55.50 | $27.00 | $27.00 | |
| 36 | Bump Grinding - PCC with Slurry Removal (505.0102) | SY | 790 | $35.00 | $70.00 | $47.50 | $30.00 | $35.00 |
| 37 | (510.90010018) | 1,360 | $22.00 | $10.00 | $10.00 | $12.00 | $31.00 | |
| 38 | Shields and Shoring (552.17) | SF | 1,535 | $1.00 | $18.00 | $100.00 | $1.00 | $35.00 |
| 39 | (552.2201) | LF | 500 | $101.00 | $350.00 | $170.00 | $230.00 | $239.00 |
| 40 | (552.230201) | SF | 1,200 | $12.50 | $17.00 | $31.00 | $30.00 | $87.00 |
| 41 | (553.030001) | EACH | 1 | $30,000 | $120,000 | $50,000 | $75,000 | $81,000 |
| 42 | (553.030002) | EACH | 1 | $30,000 | $120,000 | $65,000 | $90,000 | $89,000 |
| 43 | (553.030003) | EACH | 1 | $30,000 | $120,000 | $45,000 | $72,000 | $90,000 |
| 44 | (553.030004) | EACH | 1 | $30,000 | $75,000 | $80,000 | $82,000 | $90,000 |
| 45 | (553.030005) | EACH | 1 | $34,000 | $540,000 | $150,000 | $80,000 | $508,000 |
| 46 | (553.030006) | EACH | 1 | $24,000 | $45,000 | $50,000 | $62,000 | $32,000 |
| 47 | (553.030007) | EACH | 1 | $24,000 | $40,000 | $50,000 | $69,000 | $30,000 |
| 48 | (554.3001) | SF | 720 | $72.00 | $75.00 | $35.00 | $80.00 | $100.00 |
| 49 | (560.01010005) | 1 | $130,000 | $70,000 | $55,900 | $50,000 | $76,000 | |
| 50 | Steel Bridge Railing (Four-Rail) (568.51) | LF | 180 | $575.00 | $600.00 | $570.00 | $480.00 | $700.00 |
| 51 | Transition Bridge Railing (568.70) | LF | 576 | $265.00 | $315.00 | $315.00 | $265.00 | $490.00 |
| 52 | (583.04000008) | 1,400 | $62.00 | $98.00 | $85.00 | $70.00 | $255.00 | |
| 53 | (583.05000008) | 1,030 | $82.00 | $160.00 | $110.00 | $90.00 | $285.00 | |
| 54 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 130 | $135.00 | $90.00 | $88.50 | $110.00 | $80.00 |
| 55 | (595.50000018) | 3,308 | $10.00 | $7.00 | $10.00 | $17.00 | $20.00 | |
| 56 | (603.052210) | LF | 24 | $425.00 | $260.00 | $755.00 | $310.00 | $825.00 |
| 57 | (603.63060615) | 52 | $3,200.00 | $3,500.00 | $2,500.00 | $3,100.00 | $3,500.00 | |
| 58 | (603.63140815) | 33 | $5,700.00 | $6,700.00 | $4,650.00 | $7,000.00 | $5,400.00 | |
| 59 | (603.63160615) | 145 | $3,800.00 | $5,400.00 | $3,900.00 | $4,100.00 | $4,000.00 | |
| 60 | (603.63160815) | 55 | $4,900.00 | $5,700.00 | $5,500.00 | $5,600.00 | $5,000.00 | |
| 61 | (603.64080815) | 58 | $3,500.00 | $4,500.00 | $3,250.00 | $3,100.00 | $3,700.00 | |
| 62 | (603.67000001) | 170 | $1,900.00 | $2,400.00 | $2,200.00 | $1,420.00 | $1,050.00 | |
| 63 | Box Beam Guide Railing (606.10) | LF | 860 | $55.00 | $70.00 | $65.50 | $56.00 | $60.00 |
| 64 | Box Beam Guide Railing With Extra Long Posts (606.1001) | LF | 50 | $64.00 | $80.00 | $76.00 | $65.00 | $70.00 |
| 65 | Box Beam End Piece (606.120101) | EACH | 2 | $900.00 | $2,500.00 | $1,050.00 | $900.00 | $990.00 |
| 66 | Box Beam Guide Railing End Assembly Type IIA (606.120201) | EACH | 14 | $2,400.00 | $3,500.00 | $2,850.00 | $2,400.00 | $3,800.00 |
| 67 | Resetting Cable Guide Railing (New Posts) (606.5048) | LF | 40 | $26.00 | $30.00 | $31.00 | $26.00 | $28.00 |
| 68 | Resetting Corrugated Beam Guide Railing (New Posts) (606.5148) | LF | 72 | $33.00 | $35.00 | $39.50 | $33.00 | $36.00 |
| 69 | Resetting Box Beam Guide Railing (New Posts) (606.5348) | LF | 131 | $50.00 | $55.00 | $59.50 | $50.00 | $55.00 |
| 70 | Resetting Box Beam Median Barrier End Assembly--Type B (606.5931) | EACH | 1 | $1,215.00 | $2,000.00 | $1,450.00 | $1,215.00 | $3,800.00 |
| 71 | Removing and Storing Cable Guide Railing (606.60) | LF | 40 | $20.00 | $15.00 | $120.00 | $40.00 | $16.00 |
| 72 | Removing and Storing Corrugated Beam Guide Railing (606.61) | LF | 72 | $15.00 | $20.00 | $12.00 | $24.00 | $38.00 |
| 73 | Removing and Storing Box Beam Guide Railing (606.63) | LF | 131 | $20.00 | $20.00 | $19.50 | $48.00 | $38.00 |
| 74 | Removing and Storing Box Beam Guide Railing End Assembly (606.6920) | EACH | 1 | $50.00 | $1,800.00 | $145.00 | $4,490.00 | $1,600.00 |
| 75 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 1,360 | $20.00 | $14.00 | $7.75 | $20.00 | $27.00 |
| 76 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 5 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 77 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 90 | $140.00 | $260.00 | $695.00 | $222.00 | $197.00 |
| 78 | (609.06000008) | 3,755 | $50.00 | $27.00 | $4.35 | $9.00 | $22.00 | |
| 79 | (609.12290008) | 3,760 | $120.00 | $60.00 | $145.00 | $85.00 | $60.00 | |
| 80 | Turf Establishment – Performance (610.1605) | SY | 8,870 | $11.50 | $8.00 | $13.00 | $5.00 | $2.75 |
| 81 | (613.04000001) | 130 | $180.00 | $120.00 | $255.00 | $100.00 | $150.00 | |
| 82 | (615.01010108) | 545 | $230.00 | $180.00 | $60.50 | $170.00 | $660.00 | |
| 83 | (617.11000024) | LS | 1 | $2,500.00 | $3,000.00 | $4,700.00 | $35,000 | $14,000 |
| 84 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $685,000 | $303,185 | $1,650,000 | $1,413,517 | $1,731,000 |
| 85 | Type III Construction Barricades (619.04) | EACH | 41 | $125.00 | $150.00 | $105.00 | $450.00 | $222.00 |
| 86 | (619.080102) | LF | 23,500 | $1.70 | $1.50 | $1.55 | $2.00 | $1.50 |
| 87 | (619.100102) | LF | 14,300 | $1.30 | $1.50 | $1.50 | $2.00 | $1.40 |
| 88 | (619.110513) | EACH | 16 | $8,500.00 | $8,000.00 | $4,500.00 | $3,000.00 | $20,800 |
| 89 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 320 | $100.00 | $50.00 | $48.50 | $132.00 | $182.00 |
| 90 | Temporary Positive Barrier – Category 4 (Pinning Permitted) (619.1714) | LF | 1,800 | $150.00 | $70.00 | $115.00 | $123.00 | $154.00 |
| 91 | Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716) | LF | 700 | $150.00 | $72.00 | $115.00 | $123.00 | $191.00 |
| 92 | Temporary Impact Attenuator - Redirective (Test Level 2) (619.1802) | EACH | 9 | $10,000 | $5,000.00 | $3,850.00 | $15,160 | $19,000 |
| 93 | (619.99230103) | 32 | $750.00 | $3,000.00 | $10,800 | $16,000 | $15,000 | |
| 94 | Stone Filling (Light) (620.03) | CY | 160 | $125.00 | $130.00 | $115.00 | $200.00 | $160.00 |
| 95 | Stone Filling (Medium) (620.04) | CY | 358 | $145.00 | $275.00 | $250.00 | $270.00 | $310.00 |
| 96 | Bedding Material, Type 1 (620.0801) | CY | 180 | $160.00 | $165.00 | $110.00 | $190.00 | $235.00 |
| 97 | Clean, Grade and Shape Existing Roadside Section (621.05) | LF | 5,150 | $10.00 | $7.00 | $6.15 | $6.00 | $6.00 |
| 98 | (621.51010010) | 1,610 | $10.00 | $10.00 | $6.10 | $12.00 | $13.00 | |
| 99 | (623.12000008) | 277 | $75.00 | $98.00 | $205.00 | $130.00 | $215.00 | |
| 100 | Survey Operations (625.01) | LS | 1 | $150,000 | $200,000 | $281,000 | $250,000 | $839,000 |
| 101 | Concrete Right of Way Markers Type L (Low) (625.04) | EACH | 16 | $2,100.00 | $600.00 | $2,150.00 | $1,500.00 | $300.00 |
| 102 | (627.50140008) | 4,360 | $5.00 | $6.00 | $3.90 | $8.00 | $9.00 | |
| 103 | Cleaning Existing Pavement and/or Shoulder (633.11) | SY | 10,298 | $1.65 | $1.00 | $0.31 | $1.00 | $2.65 |
| 104 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 22 | $6,000.00 | $4,500.00 | $3,300.00 | $10,000 | $13,000 |
| 105 | Office Technology and Supplies (637.34) | DOL | 2,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 106 | Type A Sign Posts (645.81) | EACH | 7 | $300.00 | $375.00 | $355.00 | $300.00 | $330.00 |
| 107 | Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22) | EACH | 20 | $28.00 | $20.00 | $14.50 | $12.00 | $13.00 |
| 108 | Steel Post, 1.1 lb/ft (646.31) | EACH | 20 | $60.00 | $100.00 | $71.50 | $60.00 | $66.00 |
| 109 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 6 | $250.00 | $500.00 | $295.00 | $250.00 | $275.00 |
| 110 | Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51) | EACH | 1 | $125.00 | $500.00 | $570.00 | $720.00 | $275.00 |
| 111 | (658.50000008) | 2 | $3,600.00 | $4,500.00 | $2,050.00 | $2,500.00 | $980.00 | |
| 112 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 7,830 | $1.20 | $2.00 | $1.85 | $2.00 | $3.70 |
| 113 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 6,220 | $1.50 | $2.00 | $1.85 | $2.00 | $4.00 |
| 114 | Field Change Payment (FCP) (697.03) | DOL | 385,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 115 | Asphalt Price Adjustment (698.04) | DOL | 21,050 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 116 | Fuel Price Adjustment (698.05) | DOL | 9,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 117 | Steel/Iron Price Adjustment (698.06) | DOL | 600 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 118 | Mobilization (699.040001) | LS | 1 | $350,000 | $376,000 | $420,000 | $470,000 | $569,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of February 20, 2025. Compiled by Mirage Metrics.