NYSDOT contract D265386 bid tabulation

Culvert Replacements and Rehabilitations - Various Locations. Let by New York State DOT on February 20, 2025, Orange, Rockland, Region 08. 5 bids received; low bid $9,364,279 by Jrcruz Corp.

Owner
New York State DOT
Letting
20 FEB 2025
Pay items
118
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Jrcruz Corp$9,364,279Low
2Northbrook Contracting Corp$9,923,000+6.0%
3D A Collins Construction Co Inc$11,174,196+19%
4A Servidone Inc/B Anthony Construction Corp JV$12,336,048+32%
5Morano Brothers Corp$14,836,946+58%
NYSDOT contract D265386: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Jrcruz Corp2. Northbrook Contracting Corp3. D A Collins Construction Co Inc4. A Servidone Inc/B Anthony Construction Corp JV5. Morano Brothers Corp
1Clearing and Grubbing (201.06)LS1$75,000$110,000$40,300$280,000$100,000
2 (201.06000007)LS1$15,000$25,000$8,350.00$10,000$13,000
3Removal of Substructures (202.19)CY385$300.00$120.00$150.00$210.00$270.00
4Unclassified Excavation and Disposal (203.02)CY4,120$98.00$50.00$74.50$250.00$101.00
5Embankment In Place (203.03)CY3,810$28.00$35.00$49.50$55.00$46.00
6Select Structural Fill (203.21)CY1,620$130.00$95.00$71.50$155.00$128.00
7 (203.24010017)110$150.00$65.00$205.00$140.00$85.00
8Structure Excavation (206.01)CY5,707$66.00$45.00$37.50$50.00$120.00
9Trench and Culvert Excavation (206.0201)CY700$78.00$45.00$37.00$58.00$148.00
10Geotextile Bedding (207.20)SY1,090$4.25$5.00$4.80$5.00$4.50
11Prefabricated Composite Structural Drain (207.26)SY110$35.00$14.00$18.00$60.00$23.00
12Silt Fence - Temporary (209.13)LF2,155$8.25$6.00$8.95$9.00$4.80
13 (209.15200009)4$2,500.00$800.00$535.00$6,300.00$6,700.00
14Drainage Structure Inlet Protection, Silt Fence – Temporary (209.1701)LF180$40.00$5.00$37.50$40.00$10.00
15Stabilized Construction Access (209.22)SY1,465$35.00$13.00$24.50$27.00$30.00
16 (209.31000010)4$275.00$2,000.00$745.00$5,200.00$27,000
17 (210.481201)SF4,050$25.00$42.00$44.00$102.00$104.00
18 (304.00010018)2,800$2.00$1.00$1.00$2.00$4.50
19 (304.11000008)2,568$65.00$90.00$54.00$170.00$87.00
20 (404.0001)TON208$120.00$120.00$120.00$120.00$120.00
21 (404.0189)TON110$120.00$220.00$290.00$222.00$172.00
22 (404.1283)TON320$120.00$250.00$305.00$222.00$162.00
23 (404.1989)TON300$120.00$230.00$305.00$201.00$298.00
24 (404.3789)TON940$220.00$200.00$265.00$170.00$175.00
25 (404.4289)TON640$120.00$215.00$205.00$190.00$190.00
26 (404.4389)TON850$120.00$205.00$200.00$188.00$176.00
27 (404.4589)TON1,190$220.00$200.00$225.00$189.00$165.00
28Diluted Tack Coat (407.0102)GAL7,490$6.50$3.00$6.80$5.00$14.00
29Asphalt Pavement Joint Adhesive (418.7603)LF1,715$1.50$8.00$9.45$10.00$14.00
30Miscellaneous Cold Milling of Bituminous Concrete (490.30)SY610$95.00$50.00$295.00$32.00$85.00
31 (502.32010018)530$85.00$60.00$70.00$40.00$78.00
32 (502.33010018)420$110.00$95.00$78.00$13.00$80.00
33 (502.36030018)180$815.00$900.00$1,300.00$830.00$1,000.00
34 (502.37010018)530$24.00$45.00$50.00$25.00$27.00
35 (502.38010018)830$24.00$30.00$55.50$27.00$27.00
36Bump Grinding - PCC with Slurry Removal (505.0102)SY790$35.00$70.00$47.50$30.00$35.00
37 (510.90010018)1,360$22.00$10.00$10.00$12.00$31.00
38Shields and Shoring (552.17)SF1,535$1.00$18.00$100.00$1.00$35.00
39 (552.2201)LF500$101.00$350.00$170.00$230.00$239.00
40 (552.230201)SF1,200$12.50$17.00$31.00$30.00$87.00
41 (553.030001)EACH1$30,000$120,000$50,000$75,000$81,000
42 (553.030002)EACH1$30,000$120,000$65,000$90,000$89,000
43 (553.030003)EACH1$30,000$120,000$45,000$72,000$90,000
44 (553.030004)EACH1$30,000$75,000$80,000$82,000$90,000
45 (553.030005)EACH1$34,000$540,000$150,000$80,000$508,000
46 (553.030006)EACH1$24,000$45,000$50,000$62,000$32,000
47 (553.030007)EACH1$24,000$40,000$50,000$69,000$30,000
48 (554.3001)SF720$72.00$75.00$35.00$80.00$100.00
49 (560.01010005)1$130,000$70,000$55,900$50,000$76,000
50Steel Bridge Railing (Four-Rail) (568.51)LF180$575.00$600.00$570.00$480.00$700.00
51Transition Bridge Railing (568.70)LF576$265.00$315.00$315.00$265.00$490.00
52 (583.04000008)1,400$62.00$98.00$85.00$70.00$255.00
53 (583.05000008)1,030$82.00$160.00$110.00$90.00$285.00
54Drilling and Grouting Bolts or Reinforcing Bars (586.0201)EACH130$135.00$90.00$88.50$110.00$80.00
55 (595.50000018)3,308$10.00$7.00$10.00$17.00$20.00
56 (603.052210)LF24$425.00$260.00$755.00$310.00$825.00
57 (603.63060615)52$3,200.00$3,500.00$2,500.00$3,100.00$3,500.00
58 (603.63140815)33$5,700.00$6,700.00$4,650.00$7,000.00$5,400.00
59 (603.63160615)145$3,800.00$5,400.00$3,900.00$4,100.00$4,000.00
60 (603.63160815)55$4,900.00$5,700.00$5,500.00$5,600.00$5,000.00
61 (603.64080815)58$3,500.00$4,500.00$3,250.00$3,100.00$3,700.00
62 (603.67000001)170$1,900.00$2,400.00$2,200.00$1,420.00$1,050.00
63Box Beam Guide Railing (606.10)LF860$55.00$70.00$65.50$56.00$60.00
64Box Beam Guide Railing With Extra Long Posts (606.1001)LF50$64.00$80.00$76.00$65.00$70.00
65Box Beam End Piece (606.120101)EACH2$900.00$2,500.00$1,050.00$900.00$990.00
66Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH14$2,400.00$3,500.00$2,850.00$2,400.00$3,800.00
67Resetting Cable Guide Railing (New Posts) (606.5048)LF40$26.00$30.00$31.00$26.00$28.00
68Resetting Corrugated Beam Guide Railing (New Posts) (606.5148)LF72$33.00$35.00$39.50$33.00$36.00
69Resetting Box Beam Guide Railing (New Posts) (606.5348)LF131$50.00$55.00$59.50$50.00$55.00
70Resetting Box Beam Median Barrier End Assembly--Type B (606.5931)EACH1$1,215.00$2,000.00$1,450.00$1,215.00$3,800.00
71Removing and Storing Cable Guide Railing (606.60)LF40$20.00$15.00$120.00$40.00$16.00
72Removing and Storing Corrugated Beam Guide Railing (606.61)LF72$15.00$20.00$12.00$24.00$38.00
73Removing and Storing Box Beam Guide Railing (606.63)LF131$20.00$20.00$19.50$48.00$38.00
74Removing and Storing Box Beam Guide Railing End Assembly (606.6920)EACH1$50.00$1,800.00$145.00$4,490.00$1,600.00
75Removing and Disposing Box Beam Guide Railing (606.73)LF1,360$20.00$14.00$7.75$20.00$27.00
76Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013)QUALITY UNIT5$120.00$120.00$120.00$120.00$120.00
77Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON90$140.00$260.00$695.00$222.00$197.00
78 (609.06000008)3,755$50.00$27.00$4.35$9.00$22.00
79 (609.12290008)3,760$120.00$60.00$145.00$85.00$60.00
80Turf Establishment – Performance (610.1605)SY8,870$11.50$8.00$13.00$5.00$2.75
81 (613.04000001)130$180.00$120.00$255.00$100.00$150.00
82 (615.01010108)545$230.00$180.00$60.50$170.00$660.00
83 (617.11000024)LS1$2,500.00$3,000.00$4,700.00$35,000$14,000
84Basic Work Zone Traffic Control (619.01)LS1$685,000$303,185$1,650,000$1,413,517$1,731,000
85Type III Construction Barricades (619.04)EACH41$125.00$150.00$105.00$450.00$222.00
86 (619.080102)LF23,500$1.70$1.50$1.55$2.00$1.50
87 (619.100102)LF14,300$1.30$1.50$1.50$2.00$1.40
88 (619.110513)EACH16$8,500.00$8,000.00$4,500.00$3,000.00$20,800
89Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711)LF320$100.00$50.00$48.50$132.00$182.00
90Temporary Positive Barrier – Category 4 (Pinning Permitted) (619.1714)LF1,800$150.00$70.00$115.00$123.00$154.00
91Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716)LF700$150.00$72.00$115.00$123.00$191.00
92Temporary Impact Attenuator - Redirective (Test Level 2) (619.1802)EACH9$10,000$5,000.00$3,850.00$15,160$19,000
93 (619.99230103)32$750.00$3,000.00$10,800$16,000$15,000
94Stone Filling (Light) (620.03)CY160$125.00$130.00$115.00$200.00$160.00
95Stone Filling (Medium) (620.04)CY358$145.00$275.00$250.00$270.00$310.00
96Bedding Material, Type 1 (620.0801)CY180$160.00$165.00$110.00$190.00$235.00
97Clean, Grade and Shape Existing Roadside Section (621.05)LF5,150$10.00$7.00$6.15$6.00$6.00
98 (621.51010010)1,610$10.00$10.00$6.10$12.00$13.00
99 (623.12000008)277$75.00$98.00$205.00$130.00$215.00
100Survey Operations (625.01)LS1$150,000$200,000$281,000$250,000$839,000
101Concrete Right of Way Markers Type L (Low) (625.04)EACH16$2,100.00$600.00$2,150.00$1,500.00$300.00
102 (627.50140008)4,360$5.00$6.00$3.90$8.00$9.00
103Cleaning Existing Pavement and/or Shoulder (633.11)SY10,298$1.65$1.00$0.31$1.00$2.65
104Engineer’s Field Office – Type 3 (637.13)MONTH22$6,000.00$4,500.00$3,300.00$10,000$13,000
105Office Technology and Supplies (637.34)DOL2,000$1.00$1.00$1.00$1.00$1.00
106Type A Sign Posts (645.81)EACH7$300.00$375.00$355.00$300.00$330.00
107Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22)EACH20$28.00$20.00$14.50$12.00$13.00
108Steel Post, 1.1 lb/ft (646.31)EACH20$60.00$100.00$71.50$60.00$66.00
109Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31)EACH6$250.00$500.00$295.00$250.00$275.00
110Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51)EACH1$125.00$500.00$570.00$720.00$275.00
111 (658.50000008)2$3,600.00$4,500.00$2,050.00$2,500.00$980.00
112White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102)LF7,830$1.20$2.00$1.85$2.00$3.70
113Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202)LF6,220$1.50$2.00$1.85$2.00$4.00
114Field Change Payment (FCP) (697.03)DOL385,000$1.00$1.00$1.00$1.00$1.00
115Asphalt Price Adjustment (698.04)DOL21,050$1.00$1.00$1.00$1.00$1.00
116Fuel Price Adjustment (698.05)DOL9,500$1.00$1.00$1.00$1.00$1.00
117Steel/Iron Price Adjustment (698.06)DOL600$1.00$1.00$1.00$1.00$1.00
118Mobilization (699.040001)LS1$350,000$376,000$420,000$470,000$569,000
NYSDOT contract D265386: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of February 20, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy