NYSDOT contract D265424 bid tabulation
Replacement and Relining of Culverts - Various locations. Let by New York State DOT on February 27, 2025, Putnam, Westchester, Region 08. 5 bids received; low bid $13,322,365 by Jrcruz Corp.
- Owner
- New York State DOT
- Letting
- 27 FEB 2025
- Pay items
- 192
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Jrcruz Corp | $13,322,365 | Low |
| 2 | Northbrook Contracting Corp | $13,775,000 | +3.0% |
| 3 | McNamee Construction Corp | $14,874,000 | +12% |
| 4 | Montesano Bros Inc | $16,581,083 | +24% |
| 5 | Elq Industries Inc | $17,242,369 | +29% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Jrcruz Corp | 2. Northbrook Contracting Corp | 3. McNamee Construction Corp | 4. Montesano Bros Inc | 5. Elq Industries Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $100,000 | $104,000 | $100,000 | $730,000 | $400,000 |
| 2 | (201.06000007) | LS | 1 | $25,000 | $25,000 | $70,000 | $8,700.00 | $100,000 |
| 3 | Removal of Substructures (202.19) | CY | 208 | $500.00 | $370.00 | $532.00 | $320.00 | $500.00 |
| 4 | Unclassified Excavation and Disposal (203.02) | CY | 4,409 | $100.00 | $80.00 | $121.00 | $113.00 | $132.00 |
| 5 | Embankment In Place (203.03) | CY | 2,397 | $65.00 | $69.00 | $50.00 | $75.00 | $105.00 |
| 6 | Select Granular Fill (203.07) | CY | 1,300 | $65.00 | $105.00 | $120.00 | $132.00 | $160.00 |
| 7 | (203.24010017) | 5 | $250.00 | $400.00 | $150.00 | $960.00 | $145.00 | |
| 8 | (205.0201) | LS | 1 | $5,000.00 | $5,000.00 | $10,000 | $31,000 | $10,000 |
| 9 | Field Organic Vapor Monitoring of Contaminated Soil (205.03) | HR | 1 | $300.00 | $200.00 | $4,500.00 | $230.00 | $100.00 |
| 10 | Petroleum Contamination Parameter Analysis (205.0401) | EACH | 1 | $300.00 | $1,000.00 | $4,500.00 | $2,200.00 | $200.00 |
| 11 | Laboratory Analysis for Hazardous Waste RCRA Toxicity Characteristic (205.0402) | EACH | 1 | $300.00 | $1,000.00 | $4,500.00 | $1,500.00 | $1,000.00 |
| 12 | Laboratory Analysis for Ignitability (205.0403) | EACH | 1 | $300.00 | $250.00 | $4,500.00 | $1,500.00 | $100.00 |
| 13 | Laboratory Analysis for ph (205.0404) | EACH | 1 | $125.00 | $300.00 | $4,500.00 | $1,500.00 | $20.00 |
| 14 | Laboratory Analysis for Polychlorinated Biphenyls (PCB's) (205.0405) | EACH | 1 | $125.00 | $750.00 | $4,500.00 | $1,500.00 | $150.00 |
| 15 | Laboratory Analysis for Total Petroleum Hydrocarbons– Gasoline Range Organics (205.0406) | EACH | 1 | $125.00 | $750.00 | $4,500.00 | $1,500.00 | $100.00 |
| 16 | Laboratory Analysis for Total Petroleum Hydrocarbons– Diesel Range Organics (205.0407) | EACH | 1 | $125.00 | $750.00 | $4,500.00 | $1,500.00 | $100.00 |
| 17 | (205.050101) | TON | 1 | $500.00 | $1,500.00 | $350.00 | $1,800.00 | $335.00 |
| 18 | (205.050201) | TON | 1 | $500.00 | $90.00 | $150.00 | $600.00 | $85.00 |
| 19 | (205.0601) | CY | 1 | $500.00 | $150.00 | $1,000.00 | $1,800.00 | $123.00 |
| 20 | Structure Excavation (206.01) | CY | 4,082 | $100.00 | $100.00 | $145.00 | $110.00 | $205.00 |
| 21 | Trench and Culvert Excavation (206.0201) | CY | 1,764 | $100.00 | $50.00 | $225.00 | $110.00 | $120.00 |
| 22 | Test Pit Excavation (206.05) | EACH | 12 | $5,000.00 | $1,000.00 | $2,000.00 | $3,000.00 | $4,000.00 |
| 23 | Geotextile Bedding (207.20) | SY | 737 | $10.00 | $16.00 | $13.00 | $20.00 | $8.00 |
| 24 | Geotextile Drainage (207.22) | SY | 353 | $10.00 | $3.00 | $3.00 | $11.00 | $6.00 |
| 25 | Mulch – Temporary (209.100101) | SY | 2,325 | $2.50 | $7.40 | $2.50 | $18.00 | $1.50 |
| 26 | Seed and Mulch – Temporary (209.1003) | SY | 2,325 | $3.75 | $5.00 | $3.00 | $3.00 | $2.00 |
| 27 | (209.11000001) | 2 | $150.00 | $250.00 | $700.00 | $1,000.00 | $180.00 | |
| 28 | Silt Fence - Temporary (209.13) | LF | 2,966 | $10.00 | $10.00 | $11.00 | $13.00 | $10.00 |
| 29 | Turbidity Curtain – Temporary (209.1501) | LF | 301 | $55.00 | $90.00 | $50.00 | $84.00 | $135.00 |
| 30 | (209.15200009) | 2 | $25,000 | $3,500.00 | $1,500.00 | $13,000 | $3,100.00 | |
| 31 | Stabilized Construction Access (209.22) | SY | 1,325 | $30.00 | $130.00 | $45.00 | $110.00 | $50.00 |
| 32 | Sediment Filter Log, 12″ (209.2301) | LF | 29 | $15.00 | $25.00 | $25.00 | $44.00 | $40.00 |
| 33 | (209.31000010) | 1 | $5,000.00 | $3,000.00 | $10,000 | $20,000 | $14,000 | |
| 34 | Removal and Disposal of Concrete-Encased Pipe ACM (BV14) (210.3011) | LF | 1 | $9,500.00 | $4,500.00 | $8,000.00 | $13,000 | $9,500.00 |
| 35 | Removal and Disposal of Underground Pipe ACM (BV14) (210.3111) | LF | 26 | $1,400.00 | $690.00 | $375.00 | $1,000.00 | $356.00 |
| 36 | (210.481201) | SF | 65 | $250.00 | $115.00 | $250.00 | $320.00 | $190.00 |
| 37 | (304.11000008) | 1,470 | $100.00 | $130.00 | $140.00 | $137.00 | $145.00 | |
| 38 | (404.0001) | TON | 181 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 39 | (404.0179) | TON | 145 | $300.00 | $300.00 | $325.00 | $640.00 | $210.00 |
| 40 | (404.1271) | TON | 47 | $400.00 | $277.00 | $300.00 | $470.00 | $230.00 |
| 41 | (404.1273) | TON | 889 | $300.00 | $270.00 | $300.00 | $287.00 | $200.00 |
| 42 | (404.1979) | TON | 590 | $250.00 | $249.00 | $300.00 | $303.00 | $201.00 |
| 43 | (404.3779) | TON | 1,905 | $250.00 | $242.00 | $300.00 | $240.00 | $172.00 |
| 44 | Straight Tack Coat (407.0103) | GAL | 607 | $40.00 | $40.00 | $75.00 | $48.00 | $31.00 |
| 45 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 1,851 | $5.00 | $30.00 | $3.00 | $23.00 | $15.00 |
| 46 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 4,372 | $35.00 | $25.00 | $25.00 | $40.00 | $34.00 |
| 47 | Temporary Steel Sheeting (552.13) | SF | 270 | $50.00 | $290.00 | $125.00 | $173.00 | $89.00 |
| 48 | Interim Steel Sheeting (552.15) | SF | 1,395 | $50.00 | $150.00 | $150.00 | $121.00 | $89.00 |
| 49 | Shields and Shoring (552.17) | SF | 7,731 | $12.00 | $10.00 | $5.00 | $98.00 | $3.00 |
| 50 | (552.18000017) | 4,791 | $15.00 | $35.00 | $11.00 | $31.00 | $58.00 | |
| 51 | (553.010001) | EACH | 2 | $250,000 | $345,000 | $275,000 | $115,000 | $278,000 |
| 52 | (553.030001) | EACH | 1 | $200,000 | $435,000 | $160,000 | $165,000 | $330,000 |
| 53 | (553.030002) | EACH | 1 | $250,000 | $435,000 | $180,000 | $280,000 | $335,000 |
| 54 | (553.030003) | EACH | 1 | $225,000 | $370,000 | $250,000 | $163,000 | $350,000 |
| 55 | (553.030004) | EACH | 1 | $250,000 | $165,000 | $160,000 | $240,000 | $330,000 |
| 56 | (553.030005) | EACH | 1 | $250,000 | $155,000 | $260,000 | $227,000 | $160,000 |
| 57 | (553.030006) | EACH | 1 | $200,000 | $70.00 | $270,000 | $205,000 | $325,000 |
| 58 | (553.030007) | EACH | 1 | $275,000 | $125,000 | $160,000 | $163,000 | $416,000 |
| 59 | (554.3001) | SF | 160 | $200.00 | $70.00 | $100.00 | $161.00 | $170.00 |
| 60 | Concrete for Structures, Performance (555.0021) | CY | 3 | $3,500.00 | $3,800.00 | $10,000 | $3,200.00 | $5,000.00 |
| 61 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $9.89 | $9.89 | $9.89 | $9.89 | $9.89 |
| 62 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 524 | $10.00 | $18.00 | $5.00 | $8.00 | $3.00 |
| 63 | (564.0501) | LS | 1 | $12,500 | $15,000 | $115,000 | $65,000 | $26,000 |
| 64 | Steel Bridge Railing (Four-Rail) (568.51) | LF | 117 | $500.00 | $460.00 | $375.00 | $460.00 | $445.00 |
| 65 | Transition Bridge Railing (568.70) | LF | 460 | $485.00 | $445.00 | $300.00 | $445.00 | $430.00 |
| 66 | (583.04000008) | 65 | $600.00 | $610.00 | $80.00 | $57.00 | $50.00 | |
| 67 | (583.05000008) | 6,890 | $100.00 | $110.00 | $86.00 | $105.00 | $103.00 | |
| 68 | (595.50000018) | 3,274 | $20.00 | $11.00 | $11.00 | $11.00 | $19.00 | |
| 69 | (603.6002) | LF | 13 | $350.00 | $345.00 | $70.00 | $315.00 | $240.00 |
| 70 | (603.6003) | LF | 22 | $600.00 | $260.00 | $75.00 | $300.00 | $240.00 |
| 71 | (603.6010) | LF | 72 | $700.00 | $255.00 | $220.00 | $480.00 | $500.00 |
| 72 | (603.63080615) | 43 | $4,750.00 | $3,500.00 | $2,580.00 | $4,650.00 | $3,400.00 | |
| 73 | (603.63120515) | 71 | $5,000.00 | $3,200.00 | $2,800.00 | $4,470.00 | $4,300.00 | |
| 74 | (603.63140415) | 62 | $5,500.00 | $4,700.00 | $4,347.00 | $7,100.00 | $4,700.00 | |
| 75 | (603.63160815) | 40 | $6,500.00 | $4,500.00 | $4,356.00 | $7,100.00 | $5,700.00 | |
| 76 | (603.64081615) | 104 | $6,500.00 | $3,900.00 | $3,100.00 | $4,550.00 | $4,200.00 | |
| 77 | (603.64100715) | 59 | $5,000.00 | $3,300.00 | $3,100.00 | $4,600.00 | $4,100.00 | |
| 78 | (603.67000001) | 131 | $2,000.00 | $2,275.00 | $3,500.00 | $3,000.00 | $3,400.00 | |
| 79 | (603.7302) | EACH | 1 | $5,000.00 | $3,500.00 | $1,500.00 | $6,620.00 | $2,200.00 |
| 80 | (603.7303) | EACH | 2 | $5,250.00 | $2,500.00 | $3,000.00 | $7,100.00 | $2,700.00 |
| 81 | (603.7310) | EACH | 2 | $15,000 | $5,000.00 | $6,000.00 | $10,000 | $8,000.00 |
| 82 | (603.97000002) | 3 | $5,250.00 | $3,300.00 | $2,300.00 | $1,250.00 | $4,000.00 | |
| 83 | (603.9824) | LF | 130 | $125.00 | $55.00 | $60.00 | $130.00 | $160.00 |
| 84 | (603.99050002) | 2 | $2,500.00 | $300.00 | $600.00 | $1,300.00 | $805.00 | |
| 85 | (603.99220015) | 118 | $135.00 | $15.00 | $25.00 | $325.00 | $253.00 | |
| 86 | (604.07210110) | 1 | $1,500.00 | $790.00 | $300.00 | $1,350.00 | $900.00 | |
| 87 | (604.4048) | LF | 14 | $700.00 | $900.00 | $200.00 | $1,500.00 | $720.00 |
| 88 | Box Beam Guide Railing (606.10) | LF | 919 | $80.00 | $72.00 | $90.00 | $72.00 | $70.00 |
| 89 | Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002) | LF | 36 | $100.00 | $90.00 | $100.00 | $90.00 | $86.00 |
| 90 | Box Beam Guide Railing With Extra Long Posts (606.1001) | LF | 47 | $85.00 | $77.00 | $100.00 | $77.00 | $74.00 |
| 91 | Box Beam Guide Railing with Extra Long Posts (Shop Bent or Shop Mitered) (606.100102) | LF | 47 | $100.00 | $94.00 | $100.00 | $95.00 | $91.00 |
| 92 | Box Beam Guide Railing with Extra Long Posts (Shop Mitered) (606.100103) | LF | 47 | $95.00 | $84.00 | $75.00 | $84.00 | $81.00 |
| 93 | Box Beam End Piece (606.120101) | EACH | 2 | $1,050.00 | $975.00 | $1,500.00 | $1,000.00 | $940.00 |
| 94 | Box Beam Guide Railing End Assembly Type IIA (606.120201) | EACH | 7 | $4,850.00 | $4,500.00 | $4,000.00 | $4,500.00 | $4,300.00 |
| 95 | Box Beam End Assembly Type III (606.1203) | EACH | 3 | $15,000 | $12,500 | $11,000 | $13,000 | $12,000 |
| 96 | Weak-Post, Corrugated Beam Guide Rail With Extra Long Posts (606.1801) | LF | 47 | $65.00 | $52.00 | $75.00 | $60.00 | $58.00 |
| 97 | Weak-Post, Corrugated Beam Guide Rail With Extra Long Posts (Shop Curved) (606.180101) | LF | 47 | $70.00 | $56.00 | $75.00 | $65.00 | $62.00 |
| 98 | Single-Slope Concrete Median Barrier (Optional) (606.3041) | LF | 112 | $700.00 | $335.00 | $800.00 | $405.00 | $261.00 |
| 99 | Resetting HPBO (Mod.) Corrugated Beam Guide Railing (New Posts) (606.5801) | LF | 81 | $80.00 | $62.00 | $75.00 | $72.00 | $70.00 |
| 100 | Removing and Storing HPBO (Mod.) Corrugated Beam Guide Railing (606.66) | LF | 81 | $20.00 | $14.00 | $30.00 | $19.00 | $18.00 |
| 101 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 1,165 | $12.00 | $15.00 | $15.00 | $11.00 | $10.00 |
| 102 | Removing and Disposing Concrete Barrier (606.75) | LF | 112 | $225.00 | $125.00 | $100.00 | $120.00 | $115.00 |
| 103 | Transition Between Box Beam Guide Rail and Single Slope Half Section Concrete Barrier (One or Two Way Operation) (606.8803) | EACH | 1 | $12,500 | $10,000 | $10,000 | $14,600 | $10,000 |
| 104 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 4 | $85.00 | $85.00 | $85.00 | $85.00 | $85.00 |
| 105 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 36 | $500.00 | $600.00 | $300.00 | $280.00 | $290.00 |
| 106 | (609.06000008) | 296 | $50.00 | $32.00 | $20.00 | $53.00 | $10.00 | |
| 107 | (609.10010415) | 36 | $50.00 | $105.00 | $80.00 | $57.00 | $23.00 | |
| 108 | (609.12290008) | 199 | $125.00 | $75.00 | $125.00 | $194.00 | $335.00 | |
| 109 | Topsoil – On-Site Wetland Materials (610.1406) | CY | 33 | $115.00 | $110.00 | $60.00 | $195.00 | $100.00 |
| 110 | Topsoil – Wetland Materials (610.1407) | CY | 140 | $115.00 | $165.00 | $160.00 | $195.00 | $120.00 |
| 111 | Turf Establishment – Performance (610.1605) | SY | 2,472 | $15.00 | $18.00 | $6.00 | $7.00 | $3.30 |
| 112 | Wildflower Seeding (610.17) | SY | 1,229 | $3.00 | $8.00 | $6.50 | $5.00 | $3.30 |
| 113 | Watering Vegetation (610.19) | 1,000 GALLONS | 130 | $125.00 | $230.00 | $150.00 | $190.00 | $200.00 |
| 114 | (613.04000001) | 94 | $250.00 | $145.00 | $110.00 | $305.00 | $350.00 | |
| 115 | (615.01010108) | 383 | $150.00 | $320.00 | $200.00 | $441.00 | $136.00 | |
| 116 | (617.11000024) | LS | 1 | $1,000.00 | $15,000 | $5,000.00 | $142,000 | $13,000 |
| 117 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $400,000 | $1,000,419 | $2,533,328 | $830,000 | $1,998,000 |
| 118 | Type III Construction Barricades (619.04) | EACH | 74 | $50.00 | $350.00 | $200.00 | $650.00 | $800.00 |
| 119 | (619.080101) | LF | 4,853 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 120 | (619.080102) | LF | 2,629 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 121 | (619.080201) | EACH | 17 | $60.00 | $100.00 | $110.00 | $110.00 | $105.00 |
| 122 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 3,802 | $3.50 | $4.00 | $4.00 | $5.00 | $4.50 |
| 123 | Cover Existing Pavement Marking Letters or Symbols (Removable Tape) (619.0804) | EACH | 16 | $95.00 | $150.00 | $150.00 | $144.00 | $140.00 |
| 124 | (619.0904) | LF | 8,348 | $3.50 | $3.00 | $3.00 | $3.50 | $3.50 |
| 125 | (619.100101) | LF | 4,853 | $1.50 | $1.00 | $1.00 | $1.00 | $0.70 |
| 126 | (619.100201) | EACH | 16 | $65.00 | $150.00 | $100.00 | $100.00 | $94.00 |
| 127 | (619.110513) | EACH | 17 | $5,000.00 | $6,000.00 | $6,000.00 | $28,000 | $7,200.00 |
| 128 | (619.110532) | EACH | 3 | $20,000 | $8,000.00 | $6,000.00 | $47,000 | $21,000 |
| 129 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 280 | $200.00 | $90.00 | $70.00 | $42.00 | $175.00 |
| 130 | Temporary Positive Barrier – Category 3 (Pinning Prohibited) (619.1713) | LF | 157 | $200.00 | $96.00 | $70.00 | $20.00 | $175.00 |
| 131 | Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716) | LF | 1,022 | $200.00 | $60.00 | $90.00 | $71.00 | $175.00 |
| 132 | Warning Lights on Temporary Positive Barriers (619.1719) | EACH | 41 | $100.00 | $75.00 | $50.00 | $130.00 | $250.00 |
| 133 | (619.99230103) | 24 | $5,000.00 | $11,000 | $6,000.00 | $13,000 | $6,000.00 | |
| 134 | Stone Filling (Light) (620.03) | CY | 112 | $160.00 | $265.00 | $175.00 | $352.00 | $400.00 |
| 135 | Stone Filling (Medium) (620.04) | CY | 481 | $165.00 | $193.00 | $150.00 | $260.00 | $400.00 |
| 136 | Stone Filling (Heavy) (620.05) | CY | 115 | $225.00 | $305.00 | $200.00 | $540.00 | $500.00 |
| 137 | Grouted Rip-Rap (620.07) | CY | 87 | $750.00 | $600.00 | $350.00 | $390.00 | $1,200.00 |
| 138 | Bedding Material, Type 1 (620.0801) | CY | 151 | $150.00 | $205.00 | $180.00 | $270.00 | $315.00 |
| 139 | Cleaning Drainage Structures (621.04) | EACH | 8 | $800.00 | $750.00 | $500.00 | $2,200.00 | $2,100.00 |
| 140 | Clean, Grade and Shape Existing Roadside Section (621.05) | LF | 100 | $50.00 | $20.00 | $10.00 | $100.00 | $54.00 |
| 141 | (621.51010010) | 100 | $50.00 | $28.00 | $10.00 | $100.00 | $27.00 | |
| 142 | Crushed Stone (In-Place Measure) (623.12) | CY | 31 | $150.00 | $123.00 | $200.00 | $250.00 | $400.00 |
| 143 | (623.12000008) | 265 | $150.00 | $170.00 | $200.00 | $280.00 | $415.00 | |
| 144 | Asphalt Gutter (624.020101) | TON | 1 | $500.00 | $500.00 | $500.00 | $800.00 | $240.00 |
| 145 | Plant Production Quality Adjustment to 624.020101 (624.020110) | QUALITY UNIT | 1 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 146 | Survey Operations (625.01) | LS | 1 | $250,000 | $350,000 | $115,000 | $70,000 | $196,000 |
| 147 | Concrete Right of Way Markers Type L (Low) (625.04) | EACH | 27 | $1,500.00 | $1,150.00 | $700.00 | $2,300.00 | $1,400.00 |
| 148 | (627.50140008) | 609 | $6.00 | $15.00 | $10.00 | $37.00 | $6.00 | |
| 149 | Cleaning Existing Pavement and/or Shoulder (633.11) | SY | 100 | $30.00 | $17.00 | $4.00 | $2.00 | $61.00 |
| 150 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $5,000.00 | $3,000.00 | $1,300.00 | $6,600.00 | $6,500.00 |
| 151 | Engineer’s Field Office – Type 3 (637.13) | MONTH | 21 | $7,500.00 | $5,000.00 | $5,000.00 | $9,000.00 | $6,700.00 |
| 152 | Rain Gauge (637.26) | EACH | 1 | $500.00 | $250.00 | $1,700.00 | $12,800 | $1,700.00 |
| 153 | Office Technology and Supplies (637.34) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 154 | Partnering Workshop (637.35) | DOL | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 155 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 20 | $100.00 | $97.00 | $50.00 | $100.00 | $94.00 |
| 156 | Type A Sign Posts (645.81) | EACH | 15 | $430.00 | $400.00 | $500.00 | $400.00 | $380.00 |
| 157 | (645.81090003) | 2 | $115.00 | $100.00 | $2,600.00 | $100.00 | $100.00 | |
| 158 | Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22) | EACH | 20 | $100.00 | $95.00 | $150.00 | $100.00 | $93.00 |
| 159 | Reference Marker, Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels Relocation (646.24) | EACH | 2 | $185.00 | $350.00 | $100.00 | $175.00 | $166.00 |
| 160 | Steel Post, 2.0 lb/ft (646.32) | EACH | 12 | $220.00 | $200.00 | $300.00 | $200.00 | $195.00 |
| 161 | Brackets for Barrier and Multidirectional Mounting (646.50) | EACH | 2 | $185.00 | $175.00 | $100.00 | $175.00 | $165.00 |
| 162 | Relocate Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.31) | EACH | 12 | $565.00 | $500.00 | $300.00 | $520.00 | $500.00 |
| 163 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 1 | $150.00 | $575.00 | $200.00 | $140.00 | $132.00 |
| 164 | (647.83001002) | 2 | $95.00 | $290.00 | $150.00 | $90.00 | $83.00 | |
| 165 | Milled-In Audible Roadway Delineators (MIARDs) (649.01) | LF | 605 | $30.00 | $15.00 | $15.00 | $33.00 | $29.00 |
| 166 | (650.1011) | LF | 96 | $1,500.00 | $3,200.00 | $3,500.00 | $4,280.00 | $4,665.00 |
| 167 | (655.05010008) | 3 | $1,700.00 | $1,500.00 | $1,500.00 | $2,600.00 | $1,715.00 | |
| 168 | (655.05010010) | 3 | $2,250.00 | $750.00 | $500.00 | $2,600.00 | $1,300.00 | |
| 169 | Manhole Frame & Cover (655.1202) | EACH | 3 | $950.00 | $1,500.00 | $1,300.00 | $2,400.00 | $2,020.00 |
| 170 | (658.50000008) | 2 | $6,500.00 | $4,000.00 | $5,000.00 | $8,900.00 | $4,800.00 | |
| 171 | (660.21160008) | 25 | $500.00 | $445.00 | $150.00 | $1,430.00 | $500.00 | |
| 172 | (663.0108) | LF | 65 | $225.00 | $140.00 | $150.00 | $500.00 | $1,300.00 |
| 173 | (663.0112) | LF | 120 | $225.00 | $150.00 | $210.00 | $525.00 | $800.00 |
| 174 | (663.1008) | EACH | 1 | $3,500.00 | $2,900.00 | $3,000.00 | $3,400.00 | $3,000.00 |
| 175 | (663.1012) | EACH | 3 | $5,500.00 | $5,400.00 | $5,000.00 | $5,900.00 | $5,100.00 |
| 176 | (663.1712) | EACH | 2 | $25,000 | $25,000 | $7,000.00 | $22,000 | $24,000 |
| 177 | Iron Water Main Fittings (3 - 8 inch diameter) (663.2001) | LB | 275 | $6.50 | $7.00 | $8.00 | $21.00 | $8.00 |
| 178 | Iron Water Main Fittings (10 - 16 inch diameter) (663.2002) | LB | 1,752 | $6.50 | $6.00 | $12.00 | $9.00 | $7.00 |
| 179 | (663.2308) | LF | 65 | $1.00 | $5.00 | $8.00 | $11.00 | $13.00 |
| 180 | (663.2312) | LF | 120 | $1.00 | $5.00 | $8.00 | $3.00 | $7.00 |
| 181 | (663.4108) | LF | 65 | $50.00 | $50.00 | $75.00 | $190.00 | $211.00 |
| 182 | (663.4112) | LF | 110 | $50.00 | $30.00 | $75.00 | $120.00 | $190.00 |
| 183 | (664.40480006) | 19 | $700.00 | $750.00 | $250.00 | $3,100.00 | $1,600.00 | |
| 184 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 4,957 | $1.50 | $2.00 | $2.00 | $2.00 | $1.40 |
| 185 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 5,923 | $1.50 | $2.00 | $2.00 | $2.00 | $1.40 |
| 186 | Field Change Payment (FCP) (697.03) | DOL | 361,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 187 | Asphalt Price Adjustment (698.04) | DOL | 8,502 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 188 | Fuel Price Adjustment (698.05) | DOL | 2,476 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 189 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 190 | (698.93940001) | LS | 1 | $160,000 | $160,000 | $160,000 | $160,000 | $160,000 |
| 191 | (698.93940008) | LS | 1 | $375,000 | $375,000 | $375,000 | $375,000 | $375,000 |
| 192 | Mobilization (699.040001) | LS | 1 | $512,399 | $520,000 | $556,360 | $630,000 | $650,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of February 27, 2025. Compiled by Mirage Metrics.