Low bidders on NYSDOT contracts carried a median of $1,793.58 per EACH for this item, over the 24 months to 15 OCT 2026, across 18 low bids. Half of all 72 bids fell between $1,500.00 and $2,212.50.

Owner
New York State DOT
Item
655.1103
Unit
EACH
Data through
15 OCT 2026
$1,793.58Low bidder's median, per EACH
$1,743.58Median of all bids, per EACH
18Contracts in the window

By year of letting

Welded Frame & Reticuline Grate 3, NYSDOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
202288$1,200.0023$1,200.00
202377$1,400.0031$1,400.00
202477$1,200.0024$1,275.00
20251111$1,700.0048$1,653.50
202677$1,900.0024$1,850.00

Bid prices as published, not adjusted for inflation.

By region

RegionLow bidsLow-bid medianAll bidsMedian, all bids
Region 0510$1,650.0040$1,666.00
Region 083$2,200.0016$1,760.42
Welded Frame & Reticuline Grate 3, NYSDOT: unit prices by region, last 24 months

Regions with at least three low bids, over the last 24 months.

By quantity

Quantity (EACH)Low bidsLow-bid median
1 to 14$1,660.42
2 to 35$1,900.00
3 to 94$1,725.00
12 to 155$1,700.00
Welded Frame & Reticuline Grate 3, NYSDOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

Welded Frame & Reticuline Grate 3, NYSDOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractRegionQuantityLow bidder's priceMedianBidsLow bidderSource
01 OCT 2026D265850Region 051$1,250.88$1,650.003Lake Shore Paving IncNYSDOT
07 MAY 2026D265753Region 093$924.00$1,237.502Lancaster Development and Tully Construction Co LLCNYSDOT
12 MAR 2026D265690Region 0513$1,900.00$1,700.004Union Concrete & Construction CorpNYSDOT
12 MAR 2026D265726Region 071$1,800.00$2,050.003Slate Hill Constructors IncNYSDOT
05 FEB 2026D265609Region 052$1,900.00$1,850.004D&H Paving LLCNYSDOT
05 FEB 2026D265692Region 072$2,367.79$2,406.574Tadcon Electric LLCNYSDOT
22 JAN 2026D265529Region 089$2,200.00$1,850.004Verde Electric Maintenance CorpNYSDOT
25 SEP 2025D265566Region 052$2,300.00$1,674.004Millennium Construction IncNYSDOT
24 JUL 2025D265506Region 054$1,250.00$1,250.003Concrete Applied Technologies Corp/DBA:CatcoNYSDOT
26 JUN 2025D265504Region 0515$1,600.00$1,641.004Union Concrete & Construction CorpNYSDOT
22 MAY 2025D265494Region 0512$1,700.00$1,570.005McLaughlin Construction Corp/DBA Edbauer ConstructionNYSDOT
24 APR 2025D265481Region 061$1,893.60$1,840.005Bothar Construction LLCNYSDOT
27 MAR 2025D265461Region 052$1,500.00$1,850.003Concrete Applied Technologies Corp/DBA:CatcoNYSDOT
20 MAR 2025D265478Region 035$2,570.00$2,097.502Salt City Constructors LLCNYSDOT
13 MAR 2025D265463Region 0815$3,000.00$1,400.007Morano Brothers CorpNYSDOT
Latest NYSDOT contracts carrying Welded Frame & Reticuline Grate 3

Filter this item by your own quantity, region and period, or check your price against it, in the NYSDOT explorer.

How these prices were read

NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are NYSDOT's own: this item is compared with NYSDOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the NYSDOT letting of 15 OCT 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.