NYSDOT contract D265566 bid tabulation
ADA Compliance and Pedestrian Signal Upgrades. Let by New York State DOT on September 25, 2025, Cattaraugus, Chautauqua, Region 05. 4 bids received; low bid $1,533,178 by Millennium Construction Inc.
- Owner
- New York State DOT
- Letting
- 25 SEP 2025
- Pay items
- 112
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Millennium Construction Inc | $1,533,178 | Low |
| 2 | Concrete Applied Technologies Corp/DBA:Catco | $1,676,779 | +9.0% |
| 3 | Bella Concrete Solutions LLC | $1,819,143 | +19% |
| 4 | Lake Shore Paving Inc | $1,959,199 | +28% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Millennium Construction Inc | 2. Concrete Applied Technologies Corp/DBA:Catco | 3. Bella Concrete Solutions LLC | 4. Lake Shore Paving Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $5,000.00 | $5,000.00 | $3,000.00 | $2,800.00 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 55 | $125.00 | $175.00 | $150.00 | $272.00 |
| 3 | Select Granular Fill (203.07) | CY | 35 | $150.00 | $150.00 | $100.00 | $123.30 |
| 4 | Trench and Culvert Excavation (206.0201) | CY | 71 | $75.00 | $150.00 | $100.00 | $70.25 |
| 5 | (206.03050005) | 88 | $185.00 | $150.00 | $150.00 | $122.60 | |
| 6 | (206.03060005) | 151 | $72.00 | $50.00 | $50.00 | $72.45 | |
| 7 | Test Pit Excavation (206.05) | EACH | 4 | $1.00 | $2,500.00 | $3,500.00 | $1,058.70 |
| 8 | (304.15010005) | 54 | $150.00 | $150.00 | $125.00 | $222.35 | |
| 9 | (404.0001) | TON | 3 | $100.00 | $100.00 | $100.00 | $100.00 |
| 10 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 1 | $100.00 | $100.00 | $100.00 | $100.00 |
| 11 | (404.1989) | TON | 14 | $300.00 | $300.00 | $500.00 | $271.50 |
| 12 | (404.3789) | TON | 27 | $300.00 | $300.00 | $600.00 | $272.60 |
| 13 | Diluted Tack Coat (407.0102) | GAL | 7 | $1.00 | $50.00 | $1.00 | $76.25 |
| 14 | Shields and Shoring (552.17) | SF | 268 | $3.00 | $2.00 | $10.00 | $3.50 |
| 15 | (553.030001) | EACH | 1 | $1.00 | $2,500.00 | $4,000.00 | $678.10 |
| 16 | Concrete Collars (603.77) | EACH | 1 | $1,500.00 | $2,000.00 | $600.00 | $2,020.00 |
| 17 | (603.9812) | LF | 80 | $95.00 | $75.00 | $200.00 | $26.85 |
| 18 | (604.070501) | EACH | 3 | $1,500.00 | $2,500.00 | $1,000.00 | $2,910.00 |
| 19 | (604.070502) | EACH | 1 | $1,500.00 | $5,000.00 | $1,500.00 | $2,995.50 |
| 20 | (604.070503) | EACH | 1 | $1,500.00 | $3,000.00 | $1,000.00 | $1,463.80 |
| 21 | (604.500501) | LF | 9.40 | $2,000.00 | $1,000.00 | $800.00 | $1,132.20 |
| 22 | (607.97000008) | 14 | $100.00 | $270.00 | $300.00 | $1.00 | |
| 23 | Concrete Sidewalks and Driveways (608.0101) | CY | 8 | $1,200.00 | $1,200.00 | $2,500.00 | $1,310.00 |
| 24 | (608.01060415) | 5,446 | $35.00 | $33.00 | $46.39 | $42.25 | |
| 25 | (608.01070415) | 9,794 | $35.00 | $40.00 | $46.39 | $53.00 | |
| 26 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 3 | $500.00 | $1,500.00 | $1,000.00 | $1,308.60 |
| 27 | (608.03040008) | 17.50 | $300.00 | $230.00 | $500.00 | $246.35 | |
| 28 | (608.21000003) | 26.40 | $500.00 | $10.00 | $2,250.00 | $378.70 | |
| 29 | (609.10010109) | 1,473 | $115.00 | $150.00 | $100.00 | $173.10 | |
| 30 | (609.10010309) | 104 | $290.00 | $250.00 | $180.00 | $304.50 | |
| 31 | Mulch for Planting Type A, B & D Wood Chips and Shredded Bark (610.1101) | CY | 1 | $100.00 | $468.00 | $1,000.00 | $473.58 |
| 32 | Topsoil - Roadside (610.1402) | CY | 9 | $150.00 | $1,738.00 | $150.00 | $1,760.60 |
| 33 | Turf Establishment - Roadside (610.1601) | SY | 15 | $10.00 | $171.00 | $200.00 | $172.75 |
| 34 | Turf Establishment -Lawns (610.1602) | SY | 41 | $10.00 | $171.00 | $200.00 | $172.75 |
| 35 | (611.0452) | EACH | 4 | $180.00 | $479.00 | $300.00 | $484.75 |
| 36 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $125,000 | $169,600 | $60,000 | $65,089 |
| 37 | Type III Construction Barricades (619.04) | EACH | 8 | $1.00 | $250.00 | $1.00 | $348.30 |
| 38 | (619.080102) | LF | 914 | $2.10 | $1.93 | $1.75 | $1.95 |
| 39 | (619.100101) | LF | 6,222 | $0.01 | $0.83 | $0.75 | $0.85 |
| 40 | Maintain Traffic Signal Equipment (Requirement A) Intersection (619.1611) | MONTH | 36 | $160.00 | $10.00 | $100.00 | $222.90 |
| 41 | Survey Operations (625.01) | LS | 1 | $25,000 | $23,400 | $20,000 | $67,100 |
| 42 | (625.09010015) | LS | 1 | $1.00 | $1.00 | $6,000.00 | $1,118.35 |
| 43 | (627.50140008) | 307 | $10.00 | $8.00 | $15.00 | $10.00 | |
| 44 | (635.01030011) | 3,720 | $1.80 | $1.65 | $1.50 | $1.70 | |
| 45 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $1.00 | $100.00 | $500.00 | $3,030.00 |
| 46 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 18 | $450.00 | $100.00 | $3,400.00 | $3,697.00 |
| 47 | Office Technology and Supplies (637.34) | DOL | 500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 48 | White Paint Reflectorized Pavement Stripes – 20 mils (640.20) | LF | 68 | $27.00 | $25.00 | $22.60 | $24.65 |
| 49 | Ground-Mounted Sign Panels without Z-bars (645.5101) | SF | 3 | $45.00 | $41.00 | $42.00 | $41.25 |
| 50 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 323 | $60.00 | $54.00 | $63.57 | $54.60 |
| 51 | Type A Sign Posts (645.81) | EACH | 67 | $300.00 | $273.00 | $205.00 | $276.35 |
| 52 | (645.81090003) | 51 | $135.00 | $125.00 | $75.00 | $125.95 | |
| 53 | Flexible Delineator, Single Unit, One Way (646.40) | EACH | 7 | $110.00 | $319.00 | $135.00 | $323.15 |
| 54 | Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51) | EACH | 38 | $35.00 | $31.00 | $55.00 | $31.20 |
| 55 | Welded Frame & Reticuline Grate 3 (655.1103) | EACH | 2 | $2,300.00 | $1,300.00 | $1,500.00 | $1,848.00 |
| 56 | Manhole Frame & Cover (655.1202) | EACH | 1 | $1,400.00 | $1,300.00 | $1,500.00 | $1,605.60 |
| 57 | (660.65000101) | 4 | $2,000.00 | $1,200.00 | $300.00 | $493.00 | |
| 58 | (662.60000108) | 2,500 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 59 | Adjust Existing Valve Box Elevation (663.33) | EACH | 3 | $400.00 | $800.00 | $100.00 | $330.00 |
| 60 | Adjust Existing Hydrant Elevation (663.34) | EACH | 1 | $2,500.00 | $5,000.00 | $5,000.00 | $2,463.00 |
| 61 | (670.14480010) | 3 | $1,000.00 | $400.00 | $1,000.00 | $493.00 | |
| 62 | Breakaway Transformer Base (Aluminum) (670.19) | EACH | 2 | $1,000.00 | $1,300.00 | $1,500.00 | $1,170.00 |
| 63 | (680.11130814) | 2 | $10,000 | $8,700.00 | $10,752 | $14,726 | |
| 64 | (680.11131014) | 6 | $8,000.00 | $8,900.00 | $8,477.00 | $10,424 | |
| 65 | Pole Excavation and Concrete Foundation (680.5001) | CY | 3 | $3,500.00 | $3,100.00 | $2,500.00 | $5,660.65 |
| 66 | (680.50500005) | 5 | $500.00 | $500.00 | $350.00 | $668.60 | |
| 67 | (680.510301) | EACH | 5 | $2,500.00 | $2,700.00 | $2,500.00 | $2,395.75 |
| 68 | (680.520506) | LF | 108 | $16.00 | $20.00 | $15.00 | $17.85 |
| 69 | (680.520508) | LF | 264 | $16.50 | $25.00 | $20.00 | $24.50 |
| 70 | Single Span Wire Assembly (680.7001) | EACH | 2 | $2,400.00 | $4,000.00 | $3,000.00 | $3,231.50 |
| 71 | Dual Span Wire Assembly with Lower Tether Wire (680.7003) | EACH | 1 | $4,650.00 | $4,500.00 | $5,500.00 | $4,345.80 |
| 72 | Riser Assembly, 1-inch Diameter (680.700603) | EACH | 1 | $1,650.00 | $1,300.00 | $2,000.00 | $1,615.75 |
| 73 | (680.730514) | LF | 3,632 | $3.80 | $5.25 | $5.25 | $5.60 |
| 74 | (680.730714) | LF | 533 | $7.10 | $8.00 | $5.75 | $6.60 |
| 75 | (680.77000105) | 1 | $1,500.00 | $3,000.00 | $6,000.00 | $5,460.00 | |
| 76 | (680.77000205) | 1 | $1,500.00 | $3,000.00 | $6,000.00 | $5,460.00 | |
| 77 | (680.77000305) | 1 | $1,500.00 | $3,000.00 | $6,000.00 | $5,460.00 | |
| 78 | (680.78010005) | 6 | $220.00 | $1,000.00 | $500.00 | $668.60 | |
| 79 | (680.79000105) | 1 | $2,850.00 | $3,000.00 | $6,000.00 | $5,683.00 | |
| 80 | (680.79000205) | 1 | $2,850.00 | $3,000.00 | $6,000.00 | $5,683.00 | |
| 81 | (680.79000305) | 1 | $2,850.00 | $3,000.00 | $6,000.00 | $5,683.00 | |
| 82 | (680.80620215) | 1 | $6,200.00 | $3,500.00 | $6,000.00 | $2,061.50 | |
| 83 | Traffic Signal Module - 12-inch, Red Ball, LED (680.810101) | EACH | 22 | $69.00 | $160.00 | $235.00 | $139.30 |
| 84 | Traffic Signal Module - 12-inch, Yellow Ball, LED (680.810103) | EACH | 22 | $70.00 | $180.00 | $235.00 | $156.00 |
| 85 | Traffic Signal Module - 12-inch, Yellow Arrow, LED (680.810104) | EACH | 4 | $90.00 | $160.00 | $265.00 | $161.60 |
| 86 | Traffic Signal Module - 12-inch, Green Ball, LED (680.810105) | EACH | 22 | $85.00 | $180.00 | $235.00 | $167.15 |
| 87 | Traffic Signal Module - 12-inch, Green Arrow, LED (680.810106) | EACH | 4 | $90.00 | $160.00 | $260.00 | $172.75 |
| 88 | Traffic Signal Section - Aluminum Type I, 12-inch (680.810107) | EACH | 74 | $140.00 | $170.00 | $350.00 | $234.00 |
| 89 | Traffic Signal Bracket Assembly - 1 Way (680.8111) | EACH | 22 | $270.00 | $375.00 | $475.00 | $501.50 |
| 90 | Traffic Signal Disconnect Hanger (680.8120) | EACH | 22 | $1,200.00 | $520.00 | $625.00 | $663.00 |
| 91 | Pedestrian Signal Module - 12-inch, Bi-Modal Hand/Man Symbols, LED (680.813105) | EACH | 3 | $165.00 | $260.00 | $315.00 | $278.60 |
| 92 | Pedestrian Signal Section - Polycarbonate, Type I, 12-inch (680.813106) | EACH | 6 | $200.00 | $240.00 | $390.00 | $312.00 |
| 93 | Pedestrian Signal Bracket Mount Assembly (680.8141) | EACH | 2 | $240.00 | $350.00 | $475.00 | $445.75 |
| 94 | Pedestrian Signal Post Top Mount Assembly (680.8142) | EACH | 1 | $210.00 | $500.00 | $465.00 | $418.00 |
| 95 | Pedestrian Signal Module - 12-inch Countdown Timer, LED (680.815001) | EACH | 3 | $210.00 | $260.00 | $315.00 | $306.45 |
| 96 | (680.8151) | EACH | 3 | $2,000.00 | $1,100.00 | $2,020.00 | $1,331.60 |
| 97 | (680.8205) | EACH | 4 | $1,200.00 | $1,000.00 | $1,000.00 | $947.15 |
| 98 | (680.82250801) | 1 | $1,200.00 | $500.00 | $450.00 | $835.75 | |
| 99 | (680.82254110) | 1 | $15,000 | $11,500 | $22,301 | $14,375 | |
| 100 | (680.82254210) | 1 | $15,000 | $11,500 | $22,301 | $14,375 | |
| 101 | (680.83010005) | 518 | $11.50 | $1.00 | $5.00 | $4.95 | |
| 102 | Meter Pan (680.9402) | EACH | 1 | $1,125.00 | $1,100.00 | $1,000.00 | $1,950.00 |
| 103 | Install Electrical Disconnect/Generator Transfer Switch (680.9499) | EACH | 1 | $1,250.00 | $750.00 | $1,000.00 | $1,504.30 |
| 104 | (680.950106) | LF | 186 | $18.50 | $4.00 | $5.00 | $4.50 |
| 105 | Performance Concrete Quality Adjustment (680.99) | QUALITY UNIT | 1 | $10.00 | $10.00 | $10.00 | $10.00 |
| 106 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 112 | $4.75 | $4.35 | $3.95 | $4.40 |
| 107 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 5,126 | $4.75 | $4.35 | $4.95 | $4.40 |
| 108 | Field Change Payment (FCP) (697.03) | DOL | 70,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 109 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 110 | Fuel Price Adjustment (698.05) | DOL | 604 | $1.00 | $1.00 | $1.00 | $1.00 |
| 111 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 112 | Mobilization (699.040001) | LS | 1 | $58,501 | $61,000 | $69,967 | $58,500 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of September 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.