Lake Shore Paving Inc: NYSDOT bid record
Lake Shore Paving Inc submitted 21 bids on New York State DOT contracts in the data, from 19 MAY 2022 to 15 OCT 2026, and was the low bidder on 6 of them (29%). When it was not low, its total sat a median +6.0% above the low bid.
- Owner
- New York State DOT
- Low bid volume
- $15,367,087
- Latest bid
- 15 OCT 2026
- Data through
- 15 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2022 | 3 | 1 | 33% |
| 2023 | 2 | 1 | 50% |
| 2024 | 6 | 2 | 33% |
| 2025 | 6 | 1 | 17% |
| 2026 | 4 | 1 | 25% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Field Change Payment (FCP) | 697.03 | DOL | 21 | 21 (100%) | $1.00 | $1.00 |
| Fuel Price Adjustment | 698.05 | DOL | 21 | 21 (100%) | $1.00 | $1.00 |
| Steel/Iron Price Adjustment | 698.06 | DOL | 21 | 21 (100%) | $1.00 | $1.00 |
| Asphalt Price Adjustment | 698.04 | DOL | 21 | 21 (100%) | $1.00 | $1.00 |
| Office Technology and Supplies | 637.34 | DOL | 20 | 20 (100%) | $1.00 | $1.00 |
| Unclassified Excavation and Disposal | 203.02 | CY | 18 | 11 (61%) | $34.67 | $71.00 |
| 404.0001 | TON | 9 | 9 (100%) | $100.00 | $95.00 | |
| Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips | 608.020102 | TON | 18 | 8 (44%) | $265.78 | $307.93 |
| Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips | 608.000013 | QUALITY UNIT | 8 | 8 (100%) | $90.00 | $90.00 |
| Pavement Density Quality Adjustment to Asphalt Items | 404.0002 | QUALITY UNIT | 8 | 8 (100%) | $100.00 | $110.00 |
| 404.3789 | TON | 10 | 7 (70%) | $187.90 | $175.00 | |
| Permanent Survey Markers | 625.06 | EACH | 9 | 7 (78%) | $442.86 | $1,500.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| McLaughlin Construction Corp/DBA Edbauer Construction | 16 | 5 of 16 |
| Concrete Applied Technologies Corp/DBA:Catco | 14 | 6 of 14 |
| D&H Excavating Inc | 10 | 3 of 10 |
| Union Concrete & Construction Corp | 6 | 5 of 6 |
| Oakgrove Construction Inc | 6 | 4 of 6 |
| Cold Spring Construction Company | 5 | 1 of 5 |
| The L C Whitford Co Inc | 3 | 1 of 3 |
| Millennium Construction Inc | 3 | 2 of 3 |
| Amherst Paving Inc | 2 | 1 of 2 |
| H&K Services Inc | 1 | 0 of 1 |
Latest bids
| Let | Contract | Region | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 15 OCT 2026 | D265838 | Region 05 | Guiderail Replacement Project; US-62 | 2 of 3 | $1,385,382 | +4.0% |
| 01 OCT 2026 | D265850 | Region 05 | NY Route 474 ADA & Pedestrian Improvements; Town of Clymer | 1 of 3 | $2,245,147 | Low, 3.0% under the second |
| 21 MAY 2026 | D265798 | Region 05 | Highway Rehabilitation - NY 394 | 2 of 2 | $3,945,030 | +6.0% |
| 12 MAR 2026 | D265759 | Region 05 | NY-280; Highway Rehabilitation & Drainage Improvement | 2 of 4 | $8,981,482 | +4.0% |
| 20 NOV 2025 | D265603 | Region 05 | HIGHWAY RESURFACING; I-86, Southern Tier Expressway; SNI | 3 of 6 | $5,915,817 | +6.0% |
| 23 OCT 2025 | D265576 | Region 05 | Small Culvert Replacements -NY Route 950A | 3 of 6 | $1,696,232 | +45% |
| 25 SEP 2025 | D265566 | Region 05 | ADA Compliance and Pedestrian Signal Upgrades | 4 of 4 | $1,959,199 | +28% |
| 21 AUG 2025 | D265547 | Region 05 | SAFETY IMPROVEMENTS - US Route 20, NY Routes 5 & 952H | 2 of 5 | $5,747,286 | +2.0% |
| 24 JUL 2025 | D265506 | Region 05 | NY394-Mill & Resurfacing ADA Signal & Drainage Improvements | 2 of 3 | $7,135,768 | 0.0% |
| 09 JAN 2025 | D265408 | Region 05 | Pavement Resurfacing with Safety and Improvements | 1 of 6 | $3,957,619 | Low, 6.0% under the second |
| 24 OCT 2024 | D265345 | Region 05 | HIGHWAY - ADA COMPLIANCE & SIGNAL UPGRADES | 3 of 3 | $622,551 | +45% |
| 25 JUL 2024 | D265293 | Region 05 | NY 280 (BRIDGE & LARGE CULVERTS) - SNI; CATT CO | 1 of 6 | $3,800,520 | Low, 36% under the second |
| 20 JUN 2024 | D265259 | Region 05 | SAFETY IMPROVEMENT ON US ROUTE 20 AND NY ROUTE 5 | 1 of 4 | $4,281,582 | Low, 8.0% under the second |
| 23 MAY 2024 | D265249 | Region 05 | Large Culvert Replacements and Rehabilitations | 2 of 2 | $5,369,500 | +3.0% |
| 14 MAR 2024 | D265223 | Region 05 | Small Culvert Rehabilitations and Replacements | 2 of 5 | $4,397,758 | +5.0% |
| 14 MAR 2024 | D265224 | Region 05 | NY 438 PMI; SNI | 5 of 7 | $4,706,048 | +7.0% |
| 12 OCT 2023 | D265110 | Region 05 | NY Rte 280 - I86 to Quaker Lake - Highway Maintenance | 5 of 5 | $5,559,701 | +9.0% |
| 14 SEP 2023 | D265085 | Region 05 | HIGHWAY - REHAB/IMPROVEMENT - ADA Various Locations | 1 of 3 | $399,453 | Low, 25% under the second |
| 17 NOV 2022 | D264917 | Region 05 | NY Route 5, Barcelona Retaining Wall | 1 of 5 | $682,765 | Low, 0.0% under the second |
| 07 JUL 2022 | D264815 | Region 05 | LARGE CULVERT REPLACEMENT AND REHABILITATIONS NYSDOT R-5 | 5 of 5 | $3,604,811 | +28% |
| 19 MAY 2022 | D264800 | Region 05 | Retention Pond Maintenance in the Town of Salamanca. | 3 of 5 | $396,424 | +28% |
How this record was read
NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
- Every bid counted here matched its published total to within one dollar; NYSDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.