NYSDOT contract D265603 bid tabulation
HIGHWAY RESURFACING; I-86, Southern Tier Expressway; SNI. Let by New York State DOT on November 20, 2025, Cattaraugus, Region 05. 6 bids received; low bid $5,562,375 by D&H Excavating Inc.
- Owner
- New York State DOT
- Letting
- 20 NOV 2025
- Pay items
- 55
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D&H Excavating Inc | $5,562,375 | Low |
| 2 | Oakgrove Construction Inc | $5,696,070 | +2.0% |
| 3 | Lake Shore Paving Inc | $5,915,817 | +6.0% |
| 4 | Amherst Paving Inc | $5,979,623 | +8.0% |
| 5 | Concrete Applied Technologies Corp/DBA:Catco | $5,990,586 | +8.0% |
| 6 | Cold Spring Construction Company | $7,201,799 | +29% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D&H Excavating Inc | 2. Oakgrove Construction Inc | 3. Lake Shore Paving Inc | 4. Amherst Paving Inc | 5. Concrete Applied Technologies Corp/DBA:Catco | 6. Cold Spring Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $4,353.13 | $2,500.00 | $7,960.00 | $4,100.00 | $2,500.00 | $7,500.00 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 93 | $150.00 | $80.00 | $57.45 | $74.00 | $150.00 | $320.00 |
| 3 | (203.24010017) | 443 | $1.00 | $50.00 | $81.15 | $66.00 | $125.00 | $170.00 | |
| 4 | (304.15200005) | 62 | $240.00 | $150.00 | $201.00 | $110.00 | $175.00 | $380.00 | |
| 5 | (404.0001) | TON | 1,182 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 6 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 1,182 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 7 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 536 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 8 | (404.0952) | TON | 23,569 | $111.00 | $95.00 | $109.00 | $105.00 | $105.00 | $110.00 |
| 9 | (404.0982) | TON | 52 | $300.00 | $150.00 | $307.45 | $145.00 | $400.00 | $145.00 |
| 10 | (404.1989) | TON | 12 | $300.00 | $250.00 | $257.25 | $268.00 | $400.00 | $450.00 |
| 11 | (404.3789) | TON | 29 | $250.00 | $200.00 | $326.50 | $200.00 | $400.00 | $450.00 |
| 12 | Diluted Tack Coat (407.0102) | GAL | 27,934 | $5.40 | $4.00 | $5.45 | $4.50 | $4.50 | $5.50 |
| 13 | (407.01120007) | 5,302 | $5.25 | $6.00 | $4.85 | $4.50 | $4.50 | $6.00 | |
| 14 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 144,070 | $0.35 | $0.25 | $0.29 | $0.45 | $0.35 | $0.60 |
| 15 | Production Cold-Mill Surface Planing of Bituminous Concrete (490.15) | SY | 280,194 | $1.57 | $1.50 | $1.50 | $1.85 | $1.50 | $2.90 |
| 16 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 639 | $18.00 | $10.00 | $15.90 | $32.00 | $20.00 | $5.50 |
| 17 | (608.01070415) | 390 | $50.00 | $75.00 | $97.75 | $70.00 | $50.00 | $200.00 | |
| 18 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 19 | $250.00 | $350.00 | $285.00 | $260.00 | $375.00 | $350.00 |
| 19 | (608.21000003) | 6.60 | $650.00 | $550.00 | $375.00 | $585.00 | $600.00 | $450.00 | |
| 20 | (609.0401) | LF | 217 | $130.00 | $125.00 | $93.70 | $110.00 | $125.00 | $150.00 |
| 21 | (610.11040609) | 2 | $500.00 | $500.00 | $651.60 | $282.00 | $1,500.00 | $875.00 | |
| 22 | Topsoil - Roadside (610.1402) | CY | 14 | $250.00 | $100.00 | $220.00 | $160.00 | $200.00 | $250.00 |
| 23 | Turf Establishment -Lawns (610.1602) | SY | 81 | $20.00 | $2.00 | $5.65 | $15.00 | $10.00 | $11.00 |
| 24 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $85,000 | $503,000 | $227,150 | $275,000 | $150,000 | $550,000 |
| 25 | (619.0901) | LF | 169,767 | $0.22 | $0.35 | $0.21 | $0.25 | $0.21 | $0.20 |
| 26 | (619.111113) | EACH | 5 | $1,850.00 | $3,000.00 | $4,820.00 | $4,000.00 | $8,000.00 | $8,000.00 |
| 27 | Survey Operations (625.01) | LS | 1 | $6,500.00 | $2,500.00 | $25,000 | $20,000 | $20,000 | $5,000.00 |
| 28 | (627.50140008) | 230 | $1.00 | $5.00 | $4.55 | $10.00 | $11.00 | $7.50 | |
| 29 | Removal and Repair of Deteriorated Asphalt Pavement - Less than or equal to 4 Square Yards (633.1401) | SY | 2,800 | $15.00 | $45.00 | $49.30 | $50.00 | $80.00 | $95.00 |
| 30 | Removal and Repair of Deteriorated Asphalt Pavement – Greater than 4 Square Yards and less than 20 Square Yards (633.1402) | SY | 2,800 | $15.00 | $35.00 | $34.25 | $45.00 | $60.00 | $70.00 |
| 31 | Removal and Repair of Deteriorated Asphalt Pavement – 20 Square Yards or Greater (633.1403) | SY | 2,800 | $15.00 | $30.00 | $29.00 | $40.00 | $52.00 | $55.00 |
| 32 | (636.01000005) | 50,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 33 | (636.99990215) | LS | 1 | $264,875 | $271,241 | $281,706 | $284,744 | $285,266 | $342,943 |
| 34 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 14 | $2,100.00 | $2,000.00 | $2,700.00 | $2,000.00 | $2,500.00 | $2,500.00 |
| 35 | Office Technology and Supplies (637.34) | DOL | 500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 36 | White Paint Reflectorized Pavement Stripes – 15 mils (640.10) | LF | 146,516 | $0.20 | $0.25 | $0.21 | $0.25 | $0.21 | $0.20 |
| 37 | Yellow Paint Reflectorized Pavement Stripes - 15 mils (640.11) | LF | 108,135 | $0.20 | $0.25 | $0.21 | $0.25 | $0.21 | $0.20 |
| 38 | Ground-Mounted Sign Panels without Z-bars (645.5101) | SF | 854 | $35.00 | $25.00 | $26.00 | $36.00 | $36.00 | $32.00 |
| 39 | Reference Marker Panel (646.21) | EACH | 116 | $41.00 | $35.00 | $37.20 | $31.00 | $40.00 | $37.00 |
| 40 | Steel Post, 2.0 lb/ft (646.32) | EACH | 116 | $66.00 | $75.00 | $74.25 | $132.00 | $66.00 | $62.00 |
| 41 | Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41) | EACH | 116 | $8.00 | $15.00 | $16.90 | $60.00 | $8.00 | $7.25 |
| 42 | Milled-In Audible Roadway Delineators (MIARDs) (649.01) | LF | 65,175 | $0.50 | $0.50 | $0.45 | $0.46 | $0.46 | $0.44 |
| 43 | Pavement Ride Quality Adjustment to Asphalt Level 1 (653.1010) | QUALITY UNIT | 2,064 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 | $120.00 |
| 44 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 91,225 | $0.55 | $0.50 | $0.52 | $0.50 | $0.51 | $0.48 |
| 45 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 66,180 | $0.55 | $0.50 | $0.52 | $0.50 | $0.51 | $0.48 |
| 46 | (685.16010014) | 55,291 | $1.65 | $1.25 | $1.65 | $1.65 | $1.65 | $1.50 | |
| 47 | (685.17010014) | 41,955 | $1.65 | $1.25 | $1.65 | $1.65 | $1.65 | $1.50 | |
| 48 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 19,116 | $3.10 | $2.25 | $3.10 | $3.00 | $3.05 | $2.80 |
| 49 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 4 | $285.00 | $350.00 | $282.00 | $275.00 | $275.00 | $250.00 |
| 50 | (691.04000020) | 50,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 51 | Field Change Payment (FCP) (697.03) | DOL | 263,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 52 | Asphalt Price Adjustment (698.04) | DOL | 42,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 53 | Fuel Price Adjustment (698.05) | DOL | 6,200 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 54 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 55 | Mobilization (699.040001) | LS | 1 | $200,000 | $208,500 | $215,000 | $175,764 | $215,000 | $263,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of November 20, 2025. Compiled by Mirage Metrics.