NYSDOT contract D265547 bid tabulation
SAFETY IMPROVEMENTS - US Route 20, NY Routes 5 & 952H. Let by New York State DOT on August 21, 2025, Chautauqua, Region 05. 5 bids received; low bid $5,649,777 by D&H Excavating Inc.
- Owner
- New York State DOT
- Letting
- 21 AUG 2025
- Pay items
- 190
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | D&H Excavating Inc | $5,649,777 | Low |
| 2 | Lake Shore Paving Inc | $5,747,286 | +2.0% |
| 3 | Cold Spring Construction Company | $5,795,000 | +3.0% |
| 4 | Concrete Applied Technologies Corp/DBA:Catco | $5,951,484 | +5.0% |
| 5 | McLaughlin Construction Corp/DBA Edbauer Construction | $6,055,990 | +7.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D&H Excavating Inc | 2. Lake Shore Paving Inc | 3. Cold Spring Construction Company | 4. Concrete Applied Technologies Corp/DBA:Catco | 5. McLaughlin Construction Corp/DBA Edbauer Construction |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $26,000 | $11,999 | $35,000 | $20,000 | $40,000 |
| 2 | Unclassified Excavation and Disposal (203.02) | CY | 630 | $60.00 | $40.30 | $75.00 | $60.00 | $140.00 |
| 3 | Embankment In Place (203.03) | CY | 1,500 | $24.00 | $43.40 | $30.00 | $50.00 | $40.00 |
| 4 | Select Granular Fill (203.07) | CY | 320 | $64.00 | $98.76 | $90.00 | $90.00 | $90.00 |
| 5 | (203.24010017) | 8 | $150.00 | $208.85 | $250.00 | $200.00 | $75.00 | |
| 6 | Structure Excavation (206.01) | CY | 2,200 | $25.00 | $35.65 | $35.00 | $35.00 | $40.00 |
| 7 | Trench and Culvert Excavation (206.0201) | CY | 327 | $125.00 | $30.25 | $65.00 | $90.00 | $45.00 |
| 8 | (206.03050005) | 46 | $125.00 | $121.80 | $50.00 | $150.00 | $147.00 | |
| 9 | (206.03060005) | 147 | $80.00 | $77.50 | $50.00 | $80.00 | $50.00 | |
| 10 | Test Pit Excavation (206.05) | EACH | 14 | $750.00 | $1,064.45 | $1,500.00 | $2,000.00 | $2,000.00 |
| 11 | Geotextile Bedding (207.20) | SY | 310 | $8.00 | $3.10 | $5.00 | $8.50 | $5.00 |
| 12 | Prefabricated Composite Structural Drain (207.26) | SY | 48 | $42.00 | $46.91 | $20.00 | $40.00 | $20.00 |
| 13 | Seed and Mulch – Temporary (209.1003) | SY | 963 | $2.75 | $4.54 | $1.00 | $2.00 | $0.01 |
| 14 | (209.23010009) | 795 | $9.50 | $11.60 | $4.00 | $11.50 | $2.00 | |
| 15 | (304.15200005) | 447 | $102.00 | $119.28 | $75.00 | $135.00 | $95.00 | |
| 16 | (404.0001) | TON | 333 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 17 | Pavement Density Quality Adjustment to Asphalt Items (404.0002) | QUALITY UNIT | 1 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 18 | Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003) | QUALITY UNIT | 132 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 19 | (404.0962) | TON | 5,592 | $112.00 | $116.15 | $125.00 | $116.00 | $123.00 |
| 20 | (404.0982) | TON | 482 | $260.00 | $193.28 | $200.00 | $275.00 | $419.00 |
| 21 | (404.1989) | TON | 99 | $320.00 | $255.34 | $190.00 | $250.00 | $388.00 |
| 22 | (404.3789) | TON | 221 | $235.00 | $174.96 | $180.00 | $250.00 | $300.00 |
| 23 | (404.4389) | TON | 110 | $215.00 | $180.06 | $190.00 | $250.00 | $240.00 |
| 24 | (404.4589) | TON | 140 | $200.00 | $159.61 | $180.00 | $230.00 | $212.00 |
| 25 | Diluted Tack Coat (407.0102) | GAL | 7,971 | $5.75 | $6.29 | $9.00 | $4.50 | $8.00 |
| 26 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 52,520 | $0.50 | $0.46 | $0.65 | $0.60 | $0.10 |
| 27 | Production Cold Milling of Bituminous Concrete (490.10) | SY | 69,079 | $1.85 | $2.67 | $1.25 | $2.75 | $3.30 |
| 28 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 5,200 | $12.00 | $14.12 | $8.00 | $13.00 | $18.00 |
| 29 | (520.09000010) | 161 | $30.00 | $5.85 | $8.00 | $8.00 | $20.00 | |
| 30 | (520.50000004) | 40 | $120.00 | $15.49 | $20.00 | $10.00 | $50.00 | |
| 31 | (552.2001) | LF | 300 | $1.00 | $69.34 | $160.00 | $1.00 | $2.00 |
| 32 | (552.2101) | LF | 60 | $1.00 | $900.26 | $825.00 | $1.00 | $2.00 |
| 33 | (552.2201) | LF | 300 | $1.00 | $152.38 | $250.00 | $580.00 | $340.00 |
| 34 | (552.230201) | SF | 970 | $1.00 | $41.97 | $30.00 | $1.00 | $2.00 |
| 35 | (553.030001) | EACH | 1 | $14,000 | $13,085 | $40,000 | $150.00 | $10.00 |
| 36 | (553.030002) | EACH | 1 | $14,000 | $13,085 | $40,000 | $150.00 | $10.00 |
| 37 | (554.3001) | SF | 200 | $69.00 | $110.26 | $85.00 | $91.00 | $85.00 |
| 38 | (595.50000018) | 3,660 | $5.75 | $2.92 | $6.00 | $6.00 | $8.00 | |
| 39 | (603.171316) | EACH | 7 | $585.00 | $939.11 | $1,000.00 | $400.00 | $525.00 |
| 40 | (603.171614) | EACH | 2 | $1,800.00 | $1,284.84 | $1,000.00 | $1,200.00 | $890.00 |
| 41 | (603.63070415) | 117 | $1,860.00 | $1,865.44 | $1,750.00 | $1,460.00 | $2,150.00 | |
| 42 | (603.64050515) | 84 | $1,950.00 | $1,799.28 | $1,500.00 | $1,260.00 | $2,230.00 | |
| 43 | (603.67000001) | 60 | $3,600.00 | $2,036.34 | $2,500.00 | $2,700.00 | $1,850.00 | |
| 44 | Concrete Collars (603.77) | EACH | 1 | $1.00 | $1,656.30 | $2,000.00 | $1,500.00 | $950.00 |
| 45 | (603.9818) | LF | 80 | $70.00 | $23.47 | $60.00 | $85.00 | $55.00 |
| 46 | (604.070501) | EACH | 49 | $2,075.00 | $2,774.14 | $4,000.00 | $2,600.00 | $3,053.00 |
| 47 | (604.070502) | EACH | 20 | $2,600.00 | $3,540.68 | $4,500.00 | $3,500.00 | $3,812.00 |
| 48 | (604.070503) | EACH | 7 | $4,800.00 | $6,707.22 | $5,750.00 | $4,500.00 | $4,307.00 |
| 49 | Prefabricated Adjustment Rings for Manholes (604.10) | EACH | 40 | $800.00 | $617.39 | $1,000.00 | $500.00 | $250.00 |
| 50 | Underdrain Filter, Type II (605.1001) | CY | 10 | $220.00 | $151.44 | $150.00 | $100.00 | $75.00 |
| 51 | (605.1702) | LF | 50 | $3.00 | $8.25 | $8.00 | $25.00 | $32.00 |
| 52 | Box Beam Guide Railing (606.10) | LF | 1,625 | $54.00 | $52.04 | $50.00 | $52.00 | $54.00 |
| 53 | Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002) | LF | 198 | $69.00 | $66.98 | $65.00 | $67.00 | $70.00 |
| 54 | Box Beam End Piece (606.120101) | EACH | 1 | $685.00 | $664.29 | $1,000.00 | $670.00 | $653.00 |
| 55 | Box Beam Guide Railing End Assembly Type I (606.120102) | EACH | 3 | $5,000.00 | $4,799.44 | $5,000.00 | $4,800.00 | $4,725.00 |
| 56 | Box Beam Guide Railing End Assembly Type IIA (606.120201) | EACH | 6 | $2,600.00 | $2,518.74 | $3,000.00 | $2,500.00 | $2,475.00 |
| 57 | Box Beam End Assembly Type III (606.1203) | EACH | 1 | $8,100.00 | $7,871.75 | $7,500.00 | $8,000.00 | $7,732.00 |
| 58 | HPBO (Mod.) Corrugated Beam Guide Railing End Terminal (Energy-Absorbing) (606.27) | EACH | 1 | $4,800.00 | $4,666.59 | $4,500.00 | $4,700.00 | $4,584.00 |
| 59 | HPBO (Mod.) Corrugated Beam Guide Railing (606.2701) | LF | 368 | $38.00 | $36.26 | $35.00 | $36.60 | $36.00 |
| 60 | Single-Slope Concrete Half Section Barrier (Optional) (606.3061) | LF | 40 | $290.00 | $94.10 | $150.00 | $260.00 | $210.00 |
| 61 | I-Beam Posts for Existing Box Beam Guide Railing (606.4809) | EACH | 48 | $140.00 | $132.86 | $125.00 | $134.00 | $130.00 |
| 62 | Resetting Box Beam Guide Railing (New Posts) (606.5348) | LF | 259 | $36.00 | $34.60 | $35.00 | $35.00 | $40.00 |
| 63 | Removing and Storing Box Beam Guide Railing (606.63) | LF | 312 | $7.00 | $15.45 | $10.00 | $12.00 | $5.00 |
| 64 | Removing and Storing Box Beam Guide Railing End Assembly (606.6920) | EACH | 8 | $525.00 | $751.20 | $1,500.00 | $730.00 | $364.00 |
| 65 | Removing and Disposing Corrugated Beam Guide Railing (606.71) | LF | 480 | $5.00 | $12.54 | $10.00 | $9.25 | $3.00 |
| 66 | Removing and Disposing Anchorage Units for Corrugated Beam Guide Railing and Median Barrier (606.7910) | EACH | 6 | $650.00 | $1,465.25 | $1,500.00 | $732.00 | $100.00 |
| 67 | Transition: HPBO (Mod.) Corrugated Beam Guide Railing to Single Slope Concrete Half Section Barrier (606.8903) | EACH | 1 | $5,100.00 | $4,865.88 | $11,000 | $17,000 | $13,354 |
| 68 | Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013) | QUALITY UNIT | 6 | $100.00 | $100.00 | $100.00 | $100.00 | $100.00 |
| 69 | Concrete Sidewalks and Driveways (608.0101) | CY | 7 | $1,450.00 | $1,155.25 | $2,000.00 | $1,700.00 | $1,540.00 |
| 70 | (608.01060415) | 3,754 | $35.00 | $36.63 | $42.00 | $30.00 | $38.00 | |
| 71 | (608.01060615) | 277 | $60.00 | $54.50 | $65.00 | $40.00 | $44.00 | |
| 72 | (608.01070415) | 11,519 | $55.00 | $38.86 | $42.00 | $45.00 | $46.00 | |
| 73 | (608.01070615) | 371 | $70.00 | $47.71 | $65.00 | $60.00 | $50.00 | |
| 74 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 189 | $300.00 | $309.94 | $225.00 | $225.00 | $234.00 |
| 75 | (608.10080008) | 846 | $45.00 | $13.57 | $55.00 | $40.00 | $10.00 | |
| 76 | (608.21000003) | 18 | $670.00 | $496.74 | $400.00 | $600.00 | $636.00 | |
| 77 | (609.0401) | LF | 209 | $148.00 | $124.29 | $120.00 | $140.00 | $120.00 |
| 78 | (609.0407) | LF | 123 | $146.00 | $142.05 | $120.00 | $140.00 | $124.00 |
| 79 | (609.10010109) | 981 | $156.00 | $191.87 | $120.00 | $135.00 | $154.00 | |
| 80 | (609.15000008) | 12 | $220.00 | $206.50 | $80.00 | $100.00 | $95.00 | |
| 81 | (609.15100002) | 40 | $30.00 | $63.05 | $30.00 | $45.00 | $22.00 | |
| 82 | Compost (610.10) | CY | 17 | $165.00 | $219.21 | $200.00 | $220.00 | $60.00 |
| 83 | Topsoil - Roadside (610.1402) | CY | 222 | $85.00 | $160.54 | $150.00 | $145.00 | $75.00 |
| 84 | Turf Establishment -Lawns (610.1602) | SY | 1,963 | $4.50 | $4.54 | $4.25 | $4.50 | $0.01 |
| 85 | Watering Vegetation (610.19) | 1,000 GALLONS | 32 | $1.00 | $135.07 | $125.00 | $100.00 | $10.00 |
| 86 | (611.0151) | EACH | 18 | $1,300.00 | $1,478.03 | $1,400.00 | $1,500.00 | $1,150.00 |
| 87 | (611.0291) | EACH | 12 | $1,300.00 | $1,367.31 | $1,300.00 | $1,400.00 | $1,100.00 |
| 88 | (611.0351) | EACH | 3 | $750.00 | $1,135.92 | $1,050.00 | $1,150.00 | $765.00 |
| 89 | Portable Drip Irrigation System (611.17) | EACH | 33 | $82.00 | $79.71 | $75.00 | $80.00 | $110.00 |
| 90 | (611.19010024) | 18 | $60.00 | $354.28 | $325.00 | $357.00 | $100.00 | |
| 91 | (611.19020024) | 12 | $60.00 | $321.07 | $300.00 | $323.00 | $100.00 | |
| 92 | (611.19030024) | 3 | $60.00 | $243.57 | $225.00 | $245.00 | $100.00 | |
| 93 | (613.04000001) | 47 | $340.00 | $132.03 | $50.00 | $125.00 | $74.00 | |
| 94 | (614.060102) | EACH | 12 | $425.00 | $553.57 | $500.00 | $600.00 | $435.00 |
| 95 | (614.060104) | EACH | 6 | $475.00 | $553.57 | $650.00 | $800.00 | $488.00 |
| 96 | (614.060202) | EACH | 7 | $700.00 | $1,107.14 | $750.00 | $1,200.00 | $650.00 |
| 97 | (614.060204) | EACH | 4 | $750.00 | $1,107.14 | $1,000.00 | $1,200.00 | $702.00 |
| 98 | (614.060302) | EACH | 10 | $750.00 | $1,328.57 | $1,200.00 | $1,700.00 | $760.00 |
| 99 | (614.060402) | EACH | 2 | $800.00 | $1,771.42 | $1,600.00 | $2,200.00 | $812.00 |
| 100 | (614.060602) | EACH | 4 | $2,200.00 | $2,767.84 | $3,750.00 | $2,400.00 | $2,170.00 |
| 101 | (614.060704) | EACH | 1 | $3,200.00 | $4,428.55 | $6,000.00 | $4,500.00 | $3,258.00 |
| 102 | (617.10000024) | 25 | $80.00 | $47.03 | $25.00 | $115.00 | $25.00 | |
| 103 | (617.11000024) | LS | 1 | $600.00 | $308.41 | $250.00 | $2,500.00 | $100.00 |
| 104 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $92,000 | $221,998 | $110,000 | $310,000 | $400,539 |
| 105 | Type III Construction Barricades (619.04) | EACH | 9 | $75.00 | $365.98 | $125.00 | $250.00 | $200.00 |
| 106 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 2,240 | $9.00 | $5.54 | $4.25 | $8.75 | $1.00 |
| 107 | (619.0901) | LF | 41,650 | $0.35 | $0.32 | $0.30 | $0.33 | $0.32 |
| 108 | (619.0903) | LF | 6,270 | $9.00 | $5.54 | $4.25 | $0.01 | $1.00 |
| 109 | (619.111113) | EACH | 6 | $9,500.00 | $10,629 | $8,000.00 | $10,000 | $10,000 |
| 110 | (619.130101) | EACH | 1 | $26,000 | $54,250 | $65,000 | $50,000 | $70,000 |
| 111 | (619.130102) | EACH | 1 | $31,000 | $45,393 | $65,000 | $40,000 | $70,000 |
| 112 | Maintain Traffic Signal Equipment (Requirement A) Intersection (619.1611) | MONTH | 12 | $175.00 | $166.07 | $250.00 | $400.00 | $50.00 |
| 113 | Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716) | LF | 1,700 | $50.00 | $58.71 | $35.00 | $40.00 | $22.00 |
| 114 | Temporary Impact Attenuator - Redirective (Test Level 3) (619.1803) | EACH | 1 | $9,000.00 | $15,785 | $5,000.00 | $10,500 | $7,500.00 |
| 115 | Pavement Patching (Tonnage) (619.2602) | TON | 22 | $1,250.00 | $357.23 | $450.00 | $1,500.00 | $250.00 |
| 116 | Stone Filling (Medium) (620.04) | CY | 110 | $185.00 | $288.28 | $230.00 | $240.00 | $110.00 |
| 117 | Bedding Material, Type 1 (620.0801) | CY | 51 | $170.00 | $293.74 | $150.00 | $100.00 | $110.00 |
| 118 | Cleaning Culverts with Span of 50 in. or Less (621.01) | LF | 91 | $40.00 | $21.05 | $35.00 | $33.50 | $32.00 |
| 119 | Cleaning Closed Drainage Systems (621.03) | LF | 14,720 | $2.00 | $3.54 | $4.00 | $4.00 | $4.00 |
| 120 | Cleaning Drainage Structures (621.04) | EACH | 98 | $150.00 | $354.88 | $200.00 | $200.00 | $270.00 |
| 121 | (621.51000015) | 690 | $12.00 | $10.00 | $8.00 | $15.00 | $12.00 | |
| 122 | Crushed Gravel (In-Place Measure) (623.11) | CY | 102 | $135.00 | $217.28 | $125.00 | $140.00 | $110.00 |
| 123 | Survey Operations (625.01) | LS | 1 | $100,065 | $89,580 | $35,000 | $65,000 | $75,000 |
| 124 | Concrete Right of Way Markers Type L (Low) (625.04) | EACH | 12 | $1,150.00 | $553.57 | $500.00 | $600.00 | $1,100.00 |
| 125 | Steel Pin and Cap Right of Way Markers (625.05) | EACH | 31 | $275.00 | $221.43 | $175.00 | $400.00 | $240.00 |
| 126 | Permanent Survey Markers (625.06) | EACH | 14 | $1,150.00 | $442.86 | $600.00 | $2,000.00 | $1,500.00 |
| 127 | (627.50140008) | 1,941 | $7.50 | $0.25 | $6.00 | $7.00 | $5.00 | |
| 128 | Removal and Repair of Deteriorated Asphalt Pavement - Less than or equal to 4 Square Yards (633.1401) | SY | 363 | $90.00 | $123.83 | $100.00 | $90.00 | $1.00 |
| 129 | Removal and Repair of Deteriorated Asphalt Pavement – Greater than 4 Square Yards and less than 20 Square Yards (633.1402) | SY | 182 | $82.00 | $98.73 | $85.00 | $70.00 | $1.00 |
| 130 | Removal and Repair of Deteriorated Asphalt Pavement – 20 Square Yards or Greater (633.1403) | SY | 182 | $75.00 | $97.54 | $65.00 | $50.00 | $1.00 |
| 131 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $1,250.00 | $3,021.68 | $1,000.00 | $3,500.00 | $250.00 |
| 132 | Engineer’s Field Office – Type 2 (637.12) | MONTH | 19 | $2,100.00 | $3,829.07 | $2,500.00 | $2,500.00 | $2,100.00 |
| 133 | Office Technology and Supplies (637.34) | DOL | 500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 134 | White Paint Reflectorized Pavement Stripes – 15 mils (640.10) | LF | 33,440 | $0.34 | $0.31 | $0.30 | $0.31 | $0.32 |
| 135 | Yellow Paint Reflectorized Pavement Stripes - 15 mils (640.11) | LF | 34,310 | $0.34 | $0.31 | $0.30 | $0.31 | $0.32 |
| 136 | (640.12020004) | 220 | $3.00 | $2.77 | $2.75 | $2.75 | $3.00 | |
| 137 | White Paint Reflectorized Pavement Stripes – 20 mils (640.20) | LF | 35,536 | $0.35 | $0.32 | $0.30 | $0.32 | $0.32 |
| 138 | Yellow Paint Reflectorized Pavement Stripes - 20 mils (640.21) | LF | 35,560 | $0.35 | $0.32 | $0.30 | $0.32 | $0.32 |
| 139 | Ground-Mounted Sign Panels without Z-bars (645.5101) | SF | 285 | $40.00 | $38.75 | $32.00 | $39.00 | $33.00 |
| 140 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 2,011 | $50.00 | $48.72 | $34.00 | $49.00 | $34.00 |
| 141 | Type A Sign Posts (645.81) | EACH | 478 | $200.00 | $188.22 | $175.00 | $190.00 | $179.00 |
| 142 | High-Capacity Type A Sign Posts with Soil Plates Only (645.8106) | EACH | 12 | $1,150.00 | $1,124.85 | $1,050.00 | $1,135.00 | $1,065.00 |
| 143 | (645.81090003) | 102 | $81.00 | $78.60 | $80.00 | $80.00 | $82.00 | |
| 144 | Pole-Mounted Sign Support System (Band Mounting) (645.85) | EACH | 10 | $200.00 | $188.22 | $160.00 | $152.00 | $163.00 |
| 145 | Reference Marker Panel (646.21) | EACH | 35 | $38.00 | $36.54 | $27.00 | $37.00 | $27.00 |
| 146 | Steel Post, 2.0 lb/ft (646.32) | EACH | 35 | $105.00 | $99.64 | $100.00 | $100.50 | $103.00 |
| 147 | Remove and Store Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.41) | EACH | 285 | $42.00 | $40.97 | $50.00 | $41.00 | $44.00 |
| 148 | Remove and Store Sign Panel, Sign Panel Assembly Size II (30-100 Square Feet) (647.42) | EACH | 4 | $62.00 | $59.79 | $70.00 | $62.00 | $70.00 |
| 149 | (647.83001002) | 35 | $13.00 | $12.18 | $30.00 | $12.50 | $27.00 | |
| 150 | Centerline Audible Roadway Delineators (CARDs) (649.11) | LF | 4,111 | $1.40 | $1.33 | $1.50 | $1.20 | $1.35 |
| 151 | (662.60000108) | 2,500 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | |
| 152 | Adjust Existing Valve Box Elevation (663.33) | EACH | 36 | $380.00 | $192.03 | $400.00 | $300.00 | $520.00 |
| 153 | (680.05010007) | 1 | $25,000 | $24,025 | $20,000 | $25,000 | $23,100 | |
| 154 | (680.05020007) | 1 | $5,000.00 | $4,871.41 | $3,500.00 | $5,000.00 | $4,000.00 | |
| 155 | (680.11131014) | 8 | $7,200.00 | $7,982.48 | $20,000 | $6,800.00 | $4,265.00 | |
| 156 | Pole Excavation and Concrete Foundation (680.5001) | CY | 10 | $0.01 | $0.01 | $0.01 | $3,600.00 | $0.01 |
| 157 | Concrete Base for Controller Cabinet (680.5002) | EACH | 1 | $6,700.00 | $6,532.12 | $3,500.00 | $4,000.00 | $4,382.00 |
| 158 | (680.50500005) | 2 | $575.00 | $553.57 | $400.00 | $1,000.00 | $100.00 | |
| 159 | (680.510201) | EACH | 2 | $2,100.00 | $1,992.85 | $2,500.00 | $2,400.00 | $2,450.00 |
| 160 | (680.510301) | EACH | 4 | $2,500.00 | $2,380.34 | $3,500.00 | $2,600.00 | $2,720.00 |
| 161 | (680.520105) | LF | 28 | $25.00 | $24.36 | $20.00 | $50.00 | $34.00 |
| 162 | (680.520506) | LF | 92 | $17.00 | $16.61 | $25.00 | $30.00 | $14.00 |
| 163 | (680.520508) | LF | 153 | $24.00 | $23.25 | $15.00 | $21.00 | $13.00 |
| 164 | Single Span Wire Assembly (680.7001) | EACH | 1 | $3,000.00 | $2,878.56 | $3,500.00 | $3,750.00 | $3,720.00 |
| 165 | Riser Assembly, 1-inch Diameter (680.700603) | EACH | 1 | $1,600.00 | $1,550.00 | $1,000.00 | $1,100.00 | $1,740.00 |
| 166 | (680.730514) | LF | 1,691 | $5.75 | $5.54 | $10.00 | $5.10 | $2.58 |
| 167 | (680.77000105) | 1 | $5,000.00 | $5,424.98 | $3,500.00 | $2,000.00 | $2,400.00 | |
| 168 | (680.79000105) | 1 | $5,500.00 | $5,867.74 | $6,500.00 | $3,500.00 | $2,820.00 | |
| 169 | (680.80324515) | 1 | $3,250.00 | $3,432.13 | $1,500.00 | $4,000.00 | $1,997.00 | |
| 170 | (680.80324708) | 1 | $2,000.00 | $1,992.85 | $1,500.00 | $1,500.00 | $1,304.00 | |
| 171 | Traffic Signal Module - 12-inch, Red Ball, LED (680.810101) | EACH | 8 | $140.00 | $132.86 | $200.00 | $170.00 | $79.00 |
| 172 | Traffic Signal Module - 12-inch, Yellow Ball, LED (680.810103) | EACH | 8 | $145.00 | $138.39 | $200.00 | $170.00 | $79.00 |
| 173 | Traffic Signal Module - 12-inch, Green Ball, LED (680.810105) | EACH | 8 | $150.00 | $143.93 | $200.00 | $170.00 | $79.00 |
| 174 | Traffic Signal Section - Aluminum Type I, 12-inch (680.810107) | EACH | 24 | $240.00 | $232.50 | $200.00 | $210.00 | $113.00 |
| 175 | Traffic Signal Bracket Assembly - 1 Way (680.8111) | EACH | 8 | $520.00 | $509.28 | $600.00 | $390.00 | $139.00 |
| 176 | Traffic Signal Disconnect Hanger (680.8120) | EACH | 8 | $510.00 | $498.21 | $750.00 | $600.00 | $1,232.00 |
| 177 | (680.82250801) | 4 | $510.00 | $498.21 | $500.00 | $750.00 | $899.00 | |
| 178 | (680.83010005) | 134 | $4.50 | $4.43 | $4.00 | $10.00 | $10.00 | |
| 179 | Meter Pan (680.9402) | EACH | 1 | $2,000.00 | $1,937.49 | $1,000.00 | $1,100.00 | $1,034.00 |
| 180 | Install Electrical Disconnect/Generator Transfer Switch (680.9499) | EACH | 1 | $1,550.00 | $1,494.63 | $1,000.00 | $650.00 | $1,034.00 |
| 181 | (680.950106) | LF | 112 | $4.50 | $4.43 | $12.50 | $8.00 | $8.00 |
| 182 | Performance Concrete Quality Adjustment (680.99) | QUALITY UNIT | 1 | $10.00 | $10.00 | $10.00 | $10.00 | $10.00 |
| 183 | White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104) | LF | 7,370 | $4.25 | $4.15 | $4.00 | $4.15 | $4.10 |
| 184 | White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404) | EACH | 17 | $340.00 | $326.60 | $325.00 | $330.00 | $320.00 |
| 185 | (688.02010006) | 1,700 | $2.50 | $14.55 | $0.50 | $3.00 | $2.00 | |
| 186 | Field Change Payment (FCP) (697.03) | DOL | 237,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 187 | Asphalt Price Adjustment (698.04) | DOL | 12,975 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 188 | Fuel Price Adjustment (698.05) | DOL | 4,699 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 189 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 190 | Mobilization (699.040001) | LS | 1 | $212,000 | $72,850 | $208,352 | $225,000 | $232,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of August 21, 2025. Compiled by Mirage Metrics.