The L C Whitford Co Inc: NYSDOT bid record

The L C Whitford Co Inc submitted 52 bids on New York State DOT contracts in the data, from 06 JAN 2022 to 01 OCT 2026, and was the low bidder on 18 of them (35%). When it was not low, its total sat a median +14% above the low bid.

Owner
New York State DOT
Low bid volume
$45,522,261
Latest bid
01 OCT 2026
Data through
15 OCT 2026
52Bids
18Low bids
35Win rate, percent
+14%Median gap to the low bid when not low, 33 bids

By year

YearBidsLow bidsWin rate
202213538%
202316850%
202411218%
20259333%
2026300%
The L C Whitford Co Inc, NYSDOT: bids and low bids by year of letting

By region

RegionBidsLow bidsWin rate
Region 06341441%
Region 051119%
Region 046350%
Region 01, 02, 03, 04, 05, 06, 07, 08, 09, 10100%
The L C Whitford Co Inc, NYSDOT: bids and low bids by region

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Field Change Payment (FCP)697.03DOL3434 (100%)$1.00$1.00
Office Technology and Supplies637.34DOL3434 (100%)$1.00$1.00
Fuel Price Adjustment698.05DOL3434 (100%)$1.00$1.00
Steel/Iron Price Adjustment698.06DOL3434 (100%)$1.00$1.00
Asphalt Price Adjustment698.04DOL3434 (100%)$1.00$1.00
Construction Testing supplies – Consumables637.36DOL2828 (100%)$1.00$1.00
Plant Production Quality Adjustment to Asphalt Items404.000011QUALITY UNIT1515 (100%)$75.00$85.00
Engineer’s Field Office – Type 1637.11MONTH2413 (54%)$1,639.30$2,400.00
Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips608.000013QUALITY UNIT1111 (100%)$85.00$90.00
Performance Concrete Quality Adjustment – Concrete for Structures555.9902QUALITY UNIT1111 (100%)$12.02$10.50
Drilling and Grouting Bolts or Reinforcing Bars586.0201EACH158 (53%)$33.00$60.00
610.1601002098 (89%)$6.00$13.00
The L C Whitford Co Inc, NYSDOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

Latest bids

LetContractRegionProjectRankIts bidAgainst the low bid
01 OCT 2026D265839Region 06BRIDGE JOINT REPAIRS 2026/273 of 3$2,148,887+81%
13 AUG 2026D265689Region 04Replacement of Six Culverts2 of 8$8,805,239+22%
05 MAR 2026D265646Region 06Region 6 Culvert Replacements - NYS Rte 212 of 5$3,098,887+2.0%
04 DEC 2025D265625Region 06BRIDGE REPLACEMENT - NY 371 over Kirkwood Creek1 of 5$3,839,886Low, 9.0% under the second
06 NOV 2025D265613Region 06Where & When Highway Maintenance, Various Locations2 of 2$2,602,0890.0%
23 OCT 2025D265526Region 06CULVERT REPLACEMENTS - Routes NY 19, NY 275 & NY 3053 of 3$11,554,887+6.0%
11 SEP 2025D265518Region 06CULVERT REPLACEMENTS - Towns of Greenwood & Canisteo2 of 5$6,588,887+8.0%
21 AUG 2025D265560Region 06CULVERT REPLACEMENT - NY 21, CIN 6404703 of 4$2,336,477+3.0%
07 AUG 2025D265555Region 06I-86 BRIDGE DECK TREATMENT AND JOINT REPLACEMENTS5 of 6$7,369,887+46%
13 MAR 2025D265429Region 05BRIDGE REPLACEMENT - U.S. Route 219 over Great Valley Creek4 of 4$6,880,987+6.0%
13 MAR 2025D265450Region 04Highway Repair Where/When Contract for 2025 and 20261 of 4$2,206,065Low, 3.0% under the second
20 FEB 2025D265443Region 06Culvert Replacements & Retaining Wall Repairs1 of 3$1,912,985Low, 38% under the second
19 DEC 2024D265390Region 06HAZARD MITIGATION & SAFETAP BACKLOG-Various Locations2 of 4$972,573+14%
19 DEC 2024D265394Region 06PIN 6805.75 - D265394 - Bridge Bearing Repairs4 of 6$2,349,655+49%
07 NOV 2024D265340Region 06Where and When Bridge Regional 04/2025 - 04/20273 of 3$2,483,411+554%
10 OCT 2024D265334Region 06I-390/B&H RR Bridge Joint Repairs (1090651 & 1090652)4 of 5$2,494,242+33%
25 JUL 2024D265293Region 05NY 280 (BRIDGE & LARGE CULVERTS) - SNI; CATT CO5 of 6$7,058,883+86%
28 MAR 2024D265194Region 05Bridge Replacement Project, BIN 66002301 of 4$1,610,182Low, 14% under the second
14 MAR 2024D265223Region 05Small Culvert Rehabilitations and Replacements5 of 5$6,116,581+46%
08 FEB 2024D265158Region 05HIGHWAY JOB ORDER CONTRACT2 of 3$623,877+9.0%
25 JAN 2024D265186Region 01, 02, 03, 04, 05, 06, 07, 08, 09, 102024-2027 - STATEWIDE EMERGENCY BRIDGE CONTRACT2 of 4$6,631,966+3.0%
11 JAN 2024D265167Region 06BRIDGE MAINTENANCE- Job Order Contract, Various Locations.3 of 3$987,992+8.0%
11 JAN 2024D265168Region 06CULVERT MAINTENANCE - JOB ORDER CONTRACT1 of 1$493,996Low
14 DEC 2023D265157Region 06Bridge Rehab - NY 248 over Bennett's Creek/Sugar Creek1 of 3$4,288,887Low, 3.0% under the second
14 DEC 2023D265170Region 05BRIDGE WHERE & WHEN CONTRACT SFY 23-24 & 24-254 of 4$1,055,827+7.0%
The L C Whitford Co Inc: latest NYSDOT bids in the data

How this record was read

NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

  • Every bid counted here matched its published total to within one dollar; NYSDOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy