NYSDOT contract D265560 bid tabulation
CULVERT REPLACEMENT - NY 21, CIN 640470. Let by New York State DOT on August 21, 2025, Steuben, Region 06. 4 bids received; low bid $2,258,258 by Cold Spring Construction Company.
- Owner
- New York State DOT
- Letting
- 21 AUG 2025
- Pay items
- 93
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Cold Spring Construction Company | $2,258,258 | Low |
| 2 | Dalrymple Gravel & Contracting Co Inc | $2,313,444 | +2.0% |
| 3 | The L C Whitford Co Inc | $2,336,477 | +3.0% |
| 4 | Twin Tier Constructors Inc | $2,444,000 | +8.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Cold Spring Construction Company | 2. Dalrymple Gravel & Contracting Co Inc | 3. The L C Whitford Co Inc | 4. Twin Tier Constructors Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $22,500 | $21,000 | $28,078 | $58,513 |
| 2 | Removal of Substructures (202.19) | CY | 168 | $170.00 | $225.00 | $329.44 | $180.00 |
| 3 | Unclassified Excavation and Disposal (203.02) | CY | 1,172 | $50.00 | $30.00 | $51.81 | $32.00 |
| 4 | Embankment In Place (203.03) | CY | 1,474 | $35.00 | $30.00 | $65.78 | $28.00 |
| 5 | Select Structural Fill (203.21) | CY | 160 | $110.00 | $160.00 | $222.39 | $75.00 |
| 6 | Controlled Low Strength Material (CLSM) (204.01) | CY | 9 | $250.00 | $1,500.00 | $725.81 | $390.00 |
| 7 | Structure Excavation (206.01) | CY | 1,622 | $35.00 | $30.00 | $49.83 | $21.00 |
| 8 | Trench and Culvert Excavation (206.0201) | CY | 117 | $100.00 | $30.00 | $240.84 | $45.00 |
| 9 | Geotextile Bedding (207.20) | SY | 156 | $5.00 | $10.00 | $8.39 | $7.00 |
| 10 | Geotextile Separation (207.21) | SY | 3,296 | $1.00 | $1.50 | $6.59 | $2.00 |
| 11 | Prefabricated Composite Structural Drain (207.26) | SY | 144 | $15.00 | $20.00 | $34.05 | $26.00 |
| 12 | Silt Fence - Temporary (209.13) | LF | 1,095 | $5.00 | $5.00 | $9.80 | $5.00 |
| 13 | Rolled Erosion Control Product, Class II Type C, Intermediate (209.190301) | SY | 85 | $12.00 | $5.00 | $15.44 | $10.00 |
| 14 | (209.20120010) | 80 | $20.00 | $10.00 | $127.19 | $15.00 | |
| 15 | Subbase Course, Type 1 (304.11) | CY | 20 | $175.00 | $225.00 | $456.47 | $100.00 |
| 16 | Subbase Course, Optional Type (304.15) | CY | 1,336 | $70.00 | $75.00 | $89.12 | $75.00 |
| 17 | (404.0001) | TON | 8 | $75.00 | $75.00 | $75.00 | $75.00 |
| 18 | (404.0179) | TON | 21 | $225.00 | $300.00 | $303.19 | $300.00 |
| 19 | (404.0973) | TON | 450 | $130.00 | $130.00 | $159.86 | $170.00 |
| 20 | (404.2579) | TON | 442 | $120.00 | $130.00 | $155.45 | $165.00 |
| 21 | (404.3779) | TON | 1,716 | $100.00 | $130.00 | $124.58 | $130.00 |
| 22 | Diluted Tack Coat (407.0102) | GAL | 884 | $8.00 | $10.00 | $5.51 | $5.00 |
| 23 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 2,490 | $1.00 | $1.00 | $1.16 | $1.50 |
| 24 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 2,388 | $10.00 | $12.00 | $15.74 | $12.00 |
| 25 | Interim Steel Sheeting (552.15) | SF | 350 | $200.00 | $323.00 | $304.83 | $600.00 |
| 26 | (553.030001) | EACH | 1 | $50,000 | $1,000.00 | $28,243 | $50,000 |
| 27 | Concrete for Structures, Performance (555.0021) | CY | 7 | $5,000.00 | $4,500.00 | $5,228.29 | $1,000.00 |
| 28 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $25.00 | $25.00 | $25.00 | $25.00 |
| 29 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 800 | $6.00 | $5.00 | $9.91 | $4.00 |
| 30 | Protective Sealing of New Structural Concrete (559.02) | SF | 285 | $5.00 | $8.00 | $8.80 | $4.00 |
| 31 | Steel Bridge Railing (Three-Rail) (568.54) | LF | 48 | $300.00 | $250.00 | $271.55 | $270.00 |
| 32 | Transition Bridge Railing (568.70) | LF | 128 | $200.00 | $190.00 | $206.17 | $200.00 |
| 33 | (595.50000018) | 1,966 | $6.00 | $3.00 | $5.29 | $3.50 | |
| 34 | (603.64200615) | 44 | $7,500.00 | $11,250 | $5,111.40 | $7,500.00 | |
| 35 | (603.67000001) | 55 | $2,750.00 | $2,500.00 | $2,006.21 | $1,500.00 | |
| 36 | Underdrain Filter, Type II (605.1001) | CY | 30 | $200.00 | $230.00 | $300.32 | $80.00 |
| 37 | (605.1701) | LF | 400 | $5.00 | $2.50 | $29.17 | $7.00 |
| 38 | Box Beam Guide Railing (606.10) | LF | 528 | $55.00 | $50.00 | $54.02 | $54.00 |
| 39 | Box Beam Guide Railing End Assembly Type I (606.120102) | EACH | 3 | $5,000.00 | $4,200.00 | $4,591.91 | $4,500.00 |
| 40 | Removing and Disposing Corrugated Beam Guide Railing (606.71) | LF | 544 | $10.00 | $5.00 | $15.37 | $6.00 |
| 41 | Removing and Disposing Box Beam Guide Railing (606.73) | LF | 72 | $10.00 | $5.00 | $29.38 | $12.00 |
| 42 | Removing and Disposing Anchorage Units for Corrugated Beam Guide Railing and Median Barrier (606.7910) | EACH | 4 | $2,000.00 | $500.00 | $1,203.58 | $500.00 |
| 43 | Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920) | EACH | 1 | $2,000.00 | $500.00 | $1,516.54 | $45.00 |
| 44 | Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102) | TON | 16 | $350.00 | $300.00 | $275.63 | $380.00 |
| 45 | Stone Curb – Bridge (Type A) (609.0301) | LF | 60 | $125.00 | $150.00 | $262.35 | $85.00 |
| 46 | Mycorrhizal Fungi (610.0701) | LB | 16 | $35.00 | $50.00 | $55.71 | $45.00 |
| 47 | Turf Establishment – Performance (610.1605) | SY | 3,096 | $6.00 | $10.00 | $5.68 | $25.00 |
| 48 | Watering Vegetation (610.19) | 1,000 GALLONS | 74 | $100.00 | $100.00 | $115.76 | $1.00 |
| 49 | (611.0141) | EACH | 2 | $1,500.00 | $1,000.00 | $1,526.97 | $600.00 |
| 50 | (611.0291) | EACH | 6 | $1,500.00 | $1,000.00 | $1,422.23 | $600.00 |
| 51 | (611.19010024) | 2 | $400.00 | $100.00 | $396.90 | $1.00 | |
| 52 | (611.19020024) | 6 | $350.00 | $100.00 | $363.83 | $1.00 | |
| 53 | (615.01010108) | 63 | $100.00 | $140.00 | $156.49 | $100.00 | |
| 54 | (616.07000024) | 120 | $25.00 | $15.00 | $24.26 | $25.00 | |
| 55 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $75,000 | $55,000 | $70,992 | $150,000 |
| 56 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 6,386 | $4.00 | $4.00 | $3.72 | $9.00 |
| 57 | (619.100103) | LF | 10,058 | $4.00 | $4.00 | $3.60 | $9.00 |
| 58 | (619.130101) | EACH | 1 | $120,000 | $60,000 | $65,845 | $90,000 |
| 59 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 580 | $40.00 | $50.00 | $47.96 | $40.00 |
| 60 | Temporary Positive Barrier – Category 5 (Pinning Prohibited) (619.1715) | LF | 700 | $50.00 | $50.00 | $59.95 | $50.00 |
| 61 | Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716) | LF | 100 | $60.00 | $50.00 | $64.75 | $60.00 |
| 62 | Temporary Impact Attenuator - Redirective (Test Level 3) (619.1803) | EACH | 4 | $5,000.00 | $7,000.00 | $5,126.02 | $5,000.00 |
| 63 | Mailboxes (619.27) | EACH | 4 | $500.00 | $250.00 | $474.59 | $500.00 |
| 64 | Stone Filling (Light) (620.03) | CY | 14 | $200.00 | $350.00 | $337.84 | $120.00 |
| 65 | Stone Filling (Medium) (620.04) | CY | 278 | $250.00 | $200.00 | $119.64 | $160.00 |
| 66 | Bedding Material, Type 2 (620.0802) | CY | 55 | $150.00 | $150.00 | $102.63 | $70.00 |
| 67 | Clean, Grade and Shape Existing Roadside Section (621.05) | LF | 828 | $10.00 | $1.00 | $17.05 | $0.50 |
| 68 | Crushed Stone (In-Place Measure) (623.12) | CY | 60 | $150.00 | $150.00 | $190.17 | $90.00 |
| 69 | Survey Operations (625.01) | LS | 1 | $35,000 | $20,000 | $16,538 | $35,000 |
| 70 | (627.50140008) | 664 | $6.00 | $10.00 | $9.49 | $3.00 | |
| 71 | Cleaning Existing Pavement and/or Shoulder (633.11) | SY | 2,050 | $0.50 | $1.00 | $3.46 | $0.25 |
| 72 | Concrete Cylinder Curing Equipment (637.04) | EACH | 1 | $500.00 | $2,500.00 | $4,796.00 | $3,000.00 |
| 73 | Engineer’s Field Office – Type 1 (637.11) | MONTH | 24 | $2,250.00 | $1,500.00 | $1,498.75 | $500.00 |
| 74 | Office Technology and Supplies (637.34) | DOL | 2,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 75 | Construction Testing supplies – Consumables (637.36) | DOL | 200 | $1.00 | $1.00 | $1.00 | $1.00 |
| 76 | (637.41000115) | 24 | $125.00 | $50.00 | $122.40 | $200.00 | |
| 77 | (637.41000215) | 24 | $125.00 | $50.00 | $122.40 | $200.00 | |
| 78 | White Paint Reflectorized Pavement Stripes – 20 mils (640.20) | LF | 2,910 | $2.00 | $2.00 | $1.88 | $2.00 |
| 79 | Yellow Paint Reflectorized Pavement Stripes - 20 mils (640.21) | LF | 3,330 | $2.00 | $2.00 | $1.88 | $2.00 |
| 80 | Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102) | SF | 9 | $50.00 | $45.00 | $49.61 | $48.00 |
| 81 | Type A Sign Posts (645.81) | EACH | 1 | $300.00 | $285.00 | $314.21 | $300.00 |
| 82 | Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22) | EACH | 3 | $20.00 | $16.00 | $17.09 | $17.00 |
| 83 | Large Delineator, Large Snowplowing Marker, Large Supplementary Snowplowing Marker Panel (646.23) | EACH | 1 | $25.00 | $21.00 | $22.61 | $22.00 |
| 84 | Steel Post, 2.0 lb/ft (646.32) | EACH | 3 | $100.00 | $81.00 | $88.76 | $85.00 |
| 85 | Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51) | EACH | 1 | $15.00 | $11.00 | $12.13 | $12.00 |
| 86 | Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61) | EACH | 1 | $15.00 | $11.00 | $12.13 | $12.00 |
| 87 | Centerline Audible Roadway Delineators (CARDs) (649.11) | LF | 1,395 | $2.00 | $4.00 | $6.19 | $1.60 |
| 88 | Secondary Highway Audible Roadway Delineators (SHARDs) (649.21) | LF | 1,940 | $2.00 | $4.00 | $5.18 | $1.60 |
| 89 | Field Change Payment (FCP) (697.03) | DOL | 90,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 90 | Asphalt Price Adjustment (698.04) | DOL | 3,300 | $1.00 | $1.00 | $1.00 | $1.00 |
| 91 | Fuel Price Adjustment (698.05) | DOL | 1,463 | $1.00 | $1.00 | $1.00 | $1.00 |
| 92 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 | $1.00 |
| 93 | Mobilization (699.040001) | LS | 1 | $86,405 | $75,000 | $68,000 | $90,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of August 21, 2025. Compiled by Mirage Metrics.