NYSDOT contract D265625 bid tabulation

BRIDGE REPLACEMENT - NY 371 over Kirkwood Creek. Let by New York State DOT on December 4, 2025, Steuben, Region 06. 5 bids received; low bid $3,839,886 by The L C Whitford Co Inc.

Owner
New York State DOT
Letting
04 DEC 2025
Pay items
123
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1The L C Whitford Co Inc$3,839,886Low
2Twin Tier Constructors Inc$4,193,000+9.0%
3Cold Spring Construction Company$4,531,038+18%
4C P Ward Inc$4,544,654+18%
5Rochester Earth Inc$5,700,000+48%
NYSDOT contract D265625: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. The L C Whitford Co Inc2. Twin Tier Constructors Inc3. Cold Spring Construction Company4. C P Ward Inc5. Rochester Earth Inc
1Clearing and Grubbing (201.06)LS1$55,966$60,000$20,000$18,000$21,350
2 (202.120001)LS1$48,068$90,000$125,000$65,000$47,625
3Removal of Substructures (202.19)CY60$214.73$170.00$275.00$300.00$385.00
4Unclassified Excavation and Disposal (203.02)CY1,114$33.17$23.00$36.00$42.00$34.00
5Embankment In Place (203.03)CY1,303$29.23$60.00$37.00$60.00$85.00
6Select Structural Fill (203.21)CY150$86.96$85.00$125.00$95.00$125.00
7Structure Excavation (206.01)CY1,250$32.65$20.00$29.00$40.00$32.75
8Trench and Culvert Excavation (206.0201)CY150$78.94$40.00$72.00$52.00$19.00
9Geotextile Bedding (207.20)SY18$8.39$10.00$23.00$30.00$32.50
10Geotextile Separation (207.21)SY3,426$3.62$2.25$2.25$2.00$3.00
11Prefabricated Composite Integral Abutment Drain (207.27)SY146$28.33$14.00$20.00$25.00$23.50
12Seed and Mulch – Temporary (209.1003)SY2,121$2.08$0.25$1.85$3.00$2.00
13Check Dam (Ditch Bottom Width 0.0 to 3′), Gravel Bag – Temporary (209.110201)EACH2$686.54$400.00$1,100.00$800.00$540.00
14Silt Fence - Temporary (209.13)LF2,295$5.34$5.00$5.25$4.00$5.25
15Rolled Erosion Control Product, Class II Type C, Intermediate (209.190301)SY415$10.48$6.00$10.25$5.00$10.25
16 (209.20120010)310$49.07$15.00$48.00$25.00$48.50
17Removal and Disposal of Concrete-Encased Pipe ACM (BV14) (210.3011)LF32$155.04$300.00$115.00$255.00$465.00
18 (210.481201)SF1,542$25.02$20.00$55.00$30.00$104.00
19Subbase Course, Optional Type (304.15)CY2,353$79.60$60.00$90.00$98.00$83.50
20 (404.0001)TON166$95.00$95.00$95.00$95.00$95.00
21 (404.0973)TON372$228.44$155.00$145.00$140.00$150.00
22 (404.2579)TON666$137.81$140.00$120.00$125.00$146.00
23 (404.3779)TON1,899$115.76$125.00$110.00$118.00$140.00
24 (404.4389)TON491$121.28$125.00$130.00$120.00$166.00
25Diluted Tack Coat (407.0102)GAL860$9.92$10.00$10.00$15.00$17.50
26Asphalt Pavement Joint Adhesive (418.7603)LF1,121$2.76$5.00$1.00$5.00$2.50
27Miscellaneous Cold Milling of Bituminous Concrete (490.30)SY646$15.61$15.00$11.75$18.00$28.00
28Micropiles (Contractor Designed) – With Extended Lengths (551.31)EACH26$11,576$14,000$8,400.00$12,000$9,200.00
29 (551.33)317$110.25$100.00$200.00$210.00$219.00
30Furnishing Equipment for Installing Micropiles (551.34)LS1$68,563$50,000$95,000$100,000$38,325
31Static Pile Compressive Load Test (551.35)EACH1$33,075$50,000$40,000$40,000$43,800
32 (553.020001)EACH1$0.01$500.00$0.01$5,000.00$20,000
33 (553.020002)EACH1$0.01$500.00$0.01$5,000.00$20,000
34 (553.030001)EACH1$36,690$1,000.00$0.01$5,000.00$12,250
35Concrete for Structures, Performance (555.0021)CY185$1,116.72$1,650.00$1,500.00$1,300.00$1,800.00
36Performance Concrete Quality Adjustment – Concrete for Structures (555.9902)QUALITY UNIT1$12.50$12.50$12.50$12.50$12.50
37Epoxy-Coated Bar Reinforcement for Structures (556.0202)LB26,600$2.99$3.50$3.00$3.00$2.80
38 (557.1019)SY157$506.24$600.00$525.00$410.00$535.00
39 (557.1119)SY298$951.84$700.00$800.00$730.00$1,050.00
40Winter Surface Treatment – Superstructure Slabs and Structural Approach Slabs (557.29)SY455$0.02$0.01$0.01$1.00$71.00
41Performance Concrete Quality Adjustment – Superstructure and Approach Slab (557.9901)QUALITY UNIT1$11.07$11.07$11.07$11.07$11.07
42Longitudinal Sawcut Grooving of Structural Slab Surface (558.02)SY434$18.34$16.00$18.00$25.00$15.00
43Protective Sealing of Structural Concrete on New Bridge Decks and Bridge Deck Overlays (559.01)SF3,903$1.14$1.00$0.90$0.75$1.00
44Protective Sealing of New Structural Concrete (559.02)SF3,189$1.67$2.00$1.60$5.00$1.00
45Prestressed Concrete New England Bulb Tee Units (563.05)LF350$728.72$900.00$1,000.00$1,150.00$3,300.00
46 (564.20010008)3,200$1.06$10.00$0.01$1.00$2.75
47 (565.30130101)10$866.75$400.00$1,100.00$250.00$815.00
48Transition Bridge Railing (568.70)LF160$220.50$190.00$190.00$180.00$180.00
49Single Slope (Half-Section) Concrete Bridge Barrier (569.04)LF148$513.14$400.00$375.00$500.00$400.00
50Performance Concrete Quality Adjustment–Cast-In-Place Concrete Barrier (569.99)QUALITY UNIT1$11.57$11.57$11.57$11.57$11.57
51Lead-Exposure Control Plan (570.01)LS1$2,997.50$500.00$0.01$1,500.00$2,715.00
52Medical Testing (570.02)DOL500$1.00$1.00$1.00$1.00$1.00
53Personal-Exposure-Monitoring Sample Analysis (570.03)DOL1,000$1.00$1.00$1.00$1.00$1.00
54Decontamination Facilities (570.04)CALENDAR WEEK1$599.50$1.00$550.00$500.00$630.00
55 (570.10)LS1$1,560.62$3,000.00$0.01$1,500.00$7,248.00
56Disposal of Hazardous Paint Removal Waste Containing Lead (571.03)LB600$1.24$0.20$2.50$5.00$4.00
57Box Beam Guide Railing (606.10)LF444$47.41$50.00$50.00$50.00$51.25
58Box Beam Guide Railing (Shop Bent or Shop Mitered) (606.100002)LF24$62.84$70.00$65.00$65.00$65.50
59Box Beam Guide Railing End Assembly Type I (606.120102)EACH4$4,189.50$4,500.00$4,450.00$4,500.00$4,600.00
60Box Beam Guide Railing End Assembly Type IIA (606.120201)EACH1$2,205.00$2,500.00$2,350.00$2,500.00$2,385.00
61Removing and Disposing Box Beam Guide Railing (606.73)LF340$6.46$6.00$8.00$8.00$10.00
62Removing and Disposing Box Beam Guide Rail Turned-Down Terminal (606.7920)EACH4$392.26$50.00$350.00$600.00$210.00
63 (607.41010010)80$14.64$4.00$7.00$7.00$8.50
64Plant Production Quality Adjustment to Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.000013)QUALITY UNIT1$95.00$95.00$95.00$95.00$95.00
65Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON22$192.94$190.00$600.00$300.00$490.00
66Stone Curb – Bridge (Type A) (609.0301)LF60$146.09$140.00$135.00$150.00$202.00
67Mycorrhizal Fungi (610.0701)LB26$66.15$45.00$63.00$90.00$65.00
68Turf Establishment – Performance (610.1605)SY4,644$1.98$20.00$12.00$16.00$8.80
69Turf Establishment – Nurse Crops (610.1606)SY280$3.31$22.00$13.00$16.00$3.25
70Wildflower Seeding (610.17)SY280$26.45$3.00$9.00$8.00$9.25
71Watering Vegetation (610.19)1,000 GALLONS117$77.18$0.01$25.00$30.00$76.50
72 (611.0141)EACH7$1,163.14$800.00$1,100.00$1,000.00$1,155.00
73 (611.0291)EACH6$1,091.48$800.00$1,050.00$950.00$1,080.00
74 (611.19010024)7$347.29$100.00$250.00$250.00$340.00
75 (611.19020024)6$328.55$100.00$250.00$250.00$325.00
76 (615.01010108)40$143.99$80.00$350.00$90.00$160.00
77 (616.07000024)240$35.84$24.00$35.00$18.00$35.00
78 (617.11000024)LS1$5,995.00$1.00$353.64$1.00$3,350.00
79Basic Work Zone Traffic Control (619.01)LS1$38,061$50,000$100,000$40,000$82,000
80 (619.0501)LS1$316,499$470,000$700,000$650,000$600,000
81Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803)LF150$6.62$7.50$7.00$9.00$11.50
82 (619.100103)LF6,630$6.62$6.50$5.50$3.00$11.50
83 (619.130101)EACH1$60,125$80,000$74,000$110,000$90,000
84Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711)LF80$213.20$40.00$32.00$80.00$200.00
85Temporary Positive Barrier – Category 5 (Pinning Prohibited) (619.1715)LF880$35.97$40.00$42.00$60.00$43.00
86Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716)LF240$39.57$40.00$40.00$70.00$89.00
87Warning Lights on Temporary Positive Barriers (619.1719)EACH46$59.95$20.00$150.00$80.00$79.00
88Temporary Impact Attenuator - Redirective (Test Level 3) (619.1803)EACH6$2,646.00$10,000$16,000$8,500.00$8,480.00
89Mailboxes (619.27)EACH1$480.08$500.00$325.00$500.00$675.00
90Stone Filling (Light) (620.03)CY30$294.03$125.00$250.00$200.00$160.00
91Stone Filling (Heavy) (620.05)CY405$170.17$165.00$85.00$165.00$270.00
92Bedding Material, Type 2 (620.0802)CY105$89.98$100.00$115.00$120.00$110.00
93Cleaning Culverts with Span of 50 in. or Less (621.01)LF57$65.90$50.00$80.00$40.00$120.00
94Clean, Grade and Shape Existing Roadside Section (621.05)LF200$28.18$1.00$13.00$25.00$25.00
95Survey Operations (625.01)LS1$37,816$40,000$62,000$45,000$54,000
96Concrete Right of Way Markers Type H (High) (625.03)EACH1$3,197.25$700.00$1,250.00$1,500.00$2,250.00
97Concrete Right of Way Markers Type L (Low) (625.04)EACH2$1,929.38$600.00$1,200.00$1,900.00$1,400.00
98 (625.09010015)LS1$12,128$1.00$0.01$3,400.00$5,400.00
99 (627.50140008)68$12.44$6.00$10.00$3.00$3.75
100Cleaning Existing Pavement and/or Shoulder (633.11)SY378$10.10$0.50$1.30$2.00$14.00
101Concrete Cylinder Curing Equipment (637.04)EACH1$2,697.75$5,000.00$400.00$1,000.00$2,300.00
102Engineer’s Field Office – Type 1 (637.11)MONTH12$1,199.00$800.00$2,500.00$2,750.00$2,800.00
103Office Technology and Supplies (637.34)DOL200$1.00$1.00$1.00$1.00$1.00
104Construction Testing supplies – Consumables (637.36)DOL200$1.00$1.00$1.00$1.00$1.00
105 (637.41000115)12$184.85$150.00$200.00$200.00$345.00
106 (637.41000215)12$184.85$150.00$200.00$200.00$345.00
107White Paint Reflectorized Pavement Stripes – 20 mils (640.20)LF3,363$0.93$1.40$0.50$1.00$2.00
108Yellow Paint Reflectorized Pavement Stripes - 20 mils (640.21)LF1,777$0.93$1.40$0.50$1.00$2.00
109Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF22$33.08$50.00$46.00$45.00$46.00
110Type A Sign Posts (645.81)EACH3$159.86$250.00$250.00$250.00$220.00
111Reference Marker Panel (646.21)EACH2$33.08$40.00$39.00$30.00$30.00
112Delineator, Snowplowing Marker, Supplementary Snowplowing Marker Panels (646.22)EACH6$119.90$18.00$17.00$12.00$12.00
113Steel Post, 2.0 lb/ft (646.32)EACH8$68.36$90.00$90.00$75.00$70.00
114Remove and Dispose Sign Panel, Sign Panel Assembly Size I (Under 30 Square Feet) (647.51)EACH7$17.64$75.00$65.00$100.00$22.00
115Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61)EACH5$17.64$60.00$90.00$100.00$22.00
116 (648.50010008)35$36.91$30.00$125.00$150.00$714.21
117Centerline Audible Roadway Delineators (CARDs) (649.11)LF982$10.97$5.00$11.00$7.00$4.75
118 (691.04000020)14,000$1.00$1.00$1.00$1.00$1.00
119Field Change Payment (FCP) (697.03)DOL247,000$1.00$1.00$1.00$1.00$1.00
120Asphalt Price Adjustment (698.04)DOL3,744.31$1.00$1.00$1.00$1.00$1.00
121Fuel Price Adjustment (698.05)DOL1,239$1.00$1.00$1.00$1.00$1.00
122Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00$1.00
123Mobilization (699.040001)LS1$146,430$159,587$174,000$172,000$148,000
NYSDOT contract D265625: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of December 4, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy