NYSDOT contract D265443 bid tabulation
Culvert Replacements & Retaining Wall Repairs. Let by New York State DOT on February 20, 2025, Steuben, Yates, Region 06. 3 bids received; low bid $1,912,985 by The L C Whitford Co Inc.
- Owner
- New York State DOT
- Letting
- 20 FEB 2025
- Pay items
- 76
- Data through
- 15 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | The L C Whitford Co Inc | $1,912,985 | Low |
| 2 | Twin Tier Constructors Inc | $2,644,000 | +38% |
| 3 | Cold Spring Construction Company | $3,948,824 | +106% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. The L C Whitford Co Inc | 2. Twin Tier Constructors Inc | 3. Cold Spring Construction Company |
|---|---|---|---|---|---|---|
| 1 | Clearing and Grubbing (201.06) | LS | 1 | $52,756 | $120,000 | $10,500 |
| 2 | Removal of Substructures (202.19) | CY | 60 | $378.33 | $400.00 | $375.00 |
| 3 | Unclassified Excavation and Disposal (203.02) | CY | 540 | $64.70 | $38.00 | $70.00 |
| 4 | Embankment In Place (203.03) | CY | 406 | $79.72 | $95.00 | $135.00 |
| 5 | Select Granular Fill, Slope Protection - Type A (203.0801) | CY | 34 | $183.69 | $50.00 | $190.00 |
| 6 | Select Structural Fill (203.21) | CY | 462 | $133.39 | $95.00 | $190.00 |
| 7 | Controlled Low Strength Material (CLSM) (204.01) | CY | 51 | $606.09 | $450.00 | $525.00 |
| 8 | Structure Excavation (206.01) | CY | 725 | $52.22 | $38.00 | $70.00 |
| 9 | Trench and Culvert Excavation (206.0201) | CY | 226 | $113.07 | $45.00 | $100.00 |
| 10 | Geotextile Separation (207.21) | SY | 790 | $6.00 | $4.00 | $2.75 |
| 11 | Silt Fence - Temporary (209.13) | LF | 77 | $7.19 | $10.00 | $14.00 |
| 12 | Subbase Course, Optional Type (304.15) | CY | 262 | $107.01 | $90.00 | $265.00 |
| 13 | (404.0983) | TON | 143 | $297.68 | $240.00 | $315.00 |
| 14 | (404.1989) | TON | 121 | $241.45 | $240.00 | $285.00 |
| 15 | (404.2589) | TON | 15 | $330.03 | $340.00 | $415.00 |
| 16 | (404.3789) | TON | 387 | $180.81 | $240.00 | $240.00 |
| 17 | Diluted Tack Coat (407.0102) | GAL | 1,313 | $14.33 | $2.50 | $14.00 |
| 18 | Asphalt Pavement Joint Adhesive (418.7603) | LF | 234 | $2.21 | $20.00 | $6.75 |
| 19 | Miscellaneous Cold Milling of Bituminous Concrete (490.30) | SY | 300 | $39.95 | $30.00 | $25.00 |
| 20 | Fill Type Retaining Wall (Greater than 6 ft. – 12 ft.) (554.41) | SF | 1,030 | $69.99 | $120.00 | $115.00 |
| 21 | Fill Type Retaining Wall Aesthetic Treatment - Other; As Shown in the Contract Documents (554.53) | SF | 1,030 | $0.12 | $0.01 | $0.01 |
| 22 | Concrete for Structures, Performance (555.0021) | CY | 80 | $1,077.02 | $2,500.00 | $2,900.00 |
| 23 | (555.41000011) | 250 | $64.15 | $80.00 | $125.00 | |
| 24 | Performance Concrete Quality Adjustment – Concrete for Structures (555.9902) | QUALITY UNIT | 1 | $12.50 | $12.50 | $12.50 |
| 25 | Epoxy-Coated Bar Reinforcement for Structures (556.0202) | LB | 9,000 | $3.40 | $3.50 | $4.00 |
| 26 | Protective Sealing of Concrete with Coating Type Protective Sealer (559.04) | SQUAREFOOT | 2,945 | $2.20 | $3.00 | $3.75 |
| 27 | Removal of Structural Concrete (580.01) | CY | 23 | $2,128.10 | $2,200.00 | $4,250.00 |
| 28 | Drilling and Grouting Bolts or Reinforcing Bars (586.0201) | EACH | 573 | $22.19 | $35.00 | $40.00 |
| 29 | (603.6212) | LF | 196 | $577.00 | $1,800.00 | $900.00 |
| 30 | (603.6706) | LF | 43 | $404.29 | $510.00 | $600.00 |
| 31 | (603.67060008) | 1 | $18,778 | $10,000 | $10,000 | |
| 32 | (603.7312) | EACH | 2 | $23,168 | $20,000 | $11,000 |
| 33 | (603.97000002) | 1 | $948.52 | $1,500.00 | $1,115.00 | |
| 34 | (603.9836) | LF | 3 | $646.49 | $1,500.00 | $1,400.00 |
| 35 | (604.300903) | LF | 8 | $1,095.37 | $1,100.00 | $1,650.00 |
| 36 | Resetting Box Beam Guide Railing (New Posts) (606.5348) | LF | 202 | $86.00 | $100.00 | $100.00 |
| 37 | (607.96000008) | 55 | $27.36 | $105.00 | $18.00 | |
| 38 | (615.01010108) | 34 | $501.28 | $130.00 | $1,000.00 | |
| 39 | Basic Work Zone Traffic Control (619.01) | LS | 1 | $33,676 | $310,000 | $625,000 |
| 40 | Type III Construction Barricades (619.04) | EACH | 8 | $137.81 | $100.00 | $75.00 |
| 41 | Cover Existing Pavement Marking Stripes (Removable Tape) (619.0803) | LF | 5,556 | $4.97 | $6.00 | $4.75 |
| 42 | (619.100103) | LF | 8,474 | $4.14 | $5.00 | $3.95 |
| 43 | (619.110611) | WEEK | 40 | $1,199.00 | $350.00 | $900.00 |
| 44 | (619.1301) | EACH | 1 | $8,992.50 | $60,000 | $35,000 |
| 45 | (619.1303) | EACH | 1 | $25,779 | $120,000 | $25,000 |
| 46 | (619.1304) | EACH | 1 | $25,779 | $120,000 | $25,000 |
| 47 | Temporary Positive Barrier – Category 1 (Pinning Prohibited) (619.1711) | LF | 520 | $53.96 | $45.00 | $40.00 |
| 48 | Temporary Positive Barrier – Category 5 (Pinning Prohibited) (619.1715) | LF | 540 | $64.75 | $45.00 | $40.00 |
| 49 | Temporary Positive Barrier – Category 6 (Pinning Required) (619.1716) | LF | 260 | $69.54 | $50.00 | $65.00 |
| 50 | Temporary Impact Attenuator - Redirective (Test Level 2) (619.1802) | EACH | 1 | $5,145.39 | $5,365.70 | $7,500.00 |
| 51 | Mailboxes (619.27) | EACH | 8 | $453.70 | $450.00 | $325.00 |
| 52 | Stone Filling (Light) (620.03) | CY | 72 | $172.14 | $140.00 | $400.00 |
| 53 | Stone Filling (Medium) (620.04) | CY | 83 | $256.85 | $160.00 | $325.00 |
| 54 | Stone Filling (Heavy) (620.05) | CY | 67 | $325.26 | $170.00 | $550.00 |
| 55 | Bedding Material, Type 1 (620.0801) | CY | 5 | $423.53 | $140.00 | $375.00 |
| 56 | Bedding Material, Type 2 (620.0802) | CY | 75 | $139.25 | $130.00 | $265.00 |
| 57 | Clean, Grade and Shape Existing Roadside Section (621.05) | LF | 652 | $22.66 | $4.00 | $35.00 |
| 58 | Survey Operations (625.01) | LS | 1 | $22,050 | $90,000 | $130,000 |
| 59 | Concrete Right of Way Markers Type H (High) (625.03) | EACH | 4 | $896.49 | $1,000.00 | $2,450.00 |
| 60 | Steel Pin and Cap Right of Way Markers (625.05) | EACH | 18 | $459.38 | $200.00 | $175.00 |
| 61 | (627.50140008) | 829 | $11.41 | $5.00 | $8.00 | |
| 62 | Concrete Cylinder Curing Equipment (637.04) | EACH | 2 | $239.80 | $250.00 | $400.00 |
| 63 | Engineer’s Field Office – Type 1 (637.11) | MONTH | 24 | $1,798.50 | $1,600.00 | $2,600.00 |
| 64 | Office Technology and Supplies (637.34) | DOL | 200 | $1.00 | $1.00 | $1.00 |
| 65 | Construction Testing supplies – Consumables (637.36) | DOL | 200 | $1.00 | $1.00 | $1.00 |
| 66 | White Paint Reflectorized Pavement Stripes – 20 mils (640.20) | LF | 681 | $1.66 | $6.00 | $1.60 |
| 67 | Yellow Paint Reflectorized Pavement Stripes - 20 mils (640.21) | LF | 324 | $1.66 | $6.00 | $1.60 |
| 68 | (650.1254) | LF | 196 | $1,064.69 | $100.00 | $5,000.00 |
| 69 | Welded Frame & Rectangular Grate 3 (655.1003) | EACH | 1 | $2,074.75 | $1,500.00 | $2,500.00 |
| 70 | White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102) | LF | 974 | $7.72 | $5.00 | $7.40 |
| 71 | Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202) | LF | 375 | $7.72 | $5.00 | $7.40 |
| 72 | Field Change Payment (FCP) (697.03) | DOL | 121,100 | $1.00 | $1.00 | $1.00 |
| 73 | Asphalt Price Adjustment (698.04) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 74 | Fuel Price Adjustment (698.05) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 75 | Steel/Iron Price Adjustment (698.06) | DOL | 100 | $1.00 | $1.00 | $1.00 |
| 76 | Mobilization (699.040001) | LS | 1 | $70,000 | $90,000 | $151,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.
Every contract let that day: NYSDOT letting of February 20, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.