NYSDOT letting results, December 14, 2023
18 contracts let by New York State DOT on December 14, 2023, $122,615,877 in low bids, a median of 3 bidders per contract.
- Owner
- New York State DOT
- Contracts
- 18
- Low bids, total
- $122,615,877
- Data through
- 15 OCT 2026
Contracts let that day
| Contract | Project | Region | Bids | Low bidder | Low bid | Second bid | Gap | Source |
|---|---|---|---|---|---|---|---|---|
| D265151 | Highway Improvements & Bridge Replacement - US Rte. 20 | Region 05 | 4 | Union Concrete & Construction Corp | $48,450,047 | $49,501,441 | +2.0% | NYSDOT |
| D265125 | ROUTE 22 PAVING PUTNAM AND DUTCHESS COUNTIES | Region 08 | 3 | Tilcon New York Inc | $14,864,000 | $16,333,642 | +10% | NYSDOT |
| D265140 | Bridge Expansion Joint Repairs and Replacements in NYC | Region 11 | 5 | Constar Inc | $10,558,735 | $10,877,828 | +3.0% | NYSDOT |
| D265130 | NYS RT 27 Median Barrier Replacement, Suffolk County. | Region 10 | 10 | Posillico Civil Inc | $8,776,207 | $8,800,000 | 0.0% | NYSDOT |
| D265078 | 2024 Pavement Markings Requirements Contract | Region 10 | 2 | Safety Marking LLC | $8,243,010 | $13,987,231 | +70% | NYSDOT |
| D265128 | PAVEMENT MARKING PROJECT 23 | Region 02 | 2 | Accent Stripe Inc | $4,889,453 | $5,846,222 | +20% | NYSDOT |
| D265143 | RTE 46 OVER ONEIDA CREEK BRIDGE REPLACEMENT | Region 02 | 5 | Tioga Construction Company Inc | $4,385,014 | $4,451,317 | +2.0% | NYSDOT |
| D265157 | Bridge Rehab - NY 248 over Bennett's Creek/Sugar Creek | Region 06 | 3 | The L C Whitford Co Inc | $4,288,887 | $4,430,000 | +3.0% | NYSDOT |
| D265090 | Sign Panel Replacements at Rte-9A, BQE, LIE and GCP | Region 11 | 6 | Constar Inc | $3,443,410 | $3,784,122 | +10% | NYSDOT |
| D265137 | Regional Graffiti Removal Contract | Region 08 | 1 | Morano Brothers Corp | $3,343,000 | NYSDOT | ||
| D265133 | RTE 162 OVER CANYON ROAD AND FLAT CREEK DECK REPLACEMENT | Region 02 | 7 | Bette & Cring LLC | $2,839,523 | $3,230,069 | +14% | NYSDOT |
| D265162 | NY RT 104 at NY RT 93 Intersection Improvements | Region 05 | 3 | Concrete Applied Technologies Corp/DBA:Catco | $2,331,340 | $2,416,063 | +4.0% | NYSDOT |
| D265115 | ROUTES 5 & 20 CULVERT IMPROVEMENTS | Region 04 | 3 | Keeler Construction Co Inc | $1,822,598 | $1,970,000 | +8.0% | NYSDOT |
| D265153 | Bridge Washing Contract SFY 2023 | Region 01 | 3 | Fleetwash, Inc. | $998,767 | $1,272,777 | +27% | NYSDOT |
| D265170 | BRIDGE WHERE & WHEN CONTRACT SFY 23-24 & 24-25 | Region 05 | 4 | Union Concrete & Construction Corp | $982,933 | $985,967 | 0.0% | NYSDOT |
| D265149 | Bridge Cleaning & Sealing - SFY 23/24 | Region 05 | 3 | Fleetwash, Inc. | $881,772 | $990,072 | +12% | NYSDOT |
| D265152 | Highway Crack Sealing Regionwide 2024 | Region 04 | 2 | Bothar Construction LLC | $842,842 | $854,712 | +1.0% | NYSDOT |
| D265145 | NHS CULVERT REPAIRS - SFY 2023/24 | Region 06 | 2 | Precision Trenchless LLC | $674,339 | $874,580 | +30% | NYSDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than NYSDOT received, the others did not match their published totals and are left out.