NYSDOT contract D265408 bid tabulation

Pavement Resurfacing with Safety and Improvements. Let by New York State DOT on January 9, 2025, Chautauqua, Region 05. 6 bids received; low bid $3,957,619 by Lake Shore Paving Inc.

Owner
New York State DOT
Letting
09 JAN 2025
Pay items
180
Data through
15 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Lake Shore Paving Inc$3,957,619Low
2McLaughlin Construction Corp/DBA Edbauer Construction$4,192,526+6.0%
3Concrete Applied Technologies Corp/DBA:Catco$4,250,000+7.0%
4D&H Excavating Inc$4,269,278+8.0%
5Oakgrove Construction Inc$4,358,264+10%
6Cold Spring Construction Company$5,295,175+34%
NYSDOT contract D265408: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Lake Shore Paving Inc2. McLaughlin Construction Corp/DBA Edbauer Construction3. Concrete Applied Technologies Corp/DBA:Catco4. D&H Excavating Inc5. Oakgrove Construction Inc6. Cold Spring Construction Company
1Clearing and Grubbing (201.06)LS1$5,461.00$58,500$8,500.00$8,000.00$25,000$25,000
2Unclassified Excavation and Disposal (203.02)CY437$27.55$150.00$93.00$100.00$60.00$125.00
3Select Granular Fill (203.07)CY133$103.65$110.00$75.00$110.00$90.00$120.00
4Controlled Low Strength Material (CLSM) (204.01)CY15$429.35$350.00$300.00$660.00$400.00$500.00
5 (205.0201)LS1$1,098.75$250.00$2,200.00$2,500.00$1,000.00$1.00
6Field Organic Vapor Monitoring of Contaminated Soil (205.03)HR8$185.70$10.00$115.00$170.00$150.00$100.00
7Petroleum Contamination Parameter Analysis (205.0401)EACH2$359.45$10.00$300.00$140.00$350.00$200.00
8Laboratory Analysis for Hazardous Waste RCRA Toxicity Characteristic (205.0402)EACH1$1,042.40$50.00$200.00$850.00$800.00$750.00
9Laboratory Analysis for Ignitability (205.0403)EACH1$39.54$10.00$60.00$60.00$50.00$50.00
10Laboratory Analysis for ph (205.0404)EACH1$19.20$10.00$30.00$30.00$30.00$40.00
11Laboratory Analysis for Polychlorinated Biphenyls (PCB's) (205.0405)EACH1$110.25$10.00$100.00$95.00$125.00$100.00
12Laboratory Analysis for Total Petroleum Hydrocarbons– Gasoline Range Organics (205.0406)EACH1$95.85$10.00$115.00$85.00$120.00$100.00
13Laboratory Analysis for Total Petroleum Hydrocarbons– Diesel Range Organics (205.0407)EACH1$125.80$20.00$100.00$115.00$130.00$100.00
14 (205.050201)TON24$88.90$25.00$90.00$150.00$80.00$100.00
15Trench and Culvert Excavation (206.0201)CY232$56.65$45.00$83.00$100.00$65.00$50.00
16 (206.03050005)327$94.65$120.00$165.00$118.00$85.00$100.00
17 (206.03060005)384$31.15$62.00$57.20$60.00$30.00$100.00
18Test Pit Excavation (206.05)EACH3$1,073.50$5,000.00$2,750.00$1,100.00$2,000.00$2,500.00
19Seed and Mulch – Temporary (209.1003)SY365$6.20$0.25$1.10$1.50$1.00$6.00
20Check Dam (Ditch Bottom Width >6′ to 10′), Gravel Bag – Temporary (209.110203)EACH1$2,604.60$850.00$1,100.00$100.00$750.00$1,000.00
21Stabilized Construction Access (209.22)SY631$35.75$5.00$30.00$0.01$50.00$50.00
22 (209.23010009)1,110$8.85$0.01$5.00$7.50$5.00$5.00
23 (304.15200005)178$106.10$150.00$120.00$135.00$150.00$275.00
24 (404.0001)TON316$100.00$100.00$100.00$100.00$100.00$100.00
25Pavement Density Quality Adjustment to Asphalt Items (404.0002)QUALITY UNIT1$100.00$100.00$100.00$100.00$100.00$100.00
26Longitudinal Joint Density Quality Adjustment to Asphalt Items (404.0003)QUALITY UNIT222$100.00$100.00$100.00$100.00$100.00$100.00
27 (404.0962)TON5,924$116.30$112.00$115.00$107.00$110.00$125.00
28 (404.0982)TON242$198.50$332.00$270.00$272.00$275.00$300.00
29 (404.1989)TON25$214.50$374.00$335.00$285.00$275.00$350.00
30 (404.3789)TON81$185.20$306.00$300.00$265.00$200.00$225.00
31Diluted Tack Coat (407.0102)GAL7,325$5.65$6.00$0.10$6.00$4.00$10.00
32Asphalt Pavement Joint Adhesive (418.7603)LF71,021$0.30$0.05$0.05$0.40$0.25$1.00
33Production Cold Milling of Bituminous Concrete (490.10)SY70,206$2.05$2.50$2.30$1.80$2.00$2.00
34Miscellaneous Cold Milling of Bituminous Concrete (490.30)SY2,866$14.15$18.00$12.00$14.00$15.00$25.00
35Shields and Shoring (552.17)SF2,441$2.20$0.50$0.30$1.50$3.00$0.01
36 (553.030001)EACH1$14,180$100.00$1,000.00$100.00$1,500.00$25,000
37 (603.172512)EACH2$7,452.25$7,310.00$8,100.00$8,300.00$6,500.00$7,500.00
38Concrete Collars (603.77)EACH7$890.00$1,346.00$2,100.00$1,800.00$4,000.00$2,500.00
39 (603.9818)LF18$43.75$280.00$130.00$130.00$400.00$275.00
40 (603.9824)LF28$59.35$320.00$105.00$135.00$300.00$200.00
41 (603.9830)LF21$146.25$360.00$67.00$200.00$250.00$225.00
42 (604.070501)EACH69$677.75$1,043.00$650.00$1,050.00$500.00$750.00
43 (604.070502)EACH18$1,772.75$3,450.00$3,000.00$2,700.00$6,000.00$6,000.00
44 (604.070503)EACH3$2,507.00$4,550.00$4,000.00$5,000.00$9,000.00$10,000
45 (604.500101)LF21$650.65$1,087.00$600.00$615.00$750.00$1,250.00
46 (604.500102)LF22.40$783.80$1,317.00$820.00$705.00$950.00$1,250.00
47Underdrain Filter, Type II (605.1001)CY8$122.90$125.00$42.00$120.00$150.00$375.00
48 (605.1501)LF211$2.45$18.00$15.00$15.00$6.00$4.00
49Concrete Sidewalks and Driveways (608.0101)CY20$1,043.60$1,175.00$1,200.00$1,650.00$900.00$1,075.00
50 (608.01060415)1,704$26.90$50.00$33.00$45.00$45.00$50.00
51 (608.01060615)367$35.00$48.00$37.00$56.00$45.00$60.00
52 (608.01070415)3,264$37.90$50.00$35.00$77.00$45.00$50.00
53 (608.01070615)553$53.55$48.00$80.00$95.00$45.00$60.00
54Asphalt Sidewalks, Driveways, Bicycle Paths, and Vegetation Control Strips (608.020102)TON19$266.90$450.00$450.00$265.00$250.00$550.00
55 (608.03040008)31$81.90$200.00$230.00$150.00$350.00$600.00
56Surface-Applied Detectable Warning Units (608.20)SY2$810.25$550.00$1,100.00$475.00$500.00$1,000.00
57 (608.21000003)2$617.00$550.00$1,100.00$615.00$500.00$875.00
58 (609.10010109)899$95.75$108.00$100.00$120.00$80.00$150.00
59Topsoil - Roadside (610.1402)CY247$125.80$88.00$90.00$95.00$65.00$125.00
60Turf Establishment - Roadside (610.1601)SY2,196$3.75$0.10$2.00$3.00$3.00$5.00
61Watering Vegetation (610.19)1,000 GALLONS23$275.00$10.00$185.00$1.00$100.00$250.00
62 (611.0151)EACH4$1,479.75$1,462.00$1,400.00$1,400.00$750.00$1,300.00
63 (611.0432)EACH57$209.70$212.00$200.00$200.00$100.00$185.00
64 (611.0442)EACH14$209.70$212.00$200.00$200.00$125.00$185.00
65 (611.19010024)4$262.40$100.00$250.00$250.00$220.00$200.00
66 (611.19040024)71$57.50$50.00$54.00$55.00$35.00$50.00
67 (614.060104)EACH8$423.75$500.00$360.00$300.00$500.00$1,000.00
68 (614.060204)EACH5$678.00$500.00$890.00$900.00$500.00$1,500.00
69 (614.060404)EACH2$2,707.20$2,400.00$2,900.00$2,200.00$2,500.00$2,500.00
70 (617.10000024)15$70.00$25.00$80.00$40.00$100.00$0.01
71 (617.11000024)LS1$282.20$50.00$1,200.00$1.00$1,000.00$0.01
72Basic Work Zone Traffic Control (619.01)LS1$137,434$200,972$365,000$123,057$468,000$500,000
73 (619.0901)LF44,860$0.50$0.33$0.32$0.55$0.35$0.30
74 (619.111113)EACH2$9,735.00$18,000$6,000.00$5,700.00$7,500.00$24,450
75Maintain Traffic Signal Equipment (Requirement A) Intersection (619.1611)MONTH48$119.80$10.00$10.00$170.00$100.00$300.00
76Stone Filling (Medium) (620.04)CY252$203.00$95.00$106.00$160.00$150.00$150.00
77Bedding Material, Type 1 (620.0801)CY35$126.60$110.00$95.00$135.00$120.00$110.00
78Survey Operations (625.01)LS1$40,000$45,000$102,000$62,000$12,000$100,000
79Concrete Right of Way Markers Type H (High) (625.03)EACH6$839.00$1,046.00$705.00$960.00$600.00$500.00
80Concrete Right of Way Markers Type L (Low) (625.04)EACH2$718.00$1,026.00$430.00$930.00$500.00$500.00
81Steel Pin and Cap Right of Way Markers (625.05)EACH6$180.00$278.00$480.00$425.00$150.00$250.00
82Permanent Survey Markers (625.06)EACH8$420.00$1,108.00$2,000.00$1,050.00$1,000.00$1,000.00
83 (625.09010015)LS1$1,000.00$0.01$1,100.00$5,000.00$500.00$1.00
84 (627.50140008)492$8.75$12.00$11.00$10.00$8.00$10.00
85Cleaning, Sealing and/or Filling Joints (633.13)LF1,880$1.60$7.00$1.40$3.00$4.00$1.25
86Removal and Repair of Deteriorated Asphalt Pavement - Less than or equal to 4 Square Yards (633.1401)SY244$109.00$1.00$100.00$105.00$100.00$105.00
87Removal and Repair of Deteriorated Asphalt Pavement – Greater than 4 Square Yards and less than 20 Square Yards (633.1402)SY244$55.50$1.00$78.00$82.00$70.00$95.00
88Removal and Repair of Deteriorated Asphalt Pavement – 20 Square Yards or Greater (633.1403)SY244$48.25$1.00$55.00$60.00$43.00$85.00
89 (634.06000008)1$817.00$496.00$555.00$420.00$1,000.00$500.00
90 (634.06010007)3$1,150.00$1,200.00$1,200.00$1,150.00$2,000.00$1,500.00
91Concrete Cylinder Curing Equipment (637.04)EACH1$2,895.00$1.00$4,000.00$120.00$2,000.00$500.00
92Engineer’s Field Office – Type 2 (637.12)MONTH12$3,175.00$2,400.00$2,500.00$2,150.00$2,000.00$2,500.00
93Office Technology and Supplies (637.34)DOL500$1.00$1.00$1.00$1.00$1.00$1.00
94White Paint Reflectorized Pavement Stripes – 15 mils (640.10)LF18,058$0.42$0.33$0.32$0.35$0.35$0.30
95Yellow Paint Reflectorized Pavement Stripes - 15 mils (640.11)LF27,396$0.42$0.33$0.32$0.35$0.35$0.30
96Ground-Mounted Sign Panels without Z-bars (645.5101)SF132$39.55$37.00$71.00$38.00$35.00$35.00
97Ground-Mounted Sign Panels less than or equal to 32 SF with Z-bars (645.5102)SF1,894$41.95$38.00$40.00$40.00$40.00$40.00
98Type A Sign Posts (645.81)EACH351$203.70$185.00$207.00$190.00$185.00$180.00
99 (645.81090003)194$73.10$70.00$78.00$70.00$75.00$65.00
100Pole-Mounted Sign Support System (Band Mounting) (645.85)EACH6$354.65$322.00$290.00$335.00$150.00$325.00
101Reference Marker Panel (646.21)EACH58$47.95$44.00$40.00$45.00$35.00$50.00
102Steel Post, 2.0 lb/ft (646.32)EACH58$90.00$85.00$94.00$85.00$100.00$100.00
103Flexible Delineator, Single Unit, One Way (646.40)EACH24$174.00$158.00$189.00$165.00$150.00$150.00
104Remove and Dispose Signs, Ground Mounted Type A Sign Supports and Foundations - Size I (Under 30 Square Feet) (647.61)EACH195$43.15$39.00$6.90$42.00$25.00$40.00
105 (647.83001002)58$12.00$12.00$5.25$11.00$25.00$25.00
106 (650.1272)LF123$4,425.00$4,000.00$3,900.00$4,715.00$5,000.00$5,250.00
107Welded Frame & Reticuline Grate 3 (655.1103)EACH3$1,787.15$2,262.00$1,600.00$2,250.00$2,000.00$2,500.00
108Welded Frame & Reticuline Grate 11 (655.1111)EACH4$1,895.00$2,353.00$1,600.00$2,550.00$2,000.00$2,500.00
109Welded Frame & Reticuline Grate 16 (655.1116)EACH1$1,549.00$2,339.00$1,400.00$3,300.00$1,500.00$2,500.00
110 (661.01000108)LS1$2,223.00$2,800.00$7,150.00$2,900.00$2,000.00$2,000.00
111 (662.60000108)2,500$1.00$1.00$1.00$1.00$1.00$1.00
112 (662.60000208)2,500$1.00$1.00$1.00$1.00$1.00$1.00
113 (662.60000308)2,500$1.00$1.00$1.00$1.00$1.00$1.00
114 (662.60000408)2,500$1.00$1.00$1.00$1.00$1.00$1.00
115 (662.60000508)2,500$1.00$1.00$1.00$1.00$1.00$1.00
116Adjust Existing Valve Box Elevation (663.33)EACH1$420.00$1,150.00$900.00$800.00$250.00$750.00
117Adjust Existing Hydrant Elevation (663.34)EACH1$1,237.00$2,750.00$2,000.00$2,500.00$3,500.00$3,000.00
118 (670.92020004)1$2,076.50$2,800.00$5,335.00$2,900.00$2,000.00$3,000.00
119 (680.05010007)4$22,765$22,000$28,600$22,200$20,000$22,500
120 (680.05020007)4$4,074.00$3,807.00$5,225.00$4,000.00$3,500.00$5,000.00
121 (680.11120814)1$16,115$9,800.00$8,250.00$10,250$15,000$15,000
122 (680.11131014)2$13,817$6,500.00$8,800.00$6,800.00$12,000$15,000
123Pole Excavation and Concrete Foundation (680.5001)CY3$5,392.00$2,800.00$4,290.00$2,800.00$6,500.00$5,000.00
124Concrete Base for Controller Cabinet (680.5002)EACH3$3,834.00$9,200.00$5,720.00$9,600.00$3,500.00$3,500.00
125 (680.50500005)5$1,006.50$10.00$10.00$510.00$900.00$400.00
126 (680.51020009)1$1,264.00$490.00$1,375.00$510.00$1,200.00$2,000.00
127 (680.510201)EACH2$2,206.00$1,904.00$2,475.00$2,000.00$2,000.00$2,650.00
128 (680.51030009)1$976.50$600.00$1,650.00$625.00$1,000.00$1,000.00
129 (680.510301)EACH10$2,593.00$2,056.00$2,915.00$2,150.00$2,500.00$2,750.00
130 (680.510401)EACH1$3,377.55$2,448.00$3,520.00$2,550.00$3,000.00$3,000.00
131 (680.520105)LF59$26.95$20.00$56.10$17.00$25.00$25.00
132 (680.520506)LF78$43.15$20.00$28.60$16.00$40.00$35.00
133 (680.520508)LF1,227$13.20$24.00$14.30$25.00$12.00$40.00
134Single Span Wire Assembly (680.7001)EACH4$5,014.25$2,122.00$3,850.00$2,200.00$4,500.00$5,500.00
135Riser Assembly, 1-inch Diameter (680.700603)EACH5$2,009.25$1,578.00$1,100.00$1,650.00$2,000.00$2,000.00
136 (680.730514)LF5,228$3.30$5.44$5.12$5.50$3.00$6.00
137 (680.730714)LF903$4.80$6.54$5.89$6.50$5.00$9.00
138 (680.77000105)1$1,387.00$5,400.00$4,615.00$5,600.00$1,200.00$6,000.00
139 (680.77000205)1$1,387.00$5,400.00$4,615.00$5,600.00$1,200.00$6,000.00
140 (680.77000305)1$1,387.00$5,400.00$4,615.00$5,600.00$1,200.00$6,000.00
141 (680.77000405)1$1,387.00$5,400.00$4,615.00$5,600.00$1,200.00$6,000.00
142 (680.78010005)3$801.00$544.00$1,430.00$570.00$750.00$1,250.00
143 (680.78040005)2$2,502.00$2,800.00$3,025.00$5,600.00$2,250.00$2,000.00
144 (680.79000105)1$1,378.00$5,400.00$6,265.00$5,600.00$1,200.00$6,500.00
145 (680.79000205)1$1,378.00$5,400.00$6,265.00$5,600.00$1,200.00$6,500.00
146 (680.79000305)1$1,378.00$5,400.00$6,265.00$5,600.00$1,200.00$6,500.00
147 (680.79000405)1$1,378.00$5,400.00$6,265.00$5,600.00$1,200.00$6,500.00
148 (680.79000505)1$3,955.00$3,808.00$6,265.00$4,000.00$1,200.00$6,500.00
149 (680.80324515)4$2,486.15$3,209.00$3,740.00$3,300.00$2,500.00$4,500.00
150 (680.80324708)3$1,630.00$1,686.00$1,760.00$1,750.00$1,500.00$3,000.00
151 (680.80620215)1$1,529.00$1,904.00$7,095.00$2,000.00$1,500.00$6,500.00
152Traffic Signal Module - 12-inch, Red Ball, LED (680.810101)EACH28$92.25$110.00$148.50$110.00$85.00$200.00
153Traffic Signal Module - 12-inch, Red Arrow, LED (680.810102)EACH4$99.50$132.00$154.00$135.00$85.00$200.00
154Traffic Signal Module - 12-inch, Yellow Ball, LED (680.810103)EACH28$95.85$132.00$148.50$135.00$85.00$200.00
155Traffic Signal Module - 12-inch, Yellow Arrow, LED (680.810104)EACH12$99.45$142.00$154.00$145.00$85.00$200.00
156Traffic Signal Module - 12-inch, Green Ball, LED (680.810105)EACH28$95.85$142.00$148.50$145.00$85.00$200.00
157Traffic Signal Module - 12-inch, Green Arrow, LED (680.810106)EACH8$99.45$152.00$154.00$160.00$85.00$200.00
158Traffic Signal Section - Polycarbonate, Type I, 12-inch (680.810601)EACH108$221.65$110.00$159.50$110.00$100.00$200.00
159Traffic Signal Bracket Assembly - 1 Way (680.8111)EACH32$599.00$479.00$412.50$500.00$500.00$650.00
160Traffic Signal Disconnect Hanger (680.8120)EACH32$883.00$599.00$522.50$625.00$800.00$1,000.00
161 (680.8205)EACH8$1,264.00$816.00$1,001.00$850.00$1,200.00$1,250.00
162 (680.82250801)5$1,709.75$599.00$577.50$625.00$1,500.00$500.00
163 (680.82254110)1$10,110$16,000$16,445$15,800$10,000$10,000
164 (680.82254210)1$7,956.00$16,000$16,445$15,800$8,000.00$10,000
165 (680.83010005)500$15.30$5.00$2.00$4.50$15.00$5.00
166Meter Pan (680.9402)EACH5$1,553.00$25.00$935.00$20.00$1,500.00$2,000.00
167Install Electrical Disconnect/Generator Transfer Switch (680.9499)EACH5$625.50$2,200.00$935.00$2,250.00$600.00$2,000.00
168 (680.950106)LF497$12.00$5.00$3.30$5.00$10.00$10.00
169Performance Concrete Quality Adjustment (680.99)QUALITY UNIT1$10.00$10.00$10.00$10.00$10.00$10.00
170White Epoxy Reflectorized Pavement Stripes - 20 mil (685.1102)LF18,608$0.75$0.54$0.54$0.60$0.50$0.55
171Yellow Epoxy Reflectorized Pavement Stripes - 20 mil (685.1202)LF27,477$0.75$0.54$0.54$0.60$0.50$0.55
172White Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3104)LF21,108$3.37$3.20$3.25$3.40$3.00$3.00
173Yellow Epoxy Reflectorized Pavement Special Stripes - 20 mil Portable/Hand Application (685.3204)LF3,804$3.37$3.20$3.25$3.40$3.00$3.00
174White Epoxy Reflectorized Pavement Letters - 20 mil Portable/Hand Application (685.3304)EACH6$71.90$80.00$75.00$80.00$75.00$75.00
175White Epoxy Reflectorized Pavement Symbols - 20 mil Portable/Hand Application (685.3404)EACH156$317.50$220.00$219.00$230.00$200.00$205.00
176Field Change Payment (FCP) (697.03)DOL180,000$1.00$1.00$1.00$1.00$1.00$1.00
177Asphalt Price Adjustment (698.04)DOL11,295$1.00$1.00$1.00$1.00$1.00$1.00
178Fuel Price Adjustment (698.05)DOL2,675$1.00$1.00$1.00$1.00$1.00$1.00
179Steel/Iron Price Adjustment (698.06)DOL100$1.00$1.00$1.00$1.00$1.00$1.00
180Mobilization (699.040001)LS1$135,000$161,000$152,971$162,000$167,625$201,999
NYSDOT contract D265408: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from NYSDOT's tabulation for this contract. NYSDOT construction bid tabulation PDFs (vendor ranking and spread report), one per contract, January 2022 to October 2026. NYSDOT prints pay item numbers without descriptions or units, so items are found by number. For A+B contracts the item total is kept and the time part dropped.

Every contract let that day: NYSDOT letting of January 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy