NYSDOT letting results, July 7, 2022
11 contracts let by New York State DOT on July 7, 2022, $50,768,879 in low bids, a median of 3 bidders per contract.
- Owner
- New York State DOT
- Contracts
- 11
- Low bids, total
- $50,768,879
- Data through
- 15 OCT 2026
Contracts let that day
| Contract | Project | Region | Bids | Low bidder | Low bid | Second bid | Gap | Source |
|---|---|---|---|---|---|---|---|---|
| D264756 | Bridge Preservation, Northern counties in NYSDOT Region-1 | Region 01 | 3 | Reale Construction Co Inc | $11,976,000 | $12,529,238 | +5.0% | NYSDOT |
| D264835 | Drainage, Culvert, Road work SR60, Pomfret, NY | Region 05 | 5 | McLaughlin Construction Corp/DBA Edbauer Construction | $8,932,408 | $9,548,811 | +7.0% | NYSDOT |
| D264814 | Intersection Improvements US 62 AT WARD ROAD AND WITMER ROAD | Region 05 | 2 | McLaughlin Construction Corp/DBA Edbauer Construction | $7,090,226 | $9,132,001 | +29% | NYSDOT |
| D264787 | Rustic Rail Replacement, Varied State highways, NYSDOT R-8 | Region 08 | 2 | Elderlee Inc | $5,703,370 | $6,498,752 | +14% | NYSDOT |
| D264834 | MAINTENANCE CLEANING OF VARIOUS HIGHWAYS IN NYC | Region 11 | 5 | H & L Contracting LLC | $4,094,910 | $4,629,000 | +13% | NYSDOT |
| D264829 | NY 21 Over Cohocton River Bridge Replacement | Region 06 | 5 | Ramsey Constructors Inc | $2,877,305 | $2,929,749 | +2.0% | NYSDOT |
| D264815 | LARGE CULVERT REPLACEMENT AND REHABILITATIONS NYSDOT R-5 | Region 05 | 5 | Union Concrete & Construction Corp | $2,826,222 | $2,853,906 | +1.0% | NYSDOT |
| D264807 | OVERHEAD SIGN STRUCTURE NYSDOT Region-2 | Region 02 | 3 | Elderlee Inc | $2,516,324 | $2,898,822 | +15% | NYSDOT |
| D264831 | CRACK SEAL & MASTIC NYSDOT R-8 , VARIOUS LOCATIONS | Region 08 | 1 | Bothar Construction LLC | $2,127,797 | NYSDOT | ||
| D264828 | STANDBY STRUCTURES REPAIR FOR 2022 TO 2025 | Region 04 | 2 | The L C Whitford Co Inc | $1,380,000 | $1,396,451 | +1.0% | NYSDOT |
| D264820 | IMPROVEMENTS TO SOUTH FERRY DOCK | Region 10 | 2 | H & L Contracting LLC | $1,244,317 | $1,498,765 | +20% | NYSDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than NYSDOT received, the others did not match their published totals and are left out.